All Exams Test series for 1 year @ ₹349 only
Question

lf 12 men can do a work in 20 days, in how many days will the work be done by 15 men-

The correct answer is

16

Understanding Work and Time Problems

Work and time problems are fundamental concepts in quantitative aptitude, frequently appearing in various competitive examinations. These problems involve a direct or inverse relationship between the number of workers, the time taken, and the amount of work completed. The key is to understand how these quantities interact.

Men and Days Relationship

In this specific problem, we are comparing the time taken by two different groups of men to complete the same work. When the amount of work remains constant, the number of men and the number of days required to complete the work are inversely proportional. This means:

  • If the number of men increases, the number of days required to complete the work will decrease.
  • If the number of men decreases, the number of days required to complete the work will increase.

This inverse relationship is crucial for solving such problems accurately.

Calculating Total Work Done

The total work done is considered constant in such scenarios. We can represent this constant work as the product of the number of men and the number of days they work. Let:

  • \(M_1\) = Initial number of men
  • \(D_1\) = Initial number of days
  • \(M_2\) = New number of men
  • \(D_2\) = New number of days

Since the total work remains the same, we can establish the following relationship:

$$M_1 \times D_1 = M_2 \times D_2$$

This formula allows us to find an unknown variable when the other three are known.

Applying Values to the Problem

Let's extract the given information from the question:

Description Value
Initial number of men (\(M_1\)) 12 men
Initial number of days (\(D_1\)) 20 days
New number of men (\(M_2\)) 15 men
New number of days (\(D_2\)) ? (To be calculated)

Solving for Days

Now, we will substitute these values into our inverse proportion formula:

$$M_1 \times D_1 = M_2 \times D_2$$

Substituting the given values:

$$12 \text{ men} \times 20 \text{ days} = 15 \text{ men} \times D_2 \text{ days}$$

First, calculate the product on the left side, which represents the total work units:

$$12 \times 20 = 240$$

So, the total work is 240 "man-days". Now, we set this equal to the work done by 15 men in \(D_2\) days:

$$240 = 15 \times D_2$$

To find the number of days (\(D_2\)), we need to isolate \(D_2\) by dividing 240 by 15:

$$D_2 = \frac{240}{15}$$

Performing the division:

$$D_2 = 16$$

Therefore, 15 men will complete the same work in 16 days.

Was this answer helpful?

Important Questions from Time and Work

  1. Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?

  2. A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?

  3. Had been one menless, then the number of days required to do a piece of work would have been one more. If the number of Man. Days required to complete the work is 56, how many workers were there?

  4. A can do a piece of work in 16 hours, B and C can do it in 8 hours while A and C can do it 12 hours. How long will B alone take to do it?

  5. 'A', 'B' and 'C' can do a piece of work in 20, 30 and 60 days respectively. In how many days, can 'A' do the work if he is assisted by 'B' and 'C' on every third day?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App