All Exams Test series for 1 year @ ₹349 only
Question

30 persons can do a piece of work in 24 days. How many more persons are required to complete the work in 20 days?

The correct answer is

6

Work and Time: Calculating Additional Persons

This problem requires calculating the number of additional persons needed to complete a specific piece of work within a reduced timeframe. The core concept is inverse proportion: as the number of days decreases, the number of persons required increases proportionally.

Calculating Total Workload

First, establish the total effort needed for the work. This is typically measured in 'person-days', calculated by multiplying the initial number of persons by the number of days they take.

  • Initial number of persons = 30
  • Initial number of days = 24
  • Total Work = Persons $\times$ Days
  • Total Work = $30 \times 24$ person-days
  • Total Work = $720$ person-days

Determining Persons for the New Deadline

Next, determine the total number of persons necessary to complete the same amount of work (720 person-days) within the new, shorter deadline of 20 days.

  • Total Work = $720$ person-days
  • Target days = 20
  • Required Persons = Total Work / Target Days
  • Required Persons = $ \frac{720}{20} $
  • Required Persons = $36$

Finding the Number of Additional Persons

Finally, calculate how many more persons are needed by finding the difference between the number of persons required for the 20-day deadline and the original number of persons.

  • Persons required for 20 days = 36
  • Original number of persons = 30
  • More Persons Required = Required Persons - Original Persons
  • More Persons Required = $36 - 30$
  • More Persons Required = $6$

Therefore, 6 more persons are needed to finish the work in 20 days.

Was this answer helpful?

Important Questions from Work Efficiency

  1. A and B working together can complete a job in 30 days. The ratio of their efficiencies is 3 : 2. In how many days can the faster person complete the job?

  2. A takes 15 days to complete \(\frac{5}{7} \)  of a work. With the help of B, they finish the whole work in 12 days. In how many days, B alone will complete the same work

  3. A alone can complete a work in 14 days and B alone can complete the same work in 21 days. A and B start the work together but A leaves the work after 4 days of the starting of work. In how many days B will complete the remaining work?

  4. For completing a certain work, A is 50% less efficient than B and B is 50% more efficient than C. Working together A, B and C can complete the work in 48 days. A alone can complete the same work in:

  5. X is twice as good as workman as Y. Together, they finish the work in 18 days. In how many days can it be done by each separately?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App