All Exams Test series for 1 year @ ₹349 only
Question

A is 50% more efficient then B. B worked to finish the same work in 20 days. If A and B worked together, then how much time will they take to finish the same work?

This question was previously asked in
SSC CGL 2023 (Tier-II) Paper 1 Previous Year Paper (26-Oct-2023) (Shift-1)
The correct answer is

8 days

Understanding Work and Efficiency Problems

This problem involves the concepts of work, efficiency, and time. Efficiency is inversely proportional to the time taken to complete a fixed amount of work. If someone is more efficient, they take less time to finish the same work.

Analyzing the Given Information

  • A is 50% more efficient than B.
  • B takes 20 days to finish the entire work.
  • We need to find the time A and B take together to finish the same work.

Calculating Individual Work Rates (Efficiency)

Let's think about the work done per day. If B finishes the work in 20 days, B completes $\frac{1}{20}$ of the work each day. This is B's daily work rate or efficiency relative to the total work.

  • B's daily work rate = $\frac{1}{20}$ of the total work.

A is 50% more efficient than B. This means A's daily work rate is B's daily work rate plus 50% of B's daily work rate.

  • 50% of B's daily work rate = $50\%$ of $\frac{1}{20} = \frac{50}{100} \times \frac{1}{20} = \frac{1}{2} \times \frac{1}{20} = \frac{1}{40}$ of the total work.
  • A's daily work rate = B's daily work rate + 50% of B's daily work rate
  • A's daily work rate = $\frac{1}{20} + \frac{1}{40} = \frac{2}{40} + \frac{1}{40} = \frac{3}{40}$ of the total work.

Calculating Combined Work Rate

When A and B work together, their daily work rates add up.

  • Combined daily work rate of A and B = A's daily work rate + B's daily work rate
  • Combined daily work rate = $\frac{3}{40} + \frac{1}{20} = \frac{3}{40} + \frac{2}{40} = \frac{5}{40} = \frac{1}{8}$ of the total work.

This means that together, A and B complete $\frac{1}{8}$ of the total work each day.

Calculating Time Taken Together

If they complete $\frac{1}{8}$ of the work each day, the total time taken to complete the entire work (which is 1 whole) is the reciprocal of their combined daily work rate.

  • Time taken together = $\frac{1}{\text{Combined daily work rate}}$
  • Time taken together = $\frac{1}{1/8} = 8$ days.

Alternative Approach Using Efficiency Ratios

Let the efficiency of B be $E_B$.

The efficiency of A is 50% more than B, so $E_A = E_B + 0.5 E_B = 1.5 E_B$.

The ratio of efficiencies $E_A : E_B = 1.5 : 1 = 3 : 2$.

Efficiency is inversely proportional to time. So, the ratio of time taken $T_A : T_B$ is the inverse ratio of their efficiencies.

$T_A : T_B = \frac{1}{E_A} : \frac{1}{E_B} = \frac{1}{1.5 E_B} : \frac{1}{E_B} = \frac{1}{1.5} : 1 = 1 : 1.5 = 2 : 3$.

We are given that $T_B = 20$ days. Since $T_A : T_B = 2 : 3$, we have $\frac{T_A}{T_B} = \frac{2}{3}$.

$\frac{T_A}{20} = \frac{2}{3} \implies T_A = \frac{2}{3} \times 20 = \frac{40}{3}$ days.

Let the total work be $W$.

B's daily work rate $= \frac{W}{T_B} = \frac{W}{20}$.

A's daily work rate $= \frac{W}{T_A} = \frac{W}{40/3} = \frac{3W}{40}$.

Combined daily work rate $= \frac{W}{20} + \frac{3W}{40} = \frac{2W}{40} + \frac{3W}{40} = \frac{5W}{40} = \frac{W}{8}$.

The time taken by A and B together is $\frac{\text{Total Work}}{\text{Combined daily work rate}} = \frac{W}{W/8} = 8$ days.

Summary of Steps

Step Description Calculation
1 Find B's daily work rate $\frac{1}{20}$
2 Find A's daily work rate (50% more than B) $\frac{1}{20} + 0.5 \times \frac{1}{20} = \frac{3}{40}$
3 Find Combined daily work rate $\frac{1}{20} + \frac{3}{40} = \frac{5}{40} = \frac{1}{8}$
4 Find Time taken together $\frac{1}{\text{Combined rate}} = \frac{1}{1/8} = 8$ days

Therefore, if A and B worked together, they would take 8 days to finish the same work.

Revision Table: Work and Efficiency Concepts

Concept Relationship Formula
Work Rate (Efficiency) Amount of work done per unit of time. Work Rate = $\frac{\text{Total Work}}{\text{Time}}$
Time Duration to complete the work. Time = $\frac{\text{Total Work}}{\text{Work Rate}}$
Work Total task to be completed. Often assumed as 1 unit or calculated based on given rates/times. Total Work = Work Rate $\times$ Time
Efficiency & Time Inversely proportional for a fixed amount of work. $E \propto \frac{1}{T}$
Combined Work Rate Sum of individual work rates when working together. $R_{\text{combined}} = R_1 + R_2 + \dots$

Additional Information: Percentage Efficiency and Work

When efficiency is given as a percentage relative to another person, it directly affects their work rate. If someone is X% more efficient, their work rate is (100+X)% of the other person's work rate. If they are X% less efficient, their work rate is (100-X)% of the other person's work rate.

