All Exams Test series for 1 year @ ₹349 only
Question

A worker completes \(\frac{3}{5}\) of a work in 12 days. In how many days will he complete \(\frac{3}{4}\) of the work? 

This question was previously asked in
SSC CGL 2023 (Tier-II) Paper 1 Previous Year Paper (26-Oct-2023) (Shift-1)
The correct answer is

15

Understanding the Work and Time Problem

The question describes a scenario where a worker completes a certain fraction of a task in a given number of days. We need to find out how many days it will take the same worker to complete a different fraction of the same task, assuming their work rate remains constant.

Problems involving work and time often rely on the concept of the rate of work, which is the amount of work done per unit of time.

Calculating the Worker's Rate of Work

We are told that the worker completes \(\frac{3}{5}\) of the total work in 12 days.

The rate of work can be calculated as:

Rate = \(\frac{\text{Amount of Work Done}}{\text{Time Taken}}\)

In this case, the amount of work done is \(\frac{3}{5}\) and the time taken is 12 days.

Rate = \(\frac{\frac{3}{5}}{12}\) work per day

To simplify this fraction, we can write it as multiplication:

Rate = \(\frac{3}{5} \times \frac{1}{12}\) work per day

Rate = \(\frac{3 \times 1}{5 \times 12}\) work per day

Rate = \(\frac{3}{60}\) work per day

This fraction can be simplified by dividing both the numerator and the denominator by their greatest common divisor, which is 3.

Rate = \(\frac{3 \div 3}{60 \div 3}\) work per day

Rate = \(\frac{1}{20}\) work per day

So, the worker completes \(\frac{1}{20}\) of the total work every day.

Calculating Time to Complete \(\frac{3}{4}\) of the Work

Now we want to find out how many days it will take the worker to complete \(\frac{3}{4}\) of the work at the rate of \(\frac{1}{20}\) work per day.

The relationship between time, work, and rate is:

Time = \(\frac{\text{Amount of Work to be Done}}{\text{Rate of Work per Day}}\)

Here, the amount of work to be done is \(\frac{3}{4}\) and the rate is \(\frac{1}{20}\) work per day.

Time = \(\frac{\frac{3}{4}}{\frac{1}{20}}\) days

To divide by a fraction, we multiply by its reciprocal:

Time = \(\frac{3}{4} \times \frac{20}{1}\) days

Time = \(\frac{3 \times 20}{4 \times 1}\) days

Time = \(\frac{60}{4}\) days

Now, we perform the division:

Time = 15 days

Therefore, the worker will complete \(\frac{3}{4}\) of the work in 15 days.

Summary of the Solution Steps

  1. Identify the given information: Worker completes \(\frac{3}{5}\) of work in 12 days.
  2. Identify the target: Find the time to complete \(\frac{3}{4}\) of the work.
  3. Calculate the worker's daily rate: Rate = \(\frac{\text{Work Done}}{\text{Time Taken}}\) = \(\frac{3/5}{12} = \frac{1}{20}\) work per day.
  4. Calculate the time for the target work: Time = \(\frac{\text{Target Work}}{\text{Rate}}\) = \(\frac{3/4}{1/20}\) = \(\frac{3}{4} \times 20 = 15\) days.

Final Answer

The worker will complete \(\frac{3}{4}\) of the work in 15 days.

Revision Table: Key Work and Time Concepts

ConceptExplanationHow it's used here
Work DoneThe portion of the total task completed. Represented as a fraction or percentage.Given as \(\frac{3}{5}\) and \(\frac{3}{4}\) of the total work.
Time TakenThe duration required to complete a specific amount of work.Given as 12 days; we need to find another time.
Rate of WorkThe amount of work completed per unit of time (e.g., per day, per hour). Assumed constant unless stated otherwise.Calculated as \(\frac{1}{20}\) of the work completed per day.
RelationshipWork Done = Rate \(\times\) Time Taken. Time Taken = \(\frac{\text{Work Done}}{\text{Rate}}\). Rate = \(\frac{\text{Work Done}}{\text{Time Taken}}\).Used to calculate the rate from the initial information and then calculate the required time.

Additional Information: Proportionality in Work Problems

Work and Time problems with a constant rate can also be solved using proportionality. If a worker completes \(W_1\) amount of work in \(T_1\) time, and \(W_2\) amount of work in \(T_2\) time, assuming a constant rate, the ratio of work to time is constant:

\(\frac{W_1}{T_1} = \frac{W_2}{T_2}\)

In this problem:

  • \(W_1 = \frac{3}{5}\)
  • \(T_1 = 12\) days
  • \(W_2 = \frac{3}{4}\)
  • \(T_2 = ?\)

Setting up the proportion:

\(\frac{3/5}{12} = \frac{3/4}{T_2}\)

This simplifies to:

\(\frac{3}{5 \times 12} = \frac{3}{4 \times T_2}\)

\(\frac{3}{60} = \frac{3}{4 \times T_2}\)

Simplifying the left side:

\(\frac{1}{20} = \frac{3}{4 \times T_2}\)

Cross-multiply:

\(1 \times (4 \times T_2) = 3 \times 20\)

\(4 \times T_2 = 60\)

Divide by 4:

\(T_2 = \frac{60}{4}\)

\(T_2 = 15\)

This confirms that it takes 15 days to complete \(\frac{3}{4}\) of the work.

Was this answer helpful?

Similar Questions

  1. Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?

  2. A man can do a piece of work in 30 hours. If he works with his son then the same piece of work is finished in 20 hours. If the son works alone, he can do the work in:

  3. To do a certain work, A and B work on alternate days with B beginning the work on the first day. A alone can complete the same work in 24 days. If the work gets completed in  \(11 \frac{1}{3}\)  days, then B alone can complete  \(\rm \frac{7}{9}^{th}\)  part of the original work in:

  4. Two men and 7 women can complete a work in 28 days whereas 6 men and 16 women can do the same work in 11 days. In how many days can 7 men complete the same work?

  5. 4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 25 women complete it?

  6. Raju and Rajat working together take 5 days to complete a piece of work. If Raju alone can do this work in 7 days, how long would Rajat take to complete the same work?

  7. If Mohit can complete \(\frac{2}{3}\)rd of a work in 24 days, then in how many days can \(\rm\frac{1}{9}^{th}\) of the work be complete by him?

  8. A is 50% more efficient then B. B worked to finish the same work in 20 days. If A and B worked together, then how much time will they take to finish the same work?

  9. 20 women and 15 men together can complete a work in 6 days. It takes 150 days for a single woman to complete the work. In how many days can a single man complete the work?

  10. A can complete a piece of work in 25 days while B can complete the same work in 30 days. They work on alternate basis, starting with A. Both A and B follow this pattern for 5 days and then A leaves the work. In how many days will B finish the remaining work?


Important Questions from Work Efficiency

  1. Sumi can complete a job working 5 hours per day in 2 days. If she doubles her working hours per day, then in how many days will she complete the work?

  2. Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?

  3. A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?

  4. 24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?

  5. 3 men working 7 hours a day can complete a piece of work in 45 days. In how many days will 9 men working 6 hours a day complete the same work?

Need Expert Advice?
Upcoming Exams
SSC JHT
September 08, 2026
SSC Stenographer
September 09, 2026
SSC Selection Post
September 16, 2026
Test Series
SSC CGL img
SSC
SSC CGL (Tier I + Tier II) 2026 Mock Test Series - Latest Pattern
2501 Tests 6 Tests Free
4101 Attempts
4.2(839)
English, Hindi

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App