A, B, and C can complete a work in 10, 12, and 15 days, respectively. A and B work together for 3 days, after which A withdraws. B and C then work together. Find the number of days required by B and C to complete the remaining work.
3 days
A's one day work is \(\frac{1}{10}\), B's one day work is \(\frac{1}{12}\), and C's one day work is \(\frac{1}{15}\).
A and B together work for 3 days, so work done \(= 3\left(\frac{1}{10} + \frac{1}{12}\right) = 3 \times \frac{11}{60} = \frac{33}{60} = \frac{11}{20}\).
Remaining work \(= 1 - \frac{11}{20} = \frac{9}{20}\).
B and C together have a combined one day rate of \(\frac{1}{12} + \frac{1}{15} = \frac{5}{60} + \frac{4}{60} = \frac{9}{60} = \frac{3}{20}\).
Days required \(= \frac{9/20}{3/20} = 3\) days.
Hence, B and C together take 3 days to complete the remaining work.
Surbhi can do a piece of work in 24 days. She completed 3/8 of the work and then left it. Amit can complete the remaining work in 10 days. Working together, they will complete 125% of the same work in:
Rama and Hari can together finish a piece of work in 15 day. Rama works twice as fast as Hari, then Hari alone can finish work in :
Anil, Deepak and Dinesh together can complete a work in 35 days. Anil and Dinesh together can complete the same work in 60 days. In how many days Deepak alone can complete the same work?
Anu is four times as good as Binni in completing a task. Together they finish the same task in 7 hours. In how many hours will Anu alone complete the task?
P, Q and R can complete a work in 10 days, 20 days and 30 days, respectively, working alone. How soon can the work be completed if P is assisted by Q and R on alternate days?