All Exams Test series for 1 year @ ₹349 only
Question

A can do a piece of work in 16 hours, B and C can do it in 8 hours while A and C can do it 12 hours. How long will B alone take to do it?

The correct answer is

9.6 hour

Understanding the Time and Work Problem

This question asks us to find how long it takes person B to complete a certain piece of work alone. We are given the time it takes for A alone, for B and C together, and for A and C together to complete the same work.

In time and work problems, it's often helpful to think in terms of the 'rate' at which each person or group works. The rate is typically expressed as the fraction of the work done per unit of time (in this case, per hour). If someone takes $T$ hours to complete a work, their work rate is $1/T$ work per hour.

Given Information and Work Rates

Let's list the given information and convert the time taken into work rates:

  • A can do the work in 16 hours.
  • B and C together can do the work in 8 hours.
  • A and C together can do the work in 12 hours.

Based on this, we can determine their work rates:

  • Work rate of A = $\frac{1}{16}$ work per hour.
  • Work rate of (B + C) = $\frac{1}{8}$ work per hour.
  • Work rate of (A + C) = $\frac{1}{12}$ work per hour.
Worker(s) Time Taken (hours) Work Rate (work/hour)
A 16 $\frac{1}{16}$
B + C 8 $\frac{1}{8}$
A + C 12 $\frac{1}{12}$

Calculating Individual Work Rates

We need to find the work rate of B alone to determine the time B takes. We can use the given combined rates and A's rate to find the individual rates of C and then B.

Step 1: Find the Work Rate of C

We know the work rate of (A + C) and the work rate of A. The work rate of (A + C) is the sum of A's work rate and C's work rate:

Work rate of (A + C) = Work rate of A + Work rate of C

Substituting the known values:

$\frac{1}{12} = \frac{1}{16} + \text{Work rate of C}$

Now, we solve for the Work rate of C:

Work rate of C = $\frac{1}{12} - \frac{1}{16}$

To subtract these fractions, find a common denominator. The least common multiple (LCM) of 12 and 16 is 48.

$\frac{1}{12} = \frac{1 \times 4}{12 \times 4} = \frac{4}{48}$

$\frac{1}{16} = \frac{1 \times 3}{16 \times 3} = \frac{3}{48}$

So, Work rate of C = $\frac{4}{48} - \frac{3}{48} = \frac{4-3}{48} = \frac{1}{48}$ work per hour.

Step 2: Find the Work Rate of B

We know the work rate of (B + C) and we just found the work rate of C. The work rate of (B + C) is the sum of B's work rate and C's work rate:

Work rate of (B + C) = Work rate of B + Work rate of C

Substituting the known values:

$\frac{1}{8} = \text{Work rate of B} + \frac{1}{48}$

Now, we solve for the Work rate of B:

Work rate of B = $\frac{1}{8} - \frac{1}{48}$

To subtract these fractions, find a common denominator. The LCM of 8 and 48 is 48.

$\frac{1}{8} = \frac{1 \times 6}{8 \times 6} = \frac{6}{48}$

So, Work rate of B = $\frac{6}{48} - \frac{1}{48} = \frac{6-1}{48} = \frac{5}{48}$ work per hour.

Calculating Time Taken by B Alone

The work rate of B is $\frac{5}{48}$ work per hour. This means B completes $\frac{5}{48}$ of the total work in one hour. To find the time B takes to complete the entire work (which is 1 unit of work), we take the reciprocal of B's work rate.

Time taken by B alone = $\frac{1}{\text{Work rate of B}} = \frac{1}{\frac{5}{48}}$ hours

Time taken by B alone = $\frac{48}{5}$ hours

Converting to Decimal

To express the time in decimal form, divide 48 by 5:

$\frac{48}{5} = 9.6$ hours.

Therefore, B alone will take 9.6 hours to complete the work.

Summary of Solution Steps

  1. Determine the work rate for A, (B+C), and (A+C) from the given times.
  2. Use the rates of A and (A+C) to calculate the work rate of C.
  3. Use the rates of C and (B+C) to calculate the work rate of B.
  4. Find the time taken by B alone by taking the reciprocal of B's work rate.
  5. Convert the result to a decimal number.

Revision Table: Time and Work Formulas

Concept Formula Explanation
Work Rate Rate = $\frac{\text{1}}{\text{Time}}$ The amount of work done per unit of time.
Time Taken Time = $\frac{\text{1}}{\text{Rate}}$ The total time required to complete the work.
Combined Rate Rate$_{A+B}$ = Rate$_A$ + Rate$_B$ If two people work together, their individual rates add up.
Work Done Work = Rate $\times$ Time Total work done is the rate multiplied by the time spent.

Additional Information: Time and Work Concepts

Time and work problems are a common type in quantitative aptitude. They usually involve understanding the relationship between the time taken, the amount of work done, and the rate of working. The fundamental principle is that the total amount of work is constant (often taken as 1 unit). Faster workers have higher rates, meaning they complete a larger fraction of the work in the same amount of time.

When multiple people work together, their rates are typically additive, assuming they are working independently and not hindering each other. If a person's efficiency changes, their rate changes accordingly. For example, if someone becomes twice as efficient, their rate doubles, and the time taken is halved.

LCM method can also be used for these problems by considering the total work as the LCM of the individual times. For this problem, the LCM of 16, 8, and 12 is 48. We can assume the total work is 48 units. Then, the work rate of A is 48/16 = 3 units/hour, (B+C) is 48/8 = 6 units/hour, and (A+C) is 48/12 = 4 units/hour. From these rates, we can find C's rate (4 - 3 = 1 unit/hour) and then B's rate (6 - 1 = 5 units/hour). Finally, time taken by B is Total Work / B's Rate = 48 / 5 = 9.6 hours. This method often helps avoid fractions until the final step.

Was this answer helpful?

Important Questions from Time and Work

  1. Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?

  2. A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?

  3. Had been one menless, then the number of days required to do a piece of work would have been one more. If the number of Man. Days required to complete the work is 56, how many workers were there?

  4. lf 12 men can do a work in 20 days, in how many days will the work be done by 15 men-
  5. 'A', 'B' and 'C' can do a piece of work in 20, 30 and 60 days respectively. In how many days, can 'A' do the work if he is assisted by 'B' and 'C' on every third day?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App