A, B, and C can complete a work in 10, 12, and 15 days, respectively. A and B work together for 3 days, after which A withdraws. B and C then work together. Find the number of days required by B and C to complete the remaining work.
3 days
A's one day work is \(\frac{1}{10}\), B's one day work is \(\frac{1}{12}\), and C's one day work is \(\frac{1}{15}\).
A and B together work for 3 days, so work done \(= 3\left(\frac{1}{10} + \frac{1}{12}\right) = 3 \times \frac{11}{60} = \frac{33}{60} = \frac{11}{20}\).
Remaining work \(= 1 - \frac{11}{20} = \frac{9}{20}\).
B and C together have a combined one day rate of \(\frac{1}{12} + \frac{1}{15} = \frac{5}{60} + \frac{4}{60} = \frac{9}{60} = \frac{3}{20}\).
Days required \(= \frac{9/20}{3/20} = 3\) days.
Hence, B and C together take 3 days to complete the remaining work.
Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?
A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?
Had been one menless, then the number of days required to do a piece of work would have been one more. If the number of Man. Days required to complete the work is 56, how many workers were there?
A can do a piece of work in 16 hours, B and C can do it in 8 hours while A and C can do it 12 hours. How long will B alone take to do it?