In this problem, A is 50% more efficient than B.

  • Efficiency of A = 100% of Efficiency of B + 50% of Efficiency of B
  • Efficiency of A = 150% of Efficiency of B
  • Ratio of Efficiency of A to Efficiency of B = 150 : 100 = 3 : 2.

Since time is inversely proportional to efficiency, the ratio of time taken by A to time taken by B is the inverse of the efficiency ratio.

  • Ratio of Time taken by A to Time taken by B = 2 : 3.

If B takes 20 days (which corresponds to the '3' part of the ratio), then the time taken by A (corresponding to the '2' part) can be found:

  • $\frac{\text{Time}_A}{\text{Time}_B} = \frac{2}{3}$
  • $\frac{\text{Time}_A}{20} = \frac{2}{3}$
  • Time$_A = \frac{2 \times 20}{3} = \frac{40}{3}$ days.

A takes $\frac{40}{3}$ days to complete the work alone.

Using the formula for time taken by A and B together: $T_{\text{together}} = \frac{T_A \times T_B}{T_A + T_B}$ (This formula works when we have individual times for completing the *same* work).

  • $T_{\text{together}} = \frac{\frac{40}{3} \times 20}{\frac{40}{3} + 20} = \frac{\frac{800}{3}}{\frac{40}{3} + \frac{60}{3}} = \frac{\frac{800}{3}}{\frac{100}{3}} = \frac{800}{3} \times \frac{3}{100} = \frac{800}{100} = 8$ days.

Both methods confirm that A and B working together take 8 days to finish the work.

Was this answer helpful?

Similar Questions

  1. X and Y can complete a work in 9 days and 36 days, respectively. X begins to do the work and they work alternately one at a time for one day each. The whole work will be complete in:

  2. P is two times as efficient as Q. P is able to complete a piece of work in 40 days less than Q. Working together, the whole number of days taken by them to complete the work is:

    (Round off to the nearest integer)

  3. 4 women or 6 boys can finish a work in the same number of days. A boy can finish it in 60 days. In how many days can 5 women finish the work, working together every day?

  4. To do a certain work, Ajay and Bharat work on alternate days, with Bharat starting the work on the first day. Ajay can finish the work alone in 32 days. If the work gets completed in exactly 8 days, then Bharat alone can finish 7 times the same work in ____________ days.

  5. A, B and C can separately complete a work in 12, 15 and 20 days, respectively. They worked together 4 days. What will be the remaining work?

  6. A, B and C, working alone, can complete a job in 16, 24 and 36 days, respectively. In how many days can they complete the job if they work together?

  7. Rakshit, Ajay, and Satish are sanitation workers in a Municipal Corporation. Rakshit alone takes 20 hours to clean a drain while Ajay takes 12 hours when working alone to do the same. All three together take only 5 hours to clean the drain. In how many hours, can Satish complete the work alone?

  8. 15 men and 25 women can complete a piece of work in 9.6 days. If 16 women can complete the same work in 27 days, find the number of days in which 16 men can complete the same work.  

  9. A,B and C can do a piece of work in 30 days, 40 days and 50 days, respectively. Beginning with A, if A, B and C do the work alternatively then in how many days will the work be finished?

  10. Ravi can do a piece of work in 40 days and Sudha can do the same piece of work in 60 days. If they work on alternative days starting with Sudha on the first day, then in how many days will the work be completed?


Important Questions from Work Efficiency

  1. A and B working together can complete a job in 30 days. The ratio of their efficiencies is 3 : 2. In how many days can the faster person complete the job?

  2. A takes 15 days to complete \(\frac{5}{7} \)  of a work. With the help of B, they finish the whole work in 12 days. In how many days, B alone will complete the same work

  3. A alone can complete a work in 14 days and B alone can complete the same work in 21 days. A and B start the work together but A leaves the work after 4 days of the starting of work. In how many days B will complete the remaining work?

  4. For completing a certain work, A is 50% less efficient than B and B is 50% more efficient than C. Working together A, B and C can complete the work in 48 days. A alone can complete the same work in:

  5. 30 persons can do a piece of work in 24 days. How many more persons are required to complete the work in 20 days?

Need Expert Advice?
Upcoming Exams
SSC JHT
September 08, 2026
SSC Stenographer
September 09, 2026
SSC Selection Post
September 16, 2026
Test Series
SSC CGL img
SSC
SSC CGL (Tier I + Tier II) 2026 Mock Test Series - Latest Pattern
2501 Tests 6 Tests Free
4024 Attempts
4.2(839)
English, Hindi

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App