All Exams Test series for 1 year @ ₹349 only
Question

Had been one menless, then the number of days required to do a piece of work would have been one more. If the number of Man. Days required to complete the work is 56, how many workers were there?

This question was previously asked in
SSC GD 2018 Question Paper Hindi (09-Mar-2019) (Shift 1)
The correct answer is

8

Understanding the Work Problem

This problem relates the number of workers (men), the number of days they work, and the total effort required (Man. Days). We are given the total Man. Days and a condition linking the number of men and days.

Setting up the Equations

Let:

  • M be the initial number of workers.
  • D be the initial number of days required.

We know that the total Man. Days is the product of the number of men and the number of days:

$ M \times D = 56 \quad \quad (1) $

The problem states that if there had been one less man (M - 1), the work would have taken one more day (D + 1). This gives us a second equation:

$ (M - 1) \times (D + 1) = 56 \quad \quad (2) $

Solving for the Number of Workers

We can solve this system of equations. First, express D in terms of M using equation (1):

$ D = \frac{56}{M} $

Now, substitute this expression for D into equation (2):

$ (M - 1) \times \left(\frac{56}{M} + 1\right) = 56 $

Expand the left side:

$ M \times \frac{56}{M} + M \times 1 - 1 \times \frac{56}{M} - 1 \times 1 = 56 $

$ 56 + M - \frac{56}{M} - 1 = 56 $

Simplify the equation:

$ M - \frac{56}{M} - 1 = 0 $

To eliminate the fraction, multiply the entire equation by M:

$ M^2 - 56 - M = 0 $

Rearrange this into a standard quadratic equation:

$ M^2 - M - 56 = 0 $

Factor the quadratic equation. We need two numbers that multiply to -56 and add up to -1. These numbers are -8 and 7:

$ (M - 8) \times (M + 7) = 0 $

This gives two possible solutions for M:

  • M - 8 = 0 implies M = 8
  • M + 7 = 0 implies M = -7

Since the number of workers cannot be negative, we discard M = -7.

Final Answer Calculation

The initial number of workers is M = 8.

Verification:

  • If there were 8 workers, they would finish in D = 56 / 8 = 7 days.
  • If there was one less worker (7 workers), they would take D + 1 = 7 + 1 = 8 days.
  • The total Man. Days would be 7 workers × 8 days = 56 Man. Days, which matches the given information.

Therefore, there were 8 workers initially.

Was this answer helpful?

Important Questions from Time and Work

  1. Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?

  2. A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?

  3. A can do a piece of work in 16 hours, B and C can do it in 8 hours while A and C can do it 12 hours. How long will B alone take to do it?

  4. lf 12 men can do a work in 20 days, in how many days will the work be done by 15 men-
  5. 'A', 'B' and 'C' can do a piece of work in 20, 30 and 60 days respectively. In how many days, can 'A' do the work if he is assisted by 'B' and 'C' on every third day?

Need Expert Advice?
Upcoming Exams
SSC Selection Post
September 16, 2026
Test Series
SSC GD Constable img
SSC
SSC GD Constable 2026-27 Mock Tests Series (Latest Pattern)
1348 Tests 2 Tests Free
482 Attempts
4.3(267)
English, Hindi
More Questions from SSC GD Constable

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App