All Exams Test series for 1 year @ ₹349 only
Question

Two men and 7 women can complete a work in 28 days whereas 6 men and 16 women can do the same work in 11 days. In how many days can 7 men complete the same work?

This question was previously asked in
SSC CGL 2020 Tier-II (English) Previous Year Paper (29-Jan-2022)
The correct answer is

22

Understanding the Work Problem

This question is a classic example of a time and work problem involving multiple groups of workers with different efficiencies (men and women). The key is to figure out the individual work rate of one man and one woman per day and then use that to calculate the total time for a different group.

Setting Up Equations for Work Rate

Let's assume:

  • The amount of work one man can do in one day is \(m\).
  • The amount of work one woman can do in one day is \(w\).

The total work is considered as 1 unit.

According to the first statement, "Two men and 7 women can complete a work in 28 days". This means the total work done by (2 men + 7 women) in one day is \(\frac{1}{28}\) of the total work. We can write this as an equation:

\(2m + 7w = \frac{1}{28}\) (Equation 1)

According to the second statement, "6 men and 16 women can do the same work in 11 days". This means the total work done by (6 men + 16 women) in one day is \(\frac{1}{11}\) of the total work. We can write this as another equation:

\(6m + 16w = \frac{1}{11}\) (Equation 2)

Solving for Individual Work Rates

Now we have a system of two linear equations with two variables (m and w). We need to solve these equations simultaneously to find the values of \(m\) and \(w\).

Equation 1: \(2m + 7w = \frac{1}{28}\)

Equation 2: \(6m + 16w = \frac{1}{11}\)

We can multiply Equation 1 by 3 to make the coefficient of \(m\) the same as in Equation 2:

\(3 \times (2m + 7w) = 3 \times \frac{1}{28}\)

\(6m + 21w = \frac{3}{28}\) (Equation 3)

Now, subtract Equation 2 from Equation 3:

\((6m + 21w) - (6m + 16w) = \frac{3}{28} - \frac{1}{11}\)

\(5w = \frac{3 \times 11 - 1 \times 28}{28 \times 11}\)

\(5w = \frac{33 - 28}{308}\)

\(5w = \frac{5}{308}\)

Dividing both sides by 5:

\(w = \frac{5}{308 \times 5} = \frac{1}{308}\)

So, one woman can complete \(\frac{1}{308}\) of the work in one day.

Now substitute the value of \(w\) into Equation 1 to find \(m\):

\(2m + 7w = \frac{1}{28}\)

\(2m + 7 \times \frac{1}{308} = \frac{1}{28}\)

\(2m + \frac{7}{308} = \frac{1}{28}\)

Simplify the fraction \(\frac{7}{308}\): \(308 \div 7 = 44\). So, \(\frac{7}{308} = \frac{1}{44}\).

\(2m + \frac{1}{44} = \frac{1}{28}\)

Subtract \(\frac{1}{44}\) from both sides:

\(2m = \frac{1}{28} - \frac{1}{44}\)

Find a common denominator for 28 and 44. The least common multiple is 308. \(28 \times 11 = 308\), \(44 \times 7 = 308\).

\(2m = \frac{1 \times 11}{28 \times 11} - \frac{1 \times 7}{44 \times 7}\)

\(2m = \frac{11}{308} - \frac{7}{308}\)

\(2m = \frac{11 - 7}{308} = \frac{4}{308}\)

Simplify the fraction \(\frac{4}{308}\): \(308 \div 4 = 77\). So, \(\frac{4}{308} = \frac{1}{77}\).

\(2m = \frac{1}{77}\)

Divide both sides by 2:

\(m = \frac{1}{77 \times 2} = \frac{1}{154}\)

So, one man can complete \(\frac{1}{154}\) of the work in one day.

Calculating Work by 7 Men per Day

We need to find out how many days it takes for 7 men to complete the same work. First, let's find the total work done by 7 men in one day.

Work done by 1 man in 1 day = \(\frac{1}{154}\)

Work done by 7 men in 1 day = \(7 \times m = 7 \times \frac{1}{154}\)

Simplify the fraction: \(154 \div 7 = 22\).

Work done by 7 men in 1 day = \(\frac{7}{154} = \frac{1}{22}\)

So, 7 men can complete \(\frac{1}{22}\) of the total work in one day.

Finding the Time Taken by 7 Men

If 7 men complete \(\frac{1}{22}\) of the work in one day, the total number of days required to complete the entire work (1 unit) is the reciprocal of the work done per day by 7 men.

\text{Time taken} = \frac{\text{Total Work}}{\text{Work done per day}}

\text{Time taken by 7 men} = \frac{1}{\frac{1}{22}} = 1 \times 22 = 22\)

Therefore, 7 men can complete the same work in 22 days.

