Two men and 7 women can complete a work in 28 days whereas 6 men and 16 women can do the same work in 11 days. In how many days can 7 men complete the same work?
22
This question is a classic example of a time and work problem involving multiple groups of workers with different efficiencies (men and women). The key is to figure out the individual work rate of one man and one woman per day and then use that to calculate the total time for a different group.
Let's assume:
The total work is considered as 1 unit.
According to the first statement, "Two men and 7 women can complete a work in 28 days". This means the total work done by (2 men + 7 women) in one day is \(\frac{1}{28}\) of the total work. We can write this as an equation:
\(2m + 7w = \frac{1}{28}\) (Equation 1)
According to the second statement, "6 men and 16 women can do the same work in 11 days". This means the total work done by (6 men + 16 women) in one day is \(\frac{1}{11}\) of the total work. We can write this as another equation:
\(6m + 16w = \frac{1}{11}\) (Equation 2)
Now we have a system of two linear equations with two variables (m and w). We need to solve these equations simultaneously to find the values of \(m\) and \(w\).
Equation 1: \(2m + 7w = \frac{1}{28}\)
Equation 2: \(6m + 16w = \frac{1}{11}\)
We can multiply Equation 1 by 3 to make the coefficient of \(m\) the same as in Equation 2:
\(3 \times (2m + 7w) = 3 \times \frac{1}{28}\)
\(6m + 21w = \frac{3}{28}\) (Equation 3)
Now, subtract Equation 2 from Equation 3:
\((6m + 21w) - (6m + 16w) = \frac{3}{28} - \frac{1}{11}\)
\(5w = \frac{3 \times 11 - 1 \times 28}{28 \times 11}\)
\(5w = \frac{33 - 28}{308}\)
\(5w = \frac{5}{308}\)
Dividing both sides by 5:
\(w = \frac{5}{308 \times 5} = \frac{1}{308}\)
So, one woman can complete \(\frac{1}{308}\) of the work in one day.
Now substitute the value of \(w\) into Equation 1 to find \(m\):
\(2m + 7w = \frac{1}{28}\)
\(2m + 7 \times \frac{1}{308} = \frac{1}{28}\)
\(2m + \frac{7}{308} = \frac{1}{28}\)
Simplify the fraction \(\frac{7}{308}\): \(308 \div 7 = 44\). So, \(\frac{7}{308} = \frac{1}{44}\).
\(2m + \frac{1}{44} = \frac{1}{28}\)
Subtract \(\frac{1}{44}\) from both sides:
\(2m = \frac{1}{28} - \frac{1}{44}\)
Find a common denominator for 28 and 44. The least common multiple is 308. \(28 \times 11 = 308\), \(44 \times 7 = 308\).
\(2m = \frac{1 \times 11}{28 \times 11} - \frac{1 \times 7}{44 \times 7}\)
\(2m = \frac{11}{308} - \frac{7}{308}\)
\(2m = \frac{11 - 7}{308} = \frac{4}{308}\)
Simplify the fraction \(\frac{4}{308}\): \(308 \div 4 = 77\). So, \(\frac{4}{308} = \frac{1}{77}\).
\(2m = \frac{1}{77}\)
Divide both sides by 2:
\(m = \frac{1}{77 \times 2} = \frac{1}{154}\)
So, one man can complete \(\frac{1}{154}\) of the work in one day.
We need to find out how many days it takes for 7 men to complete the same work. First, let's find the total work done by 7 men in one day.
Work done by 1 man in 1 day = \(\frac{1}{154}\)
Work done by 7 men in 1 day = \(7 \times m = 7 \times \frac{1}{154}\)
Simplify the fraction: \(154 \div 7 = 22\).
Work done by 7 men in 1 day = \(\frac{7}{154} = \frac{1}{22}\)
So, 7 men can complete \(\frac{1}{22}\) of the total work in one day.
If 7 men complete \(\frac{1}{22}\) of the work in one day, the total number of days required to complete the entire work (1 unit) is the reciprocal of the work done per day by 7 men.
\text{Time taken} = \frac{\text{Total Work}}{\text{Work done per day}}
\text{Time taken by 7 men} = \frac{1}{\frac{1}{22}} = 1 \times 22 = 22\)
Therefore, 7 men can complete the same work in 22 days.
Here's a quick summary of the steps taken:
| Worker Type | Daily Work Rate |
|---|---|
| 1 Man | \(\frac{1}{154}\) |
| 1 Woman | \(\frac{1}{308}\) |
| 7 Men | \(7 \times \frac{1}{154} = \frac{1}{22}\) |
| Concept | Description | Formula/Relation |
|---|---|---|
| Work Rate | Amount of work done by a person/group in a unit of time (e.g., per day). | Work Rate = \(\frac{\text{Total Work}}{\text{Time Taken}}\) |
| Total Work | The entire task to be completed, often considered as 1 unit. | Total Work = Work Rate \(\times\) Time Taken |
| Time Taken | The duration required to complete the total work. | Time Taken = \(\frac{\text{Total Work}}{\text{Work Rate}}\) |
| Combined Work Rate | The sum of individual work rates when multiple people/groups work together. | Rate\(_{\text{Total}}\) = Rate\(_1\) + Rate\(_2\) + ... |
| Efficiency | Related to work rate; a more efficient worker has a higher work rate. | Time Taken \(\propto \frac{1}{\text{Work Rate}}\) |
Time and work problems often involve scenarios where individuals or groups work at different rates. The core idea is to standardize the work done per unit of time (usually per day). Here are some common variations and approaches:
Solving these problems relies on converting the given information into daily work rates and then manipulating these rates to find the required time or number of workers.
Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?
A man can do a piece of work in 30 hours. If he works with his son then the same piece of work is finished in 20 hours. If the son works alone, he can do the work in:
To do a certain work, A and B work on alternate days with B beginning the work on the first day. A alone can complete the same work in 24 days. If the work gets completed in \(11 \frac{1}{3}\) days, then B alone can complete \(\rm \frac{7}{9}^{th}\) part of the original work in:
4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 25 women complete it?
Raju and Rajat working together take 5 days to complete a piece of work. If Raju alone can do this work in 7 days, how long would Rajat take to complete the same work?
P and Q together can complete a piece of work in 6 days. If P can alone complete the work in 18 days, then the number of days required for Q to finish the work is:
If Mohit can complete \(\frac{2}{3}\)rd of a work in 24 days, then in how many days can \(\rm\frac{1}{9}^{th}\) of the work be complete by him?
A is 50% more efficient then B. B worked to finish the same work in 20 days. If A and B worked together, then how much time will they take to finish the same work?
20 women and 15 men together can complete a work in 6 days. It takes 150 days for a single woman to complete the work. In how many days can a single man complete the work?
A worker completes \(\frac{3}{5}\) of a work in 12 days. In how many days will he complete \(\frac{3}{4}\) of the work?
Sumi can complete a job working 5 hours per day in 2 days. If she doubles her working hours per day, then in how many days will she complete the work?
Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?
A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?
24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?
3 men working 7 hours a day can complete a piece of work in 45 days. In how many days will 9 men working 6 hours a day complete the same work?