Workers P and Q can complete a task in 16 days if working together. P alone takes 24 days. If P and Q start the task together, but Q leaves after 4 days, how many more days will P alone take to finish the work?
18 days
P and Q's combined 1-day work \(= \frac{1}{16}\).
P's 1-day work \(= \frac{1}{24}\).
Work done together in 4 days \(= 4 \times \frac{1}{16} = \frac{1}{4}\).
Remaining work \(= 1 - \frac{1}{4} = \frac{3}{4}\).
Days needed by P alone to finish remaining work \(= \frac{3}{4} \div \frac{1}{24} = \frac{3}{4} \times 24 = 18\) days.
Hence, P alone will take 18 more days to finish the work.
Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?
A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?
Had been one menless, then the number of days required to do a piece of work would have been one more. If the number of Man. Days required to complete the work is 56, how many workers were there?
A can do a piece of work in 16 hours, B and C can do it in 8 hours while A and C can do it 12 hours. How long will B alone take to do it?