All Exams Test series for 1 year @ ₹349 only
Question

Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?

This question was previously asked in
RBI Assistant Prelims Memory Based Paper (27 March 2022) (Shift 2)
The correct answer is

15/2 days

Work and Time Calculation: Mohan and Sohan's Effort

This question involves calculating the time taken to complete a work when individuals work together and then one leaves. We need to determine how long it takes Sohan to finish the remaining portion of the work.

Understanding Work Rates

First, let's figure out the rate at which each person works. The rate is the amount of work done per day.

  • Mohan completes the work in 10 days. So, Mohan's work rate is $\frac{1}{10}$ of the work per day.
  • Sohan completes the work in 15 days. So, Sohan's work rate is $\frac{1}{15}$ of the work per day.

Combined Work Rate

When they work together, their rates add up. The combined work rate is:

Combined Rate = Mohan's Rate + Sohan's Rate

Combined Rate = $\frac{1}{10} + \frac{1}{15}$

To add these fractions, we find a common denominator, which is 30.

Combined Rate = $\frac{3}{30} + \frac{2}{30} = \frac{3+2}{30} = \frac{5}{30} = \frac{1}{6}$ of the work per day.

Work Done Together

Mohan and Sohan worked together for 3 days. The total work done during these 3 days is:

Work Done = Combined Rate $\times$ Number of Days

Work Done = $\frac{1}{6} \times 3 = \frac{3}{6} = \frac{1}{2}$ of the work.

Remaining Work

After 3 days, half of the work is completed. The remaining work is:

Remaining Work = Total Work - Work Done

Remaining Work = $1 - \frac{1}{2} = \frac{1}{2}$ of the work.

Time for Sohan to Finish

Now, Sohan has to complete the remaining half of the work alone. We know Sohan's work rate is $\frac{1}{15}$ of the work per day.

Time Taken = $\frac{\text{Remaining Work}}{\text{Sohan's Work Rate}}$

Time Taken = $\frac{\frac{1}{2}}{\frac{1}{15}}$

To divide fractions, we multiply by the reciprocal of the divisor:

Time Taken = $\frac{1}{2} \times \frac{15}{1} = \frac{15}{2}$ days.

Therefore, Sohan will take $\frac{15}{2}$ days to finish the remaining work.

Was this answer helpful?

Similar Questions

  1. A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?


Important Questions from Time and Work

  1. Surbhi can do a piece of work in 24 days. She completed 3/8 of the work and then left it. Amit can complete the remaining work in 10 days. Working together, they will complete 125% of the same work in:

  2. Rama and Hari can together finish a piece of work in 15 day. Rama works twice as fast as Hari, then Hari alone can finish work in :

  3. Anil, Deepak and Dinesh together can complete a work in 35 days. Anil and Dinesh together can complete the same work in 60 days. In how many days Deepak alone can complete the same work?

  4. Anu is four times as good as Binni in completing a task. Together they finish the same task in 7 hours. In how many hours will Anu alone complete the task?

  5. P, Q and R can complete a work in 10 days, 20 days and 30 days, respectively, working alone. How soon can the work be completed if P is assisted by Q and R on alternate days?

Need Expert Advice?
Upcoming Exams
SBI Clerk
September 16, 2026
IBPS RRB
November 21, 2026
IBPS RRB Clerk
December 06, 2026
Test Series
RBI Assistant img
Banking
RBI Assistant (Pre & mains) 2026 Mock Test Series
190 Tests 1 Tests Free
4677 Attempts
4.7(28)
English, Hindi

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App