All Exams Test series for 1 year @ ₹349 only
Question

John, Johnny and Janardan can finish a task in a field in 6, 12, and 24 days, respectively. In how many days will they finish the task working together?

This question was previously asked in
RRB NTPC 2019 CBT 1 Question Paper PDF (31-Jan-2021) (Shift 1)
The correct answer is
$3\frac{3}{7}$ days

Calculating Combined Work Time

This problem involves calculating the time required for multiple individuals, John, Johnny, and Janardan, to complete a task when working together. We are given the time each person takes individually.

Individual Work Rates

First, determine the rate at which each person completes the task per day:

  • John's rate: If he finishes in 6 days, he completes $ \frac{1}{6} $ of the task per day.
  • Johnny's rate: If he finishes in 12 days, he completes $ \frac{1}{12} $ of the task per day.
  • Janardan's rate: If he finishes in 24 days, he completes $ \frac{1}{24} $ of the task per day.

Combined Work Rate Calculation

To find the rate at which they work together, add their individual rates:

Combined Rate = John's Rate + Johnny's Rate + Janardan's Rate

Combined Rate = $ \frac{1}{6} + \frac{1}{12} + \frac{1}{24} $

To add these fractions, find a common denominator, which is 24:

Combined Rate = $ \frac{4}{24} + \frac{2}{24} + \frac{1}{24} $

Combined Rate = $ \frac{4 + 2 + 1}{24} = \frac{7}{24} $

This means together they complete $ \frac{7}{24} $ of the task each day.

Time Taken Together

The time taken to complete the task together is the reciprocal of their combined rate:

Time Together = $ \frac{1}{\text{Combined Rate}} $

Time Together = $ \frac{1}{7/24} $

Time Together = $ \frac{24}{7} $ days

Convert to Mixed Fraction

Convert the improper fraction $ \frac{24}{7} $ to a mixed number:

$ 24 \div 7 = 3 $ with a remainder of $ 3 $.

Therefore, the time taken is $ 3 \frac{3}{7} $ days.

Was this answer helpful?

Similar Questions

  1. Narendra finishes a job in 10 days. Amit completes the same job in 12 days. How many days will it take for both of them to finish the job while working together?
  2. Sita can clean a hotel in 20 days. Rita can clean the same hotel in 30 days. How many days will they take to clean the hotel together?
  3. A, B and C can complete a task in 36, 54 and 72 days respectively. Together they started the task but A left 8 days before the completion of the task while B left 12 days before the completion. The number of days for which C worked is:
  4. A alone can complete $\frac{2}{5}$ of a task in 12 days, while B alone can complete $\frac{3}{4}$ of the same task in 25 days. In how many days can they complete the task if they work together?
  5. If A, B and C can complete a task alone in 15 days, 20 days and 25 days, respectively, then in how many days can they complete the same task if they work together?
  6. A and B working alone can finish a task in 12 and 16 days respectively. In how many days can the task be finished if they work for one day each alternatively, and A begins the work?
  7. Reena and Jaya can complete a piece of work in 6 days and Jaya alone can complete it in 8 days. In how many days can Reena alone complete it?
  8. 12 people can sweep the floor in 4 days with 12 brooms. In how many days can 8 people sweep the floor with 8 brooms?
  9. X can work as fast as Y and Z together. X and Y together can finish the same task 3 times as fast as Z. If all three working together can finish the task in 15 days, how many days, will Z take to finish the task?
  10. 18 skilled workers can complete a task in 12 days while 24 semi-skilled workers need 15 days to complete the same task. 12 skilled workers started the task but 3 of them left after a few days. How many semi-skilled workers should replace the 3 skilled ones who left so that the task can be completed in stipulated time?

Important Questions from Time and Work

  1. A works thrice as fast as B. If B can complete a work in 256 days independently, then find the number of days in which A and B can together
    finish the work.
  2. A can finish a job in 146 days, B can finish the same job in 219 days and C can finish the same job in 292 days. If all three are working together, how many days will they require to complete the same job?
  3. X can finish a work in 153 days, Y can finish a work in 255 and Z can finish the same piece of work 340 days. How many days will they require to complete the work, if X, Y and Z are working together?
  4. A finish a work in 1170 days and B can do the same work in 2340 days. Working together, they will complete the same work in how many days?
  5. A can finish a job in 102 days, B can finish the same job in 153 days and C can finish the same job in 204 days. If all three are working together, how many days will they require to complete the same job?
Need Expert Advice?
Upcoming Exams
RRB Staff Nurse
November 23, 2026
RRB Paramedical
November 23, 2026
Test Series
RRB NTPC img
Railways
RRB NTPC Under Graduate 2026 New Mock Test Series
1612 Tests 1 Tests Free
1334 Attempts
4.3(521)
English, Hindi, Telugu +7 More
More Questions from RRB NTPC

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App