All Exams Test series for 1 year @ ₹349 only
Question

A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?

This question was previously asked in
RBI Assistant Prelims Memory Based Paper (27 March 2022) (Shift 2)
The correct answer is

36 hours

Tank Filling Time Calculation

This problem involves calculating the time taken by a specific tap (Tap B) to fill a tank, given the combined filling time of multiple taps and the relationships between their speeds.

Understanding Tap Speeds and Relationships

Let the rate at which each tap fills the tank be represented by $R_A$, $R_B$, and $R_C$ for taps A, B, and C, respectively. The problem states the following relationships:

  • Tap C is thrice as fast as Tap B: $R_C = 3 \times R_B$
  • Tap B is twice as fast as Tap A: $R_B = 2 \times R_A$

From the second relationship, we can express the rate of Tap A in terms of Tap B's rate: $R_A = \frac{R_B}{2}$.

Calculating Combined Rate

All three taps (A, B, and C) together fill the tank in 8 hours. The combined rate of filling is the sum of their individual rates: $R_{Combined} = R_A + R_B + R_C$.

Now, let's express all rates in terms of $R_B$:

  • $R_A = \frac{R_B}{2}$
  • $R_B = R_B$
  • $R_C = 3 \times R_B$

Substituting these into the combined rate equation:

$R_{Combined} = \frac{R_B}{2} + R_B + 3 \times R_B$

To add these, we find a common denominator (which is 2):

$R_{Combined} = \frac{R_B}{2} + \frac{2 R_B}{2} + \frac{6 R_B}{2}$

$R_{Combined} = \frac{R_B + 2 R_B + 6 R_B}{2}$

$R_{Combined} = \frac{9 R_B}{2}$

Determining Total Work Done

Let the total work (filling one tank) be represented by $W$. The relationship between work, rate, and time is $W = \text{Rate} \times \text{Time}$.

Since the combined rate of taps A, B, and C fills the tank in 8 hours, we have:

$W = R_{Combined} \times 8$

Substitute the combined rate we found:

$W = \left( \frac{9 R_B}{2} \right) \times 8$

$W = 9 \times R_B \times 4$

$W = 36 \times R_B$

This equation tells us that the total work required to fill the tank is equivalent to 36 times the rate of Tap B.

Calculating Time Taken by Tap B Alone

We want to find the time taken by Tap B alone to complete the same work $W$. Let this time be $T_B$. The equation is:

$W = R_B \times T_B$

We already found that $W = 36 \times R_B$. Now we can set the two expressions for $W$ equal to each other:

$R_B \times T_B = 36 \times R_B$

To find $T_B$, we can divide both sides by $R_B$ (assuming $R_B$ is not zero, which is true since it's filling the tank):

$T_B = \frac{36 \times R_B}{R_B}$

$T_B = 36$ hours

Conclusion

Therefore, Tap B alone will take 36 hours to fill the tank.

Was this answer helpful?

Similar Questions

  1. Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?


Important Questions from Time and Work

  1. A and B can do a piece of work in 18 days. B and C together can do it in 30 days. If A is twice as good a workman as C, find in how many days B alone can do the work?

  2. Two men and 7 women can complete a work in 28 days, whereas 6 men and 16 women can do the same work in 11 days. In how many days will 5 men and 4 women, working together, complete the same work?

  3. A man and a woman, working together can do a work in 66 days. The ratio of their working efficiencies is 3 ∶ 2. In how many days 6 men and 2 women together can do the same work?

  4. Each one of five men independently can complete a work in 20 days. The work is started by one person. Next day one more person joins and every next day one more person joins. From the fifth day, five persons continued working as a team. In how many days, will the work be completed?

  5. Numan does half the work as Gagan in 4/5 of the time. If together they take 16 days to complete a piece of work, then how long will it take Gagan to complete the work?

Need Expert Advice?
Upcoming Exams
RBI Grade B
July 25, 2026
SBI PO
August 01, 2026
IBPS PO
August 22, 2026
IBPS SO
August 29, 2026
IBPS Clerk
October 10, 2026
Test Series
RBI Assistant img
Banking
RBI Assistant (Pre & mains) 2026 Mock Test Series
190 Tests 1 Tests Free
4666 Attempts
4.7(27)
English, Hindi

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App