All Exams Test series for 1 year @ ₹349 only
Question

A and B working alone can finish a task in 12 and 16 days respectively. In how many days can the task be finished if they work for one day each alternatively, and A begins the work?

This question was previously asked in
RRB NTPC 2019 CBT 1 Question Paper PDF (31-Jan-2021) (Shift 1)
The correct answer is
$13\frac{2}{3}$ days

Here's how to solve the problem step-by-step:

1. Calculate Individual Work Rates

  • A's rate: If A finishes the task in 12 days, A completes $\frac{1}{12}$ of the task per day.
  • B's rate: If B finishes the task in 16 days, B completes $\frac{1}{16}$ of the task per day.

2. Calculate Work Done in a 2-Day Cycle

Since they work alternatively and A starts:

  • Day 1: A works, completes $\frac{1}{12}$.
  • Day 2: B works, completes $\frac{1}{16}$.
  • Work done in 2 days = Work by A + Work by B
  • Work = $\frac{1}{12} + \frac{1}{16}$
  • To add these fractions, find a common denominator (LCM of 12 and 16 is 48):
  • Work = $\frac{4}{48} + \frac{3}{48} = \frac{7}{48}$ of the task.

3. Determine Full Cycles Completed

We need to find how many 2-day cycles are needed to complete the task. Calculate the number of cycles ($k$) so that the work done is close to 1 (the whole task).

  • Work per cycle = $\frac{7}{48}$.
  • Let's estimate $k$. Total work needed is 1. $1 \div \frac{7}{48} = \frac{48}{7} \approx 6.85$. This suggests around 6 full cycles.
  • Work done in 6 cycles = $6 \times \frac{7}{48} = \frac{42}{48} = \frac{7}{8}$ of the task.
  • Number of days passed = $6 \text{ cycles} \times 2 \text{ days/cycle} = 12$ days.

4. Calculate Remaining Work

After 12 days, the remaining work is:

  • Remaining Work = $1 - \frac{7}{8} = \frac{1}{8}$ of the task.

5. Calculate Time for Remaining Work

The 13th day begins, and A starts working:

  • Work done by A on Day 13 = $\frac{1}{12}$.
  • Total work completed after 13 days = Work after 12 days + Work on Day 13
  • Total Work = $\frac{7}{8} + \frac{1}{12} = \frac{21}{24} + \frac{2}{24} = \frac{23}{24}$ of the task.
  • Remaining work after Day 13 = $1 - \frac{23}{24} = \frac{1}{24}$ of the task.

The 14th day begins, and it's B's turn:

  • B's rate = $\frac{1}{16}$ per day.
  • Time needed for B to complete the remaining $\frac{1}{24}$ work = $\frac{\text{Remaining Work}}{\text{B's Rate}}$
  • Time = $\frac{1/24}{1/16} = \frac{1}{24} \times 16 = \frac{16}{24} = \frac{2}{3}$ days.

6. Calculate Total Time

Total time = Days from full cycles + Day 13 + Fractional day on Day 14

  • Total Time = $12 \text{ days} + 1 \text{ day} + \frac{2}{3} \text{ days}$
  • Total Time = $13 \frac{2}{3}$ days.
Was this answer helpful?

Similar Questions

  1. John, Johnny and Janardan can finish a task in a field in 6, 12, and 24 days, respectively. In how many days will they finish the task working together?
  2. Narendra finishes a job in 10 days. Amit completes the same job in 12 days. How many days will it take for both of them to finish the job while working together?
  3. Sita can clean a hotel in 20 days. Rita can clean the same hotel in 30 days. How many days will they take to clean the hotel together?
  4. A, B and C can complete a task in 36, 54 and 72 days respectively. Together they started the task but A left 8 days before the completion of the task while B left 12 days before the completion. The number of days for which C worked is:
  5. A alone can complete $\frac{2}{5}$ of a task in 12 days, while B alone can complete $\frac{3}{4}$ of the same task in 25 days. In how many days can they complete the task if they work together?
  6. If A, B and C can complete a task alone in 15 days, 20 days and 25 days, respectively, then in how many days can they complete the same task if they work together?
  7. Reena and Jaya can complete a piece of work in 6 days and Jaya alone can complete it in 8 days. In how many days can Reena alone complete it?
  8. 12 people can sweep the floor in 4 days with 12 brooms. In how many days can 8 people sweep the floor with 8 brooms?
  9. X can work as fast as Y and Z together. X and Y together can finish the same task 3 times as fast as Z. If all three working together can finish the task in 15 days, how many days, will Z take to finish the task?
  10. 18 skilled workers can complete a task in 12 days while 24 semi-skilled workers need 15 days to complete the same task. 12 skilled workers started the task but 3 of them left after a few days. How many semi-skilled workers should replace the 3 skilled ones who left so that the task can be completed in stipulated time?

Important Questions from Time and Work

  1. A works thrice as fast as B. If B can complete a work in 256 days independently, then find the number of days in which A and B can together
    finish the work.
  2. A can finish a job in 146 days, B can finish the same job in 219 days and C can finish the same job in 292 days. If all three are working together, how many days will they require to complete the same job?
  3. X can finish a work in 153 days, Y can finish a work in 255 and Z can finish the same piece of work 340 days. How many days will they require to complete the work, if X, Y and Z are working together?
  4. A finish a work in 1170 days and B can do the same work in 2340 days. Working together, they will complete the same work in how many days?
  5. A can finish a job in 102 days, B can finish the same job in 153 days and C can finish the same job in 204 days. If all three are working together, how many days will they require to complete the same job?
Need Expert Advice?
Upcoming Exams
RRB Staff Nurse
November 23, 2026
RRB Paramedical
November 23, 2026
Test Series
RRB NTPC img
Railways
RRB NTPC Under Graduate 2026 New Mock Test Series
1612 Tests 1 Tests Free
1334 Attempts
4.3(521)
English, Hindi, Telugu +7 More
More Questions from RRB NTPC

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App