All Exams Test series for 1 year @ ₹349 only
Question

A takes 15 days to complete \(\frac{5}{7} \)  of a work. With the help of B, they finish the whole work in 12 days. In how many days, B alone will complete the same work

The correct answer is

28 days

Solving Work and Time Problems: Finding Individual Work Days

This problem involves understanding how individuals and groups complete a piece of work over time. We are given information about how long A takes to complete a fraction of the work and how long A and B together take to complete the whole work. Our goal is to find out how many days B alone would take to complete the same work.

Let's break down the information provided:

  • A completes \(\frac{5}{7}\) of the work in 15 days.
  • A and B together complete the whole work (which is 1 or \(\frac{7}{7}\) of the work) in 12 days.

We need to find the number of days B alone will take to complete the whole work.

Step-by-Step Solution to Find B's Work Time

Step 1: Find the time A takes to complete the whole work.

If A completes \(\frac{5}{7}\) of the work in 15 days, the time taken to complete the entire work (which is \(\frac{7}{7}\) or 1 unit) can be found using a proportion or by finding the time per fraction of work.

Time for 1 unit of work = \(\text{Time for } \frac{5}{7} \text{ work} \div \frac{5}{7}\)

Time taken by A to complete the whole work = \(15 \text{ days} \div \frac{5}{7} = 15 \times \frac{7}{5} \text{ days}\)

Calculating this:

\(15 \times \frac{7}{5} = \frac{15 \times 7}{5} = \frac{105}{5} = 21\) days.

So, A alone takes 21 days to complete the entire work.

Step 2: Determine the work rate of A and the combined work rate of A and B.

The work rate is the amount of work done per day. If a person takes \(D\) days to complete a work, their work rate is \(\frac{1}{D}\) of the work per day.

  • Work rate of A = \(\frac{1}{\text{Time taken by A}} = \frac{1}{21}\) of the work per day.
  • Work rate of A and B together = \(\frac{1}{\text{Time taken by A and B together}} = \frac{1}{12}\) of the work per day.

Step 3: Find the work rate of B.

The combined work rate of A and B is the sum of their individual work rates. That is, Work Rate (A + B) = Work Rate (A) + Work Rate (B).

We know the combined rate (\(\frac{1}{12}\)) and A's rate (\(\frac{1}{21}\)). We can find B's rate:

Work Rate (B) = Work Rate (A + B) - Work Rate (A)

Work Rate (B) = \(\frac{1}{12} - \frac{1}{21}\)

To subtract these fractions, we find a common denominator for 12 and 21. The least common multiple (LCM) of 12 and 21 is 84.

\(\frac{1}{12} = \frac{1 \times 7}{12 \times 7} = \frac{7}{84}\)

\(\frac{1}{21} = \frac{1 \times 4}{21 \times 4} = \frac{4}{84}\)

Work Rate (B) = \(\frac{7}{84} - \frac{4}{84} = \frac{7-4}{84} = \frac{3}{84}\)

Simplify the fraction \(\frac{3}{84}\) by dividing the numerator and denominator by their greatest common divisor, which is 3.

Work Rate (B) = \(\frac{3 \div 3}{84 \div 3} = \frac{1}{28}\) of the work per day.

Step 4: Calculate the time B takes to complete the whole work.

Since B completes \(\frac{1}{28}\) of the work per day, the time taken for B to complete the whole work is the reciprocal of B's work rate.

Time taken by B = \(\frac{1}{\text{Work Rate (B)}} = \frac{1}{\frac{1}{28}}\) days.

Time taken by B = \(28\) days.

Thus, B alone will complete the same work in 28 days.

Let's summarize the key times calculated:

  • A takes 21 days to complete the whole work.
  • A and B together take 12 days to complete the whole work.
  • B takes 28 days to complete the whole work.

Detailed Calculations Overview

The calculation process involved converting the fraction of work done by A into the time taken for the whole work, determining individual and combined work rates, and then using these rates to find the required time for B.

  • A's total time = \(15 \text{ days} \times \frac{7}{5} = 21 \text{ days}\)
  • A's rate = \(\frac{1}{21}\) work/day
  • (A+B)'s rate = \(\frac{1}{12}\) work/day
  • B's rate = (A+B)'s rate - A's rate = \(\frac{1}{12} - \frac{1}{21} = \frac{7}{84} - \frac{4}{84} = \frac{3}{84} = \frac{1}{28}\) work/day
  • B's total time = \(\frac{1}{\text{B's rate}} = \frac{1}{\frac{1}{28}} = 28 \text{ days}\)

The final answer is 28 days.

Revision Table: Work and Time Concepts

Concept Definition Formula/Relationship
Work A task to be completed (often represented as 1 unit for the whole work). Usually normalized to 1 for the whole job.
Time Duration taken to complete the work. Measured in days, hours, minutes, etc.
Work Rate (Efficiency) Amount of work done per unit of time. Work Rate = \(\frac{\text{Work Done}}{\text{Time Taken}}\). For whole work, Rate = \(\frac{1}{\text{Time Taken}}\).
Inverse Relationship Time taken is inversely proportional to Work Rate. Time Taken = \(\frac{1}{\text{Work Rate}}\). Higher rate means less time.
Combined Work Rate The sum of individual work rates when people work together. Rate\(_{(A+B)}\) = Rate\(_A\) + Rate\(_B\).

Additional Information: Efficiency and Combined Work

Work and time problems often rely on the concept of efficiency, which is directly related to the work rate. A more efficient person has a higher work rate and takes less time to complete the same amount of work.

When multiple people work together, their efficiencies (or work rates) add up, allowing them to complete the work faster than any individual could alone (assuming they don't hinder each other). This is why A and B together take 12 days, which is less than the 21 days A alone takes.

The fraction of work concept is also key. If a person completes a fraction \(f\) of the work in \(d\) days, the time they would take for the whole work is \(d/f\). In our problem, A completes \(\frac{5}{7}\) of the work in 15 days, so the time for the whole work is \(15 / (\frac{5}{7}) = 15 \times \frac{7}{5} = 21\) days.

Understanding these fundamental principles helps in solving various work and time problems efficiently.

Was this answer helpful?

Important Questions from Work Efficiency

  1. A and B working together can complete a job in 30 days. The ratio of their efficiencies is 3 : 2. In how many days can the faster person complete the job?

  2. A alone can complete a work in 14 days and B alone can complete the same work in 21 days. A and B start the work together but A leaves the work after 4 days of the starting of work. In how many days B will complete the remaining work?

  3. For completing a certain work, A is 50% less efficient than B and B is 50% more efficient than C. Working together A, B and C can complete the work in 48 days. A alone can complete the same work in:

  4. 30 persons can do a piece of work in 24 days. How many more persons are required to complete the work in 20 days?

  5. X is twice as good as workman as Y. Together, they finish the work in 18 days. In how many days can it be done by each separately?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App