lf 12 men can do a work in 20 days, in how many days will the work be done by 15 men-
16
Work and time problems are fundamental concepts in quantitative aptitude, frequently appearing in various competitive examinations. These problems involve a direct or inverse relationship between the number of workers, the time taken, and the amount of work completed. The key is to understand how these quantities interact.
In this specific problem, we are comparing the time taken by two different groups of men to complete the same work. When the amount of work remains constant, the number of men and the number of days required to complete the work are inversely proportional. This means:
This inverse relationship is crucial for solving such problems accurately.
The total work done is considered constant in such scenarios. We can represent this constant work as the product of the number of men and the number of days they work. Let:
Since the total work remains the same, we can establish the following relationship:
$$M_1 \times D_1 = M_2 \times D_2$$
This formula allows us to find an unknown variable when the other three are known.
Let's extract the given information from the question:
| Description | Value |
|---|---|
| Initial number of men (\(M_1\)) | 12 men |
| Initial number of days (\(D_1\)) | 20 days |
| New number of men (\(M_2\)) | 15 men |
| New number of days (\(D_2\)) | ? (To be calculated) |
Now, we will substitute these values into our inverse proportion formula:
$$M_1 \times D_1 = M_2 \times D_2$$
Substituting the given values:
$$12 \text{ men} \times 20 \text{ days} = 15 \text{ men} \times D_2 \text{ days}$$
First, calculate the product on the left side, which represents the total work units:
$$12 \times 20 = 240$$
So, the total work is 240 "man-days". Now, we set this equal to the work done by 15 men in \(D_2\) days:
$$240 = 15 \times D_2$$
To find the number of days (\(D_2\)), we need to isolate \(D_2\) by dividing 240 by 15:
$$D_2 = \frac{240}{15}$$
Performing the division:
$$D_2 = 16$$
Therefore, 15 men will complete the same work in 16 days.
Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?
A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?
Had been one menless, then the number of days required to do a piece of work would have been one more. If the number of Man. Days required to complete the work is 56, how many workers were there?
A can do a piece of work in 16 hours, B and C can do it in 8 hours while A and C can do it 12 hours. How long will B alone take to do it?
'A', 'B' and 'C' can do a piece of work in 20, 30 and 60 days respectively. In how many days, can 'A' do the work if he is assisted by 'B' and 'C' on every third day?