This problem involves calculating the time taken for a task when some individuals leave before completion. We use the concept of work rate.
First, find the Least Common Multiple (LCM) of the days taken by A, B, and C to find the total units of work.
Let '$D$' be the total number of days the task took to complete. C worked for all $D$ days.
A left 8 days before completion, so A worked for $(D - 8)$ days.
B left 12 days before completion, so B worked for $(D - 12)$ days.
The total work done is the sum of the work done by A, B, and C:
$Total Work = (Rate_A \times Days_A) + (Rate_B \times Days_B) + (Rate_C \times Days_C)$ $216 = (6 \times (D - 8)) + (4 \times (D - 12)) + (3 \times D)$Now, solve the equation:
$216 = 6D - 48 + 4D - 48 + 3D$ $216 = (6D + 4D + 3D) - (48 + 48)$ $216 = 13D - 96$ $216 + 96 = 13D$ $312 = 13D$ $D = \frac{312}{13}$ $D = 24$The total number of days the task took is $D$, which is 24 days. C worked for the entire duration.
Therefore, C worked for 24 days.
Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?
A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?
Had been one menless, then the number of days required to do a piece of work would have been one more. If the number of Man. Days required to complete the work is 56, how many workers were there?
A can do a piece of work in 16 hours, B and C can do it in 8 hours while A and C can do it 12 hours. How long will B alone take to do it?