A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?
36 hours
This problem involves calculating the time taken by a specific tap (Tap B) to fill a tank, given the combined filling time of multiple taps and the relationships between their speeds.
Let the rate at which each tap fills the tank be represented by $R_A$, $R_B$, and $R_C$ for taps A, B, and C, respectively. The problem states the following relationships:
From the second relationship, we can express the rate of Tap A in terms of Tap B's rate: $R_A = \frac{R_B}{2}$.
All three taps (A, B, and C) together fill the tank in 8 hours. The combined rate of filling is the sum of their individual rates: $R_{Combined} = R_A + R_B + R_C$.
Now, let's express all rates in terms of $R_B$:
Substituting these into the combined rate equation:
$R_{Combined} = \frac{R_B}{2} + R_B + 3 \times R_B$
To add these, we find a common denominator (which is 2):
$R_{Combined} = \frac{R_B}{2} + \frac{2 R_B}{2} + \frac{6 R_B}{2}$
$R_{Combined} = \frac{R_B + 2 R_B + 6 R_B}{2}$
$R_{Combined} = \frac{9 R_B}{2}$
Let the total work (filling one tank) be represented by $W$. The relationship between work, rate, and time is $W = \text{Rate} \times \text{Time}$.
Since the combined rate of taps A, B, and C fills the tank in 8 hours, we have:
$W = R_{Combined} \times 8$
Substitute the combined rate we found:
$W = \left( \frac{9 R_B}{2} \right) \times 8$
$W = 9 \times R_B \times 4$
$W = 36 \times R_B$
This equation tells us that the total work required to fill the tank is equivalent to 36 times the rate of Tap B.
We want to find the time taken by Tap B alone to complete the same work $W$. Let this time be $T_B$. The equation is:
$W = R_B \times T_B$
We already found that $W = 36 \times R_B$. Now we can set the two expressions for $W$ equal to each other:
$R_B \times T_B = 36 \times R_B$
To find $T_B$, we can divide both sides by $R_B$ (assuming $R_B$ is not zero, which is true since it's filling the tank):
$T_B = \frac{36 \times R_B}{R_B}$
$T_B = 36$ hours
Therefore, Tap B alone will take 36 hours to fill the tank.
Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?
Surbhi can do a piece of work in 24 days. She completed 3/8 of the work and then left it. Amit can complete the remaining work in 10 days. Working together, they will complete 125% of the same work in:
Rama and Hari can together finish a piece of work in 15 day. Rama works twice as fast as Hari, then Hari alone can finish work in :
Anil, Deepak and Dinesh together can complete a work in 35 days. Anil and Dinesh together can complete the same work in 60 days. In how many days Deepak alone can complete the same work?
Anu is four times as good as Binni in completing a task. Together they finish the same task in 7 hours. In how many hours will Anu alone complete the task?
P, Q and R can complete a work in 10 days, 20 days and 30 days, respectively, working alone. How soon can the work be completed if P is assisted by Q and R on alternate days?