Summary of Steps

Here's a quick summary of the steps taken:

  1. Defined variables \(m\) and \(w\) for the daily work rate of a man and a woman.
  2. Set up two linear equations based on the given information.
  3. Solved the system of equations to find the individual work rates (\(m\) and \(w\)).
  4. Calculated the combined work rate of 7 men per day.
  5. Determined the total time required for 7 men to complete the work.
Worker Type Daily Work Rate
1 Man \(\frac{1}{154}\)
1 Woman \(\frac{1}{308}\)
7 Men \(7 \times \frac{1}{154} = \frac{1}{22}\)

Revision Table: Key Concepts in Time and Work

Concept Description Formula/Relation
Work Rate Amount of work done by a person/group in a unit of time (e.g., per day). Work Rate = \(\frac{\text{Total Work}}{\text{Time Taken}}\)
Total Work The entire task to be completed, often considered as 1 unit. Total Work = Work Rate \(\times\) Time Taken
Time Taken The duration required to complete the total work. Time Taken = \(\frac{\text{Total Work}}{\text{Work Rate}}\)
Combined Work Rate The sum of individual work rates when multiple people/groups work together. Rate\(_{\text{Total}}\) = Rate\(_1\) + Rate\(_2\) + ...
Efficiency Related to work rate; a more efficient worker has a higher work rate. Time Taken \(\propto \frac{1}{\text{Work Rate}}\)

Additional Information on Solving Work Problems

Time and work problems often involve scenarios where individuals or groups work at different rates. The core idea is to standardize the work done per unit of time (usually per day). Here are some common variations and approaches:

  • Individual vs. Group Work: Problems might give times for individuals or groups and ask for times for different combinations. Always find the individual work rate first if possible.
  • Working Together: When people work together, their daily work rates add up. If A does \(1/a\) work per day and B does \(1/b\) per day, together they do \((1/a + 1/b)\) work per day.
  • Working Alternatively: Sometimes, people work one after another. Calculate the work done in one cycle (e.g., A works day 1, B works day 2) and the number of days per cycle.
  • Leaving or Joining: If workers leave or join mid-task, calculate the work done before the change and the remaining work. Then, calculate the time for the remaining work with the new group composition.
  • Efficiency Ratios: Problems might give efficiency ratios (e.g., A is twice as efficient as B). This directly relates their work rates (Rate of A = 2 × Rate of B).

Solving these problems relies on converting the given information into daily work rates and then manipulating these rates to find the required time or number of workers.

Was this answer helpful?

Similar Questions

  1. Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?

  2. A man can do a piece of work in 30 hours. If he works with his son then the same piece of work is finished in 20 hours. If the son works alone, he can do the work in:

  3. To do a certain work, A and B work on alternate days with B beginning the work on the first day. A alone can complete the same work in 24 days. If the work gets completed in  \(11 \frac{1}{3}\)  days, then B alone can complete  \(\rm \frac{7}{9}^{th}\)  part of the original work in:

  4. 4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 25 women complete it?

  5. Raju and Rajat working together take 5 days to complete a piece of work. If Raju alone can do this work in 7 days, how long would Rajat take to complete the same work?

  6. P and Q together can complete a piece of work in 6 days. If P can alone complete the work in 18 days, then the number of days required for Q to finish the work is:

  7. If Mohit can complete \(\frac{2}{3}\)rd of a work in 24 days, then in how many days can \(\rm\frac{1}{9}^{th}\) of the work be complete by him?

  8. A is 50% more efficient then B. B worked to finish the same work in 20 days. If A and B worked together, then how much time will they take to finish the same work?

  9. 20 women and 15 men together can complete a work in 6 days. It takes 150 days for a single woman to complete the work. In how many days can a single man complete the work?

  10. A worker completes \(\frac{3}{5}\) of a work in 12 days. In how many days will he complete \(\frac{3}{4}\) of the work? 


Important Questions from Work Efficiency

  1. Sumi can complete a job working 5 hours per day in 2 days. If she doubles her working hours per day, then in how many days will she complete the work?

  2. Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?

  3. A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?

  4. 24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?

  5. 3 men working 7 hours a day can complete a piece of work in 45 days. In how many days will 9 men working 6 hours a day complete the same work?

Need Expert Advice?
Upcoming Exams
SSC JHT
September 08, 2026
SSC Stenographer
September 09, 2026
SSC Selection Post
September 16, 2026
Test Series
SSC CGL img
SSC
SSC CGL (Tier I + Tier II) 2026 Mock Test Series - Latest Pattern
2501 Tests 6 Tests Free
4031 Attempts
4.2(839)
English, Hindi

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App