'A', 'B' and 'C' can do a piece of work in 20, 30 and 60 days respectively. In how many days, can 'A' do the work if he is assisted by 'B' and 'C' on every third day?
This question involves the concept of Work and Time. We are given the time taken by three individuals, 'A', 'B', and 'C', to complete a piece of work independently. We need to find the total time taken to finish the work when 'A' works consistently, and 'B' and 'C' join him on every third day.
First, let's determine the amount of work each person can complete in one day. The total work is considered as 1 unit.
The work pattern is as follows:
This cycle of 3 days repeats until the work is completed.
Let's calculate the total work done in one 3-day cycle:
To add these fractions, we find a common denominator, which is the Least Common Multiple (LCM) of 20, 30, and 60. The LCM is 60.
Combined daily rate = \( \frac{3}{60} + \frac{2}{60} + \frac{1}{60} = \frac{3+2+1}{60} = \frac{6}{60} = \frac{1}{10} \)
So, the work done on Day 3 by A, B, and C together is \( \frac{1}{10} \).
Total work done in one 3-day cycle = (Work on Day 1) + (Work on Day 2) + (Work on Day 3)
Total work in 3 days = \( \frac{1}{20} + \frac{1}{20} + \frac{1}{10} = \frac{2}{20} + \frac{1}{10} = \frac{1}{10} + \frac{1}{10} = \frac{2}{10} = \frac{1}{5} \)
Thus, \( \frac{1}{5} \) of the work is completed in every 3-day cycle.
To complete the entire work (which is 1 unit), we need to find out how many such 3-day cycles are required.
Number of cycles = \( \frac{\text{Total Work}}{\text{Work Done in one Cycle}} = \frac{1}{\frac{1}{5}} = 1 \times 5 = 5 \) cycles.
Since each cycle takes 3 days, the total number of days to complete the work is:
Total days = Number of cycles \( \times \) Days per cycle
Total days = \( 5 \times 3 = 15 \) days.
Following the pattern where 'A' works alone for two days and is assisted by 'B' and 'C' on every third day, the total work will be completed in 15 days.
Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?
A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?
Had been one menless, then the number of days required to do a piece of work would have been one more. If the number of Man. Days required to complete the work is 56, how many workers were there?
A can do a piece of work in 16 hours, B and C can do it in 8 hours while A and C can do it 12 hours. How long will B alone take to do it?