All Exams Test series for 1 year @ ₹349 only
Question

A alone can complete a work in 14 days and B alone can complete the same work in 21 days. A and B start the work together but A leaves the work after 4 days of the starting of work. In how many days B will complete the remaining work?

The correct answer is

11 days

Understanding the Work and Time Problem

This problem involves calculating the time taken by individuals and a team to complete a certain amount of work. We are given the time A and B take individually to complete the entire work and the period they work together before A leaves. We need to find how long B takes to finish the remaining part of the work.

Calculating Individual Work Rates

In work and time problems, the work rate is the amount of work done by a person in one unit of time (usually one day). If a person can complete a work in 'd' days, their daily work rate is $\frac{1}{d}$ of the total work.

  • A alone completes the work in 14 days.
  • So, A's daily work rate is $\frac{1}{14}$ of the work per day.
  • B alone completes the same work in 21 days.
  • So, B's daily work rate is $\frac{1}{21}$ of the work per day.

Calculating Combined Work Rate

When A and B work together, their combined daily work rate is the sum of their individual daily work rates.

Combined daily work rate of A and B = A's daily rate + B's daily rate

Combined daily work rate = $\frac{1}{14} + \frac{1}{21}$

To add these fractions, we find a common denominator. The least common multiple (LCM) of 14 and 21 is 42.

$\frac{1}{14} = \frac{1 \times 3}{14 \times 3} = \frac{3}{42}$

$\frac{1}{21} = \frac{1 \times 2}{21 \times 2} = \frac{2}{42}$

Combined daily work rate = $\frac{3}{42} + \frac{2}{42} = \frac{3+2}{42} = \frac{5}{42}$ of the work per day.

Work Done by A and B Together

A and B start the work together and work for 4 days before A leaves. The amount of work done in these 4 days is calculated by multiplying their combined daily work rate by the number of days they worked together.

Work done by A and B in 4 days = Combined daily work rate $\times$ Number of days worked together

Work done in 4 days = $\frac{5}{42} \times 4 = \frac{20}{42}$

This fraction can be simplified by dividing the numerator and denominator by their greatest common divisor, which is 2.

Work done in 4 days = $\frac{20 \div 2}{42 \div 2} = \frac{10}{21}$ of the total work.

Calculating Remaining Work

The total work is considered as 1 unit. The remaining work is the total work minus the work done by A and B together.

Remaining work = Total work - Work done in 4 days

Remaining work = $1 - \frac{10}{21}$

To subtract, we write 1 as $\frac{21}{21}$.

Remaining work = $\frac{21}{21} - \frac{10}{21} = \frac{21-10}{21} = \frac{11}{21}$ of the total work.

Time Taken by B to Complete the Remaining Work

After A leaves, only B is left to complete the remaining work. We know B's daily work rate is $\frac{1}{21}$ of the work per day. To find the time B takes to complete the remaining $\frac{11}{21}$ of the work, we divide the remaining work by B's daily work rate.

Time taken by B = $\frac{\text{Remaining work}}{\text{B's daily work rate}}$

Time taken by B = $\frac{11/21}{1/21}$

Dividing by a fraction is the same as multiplying by its reciprocal.

Time taken by B = $\frac{11}{21} \times \frac{21}{1} = \frac{11 \times 21}{21 \times 1} = \frac{231}{21}$

Dividing 231 by 21 gives 11.

Time taken by B = 11 days.

So, B will complete the remaining work in 11 days.

Summary of Steps

Step Description Calculation
1 A's daily work rate $\frac{1}{14}$
2 B's daily work rate $\frac{1}{21}$
3 Combined daily work rate (A + B) $\frac{1}{14} + \frac{1}{21} = \frac{5}{42}$
4 Work done by A & B in 4 days $\frac{5}{42} \times 4 = \frac{10}{21}$
5 Remaining work $1 - \frac{10}{21} = \frac{11}{21}$
6 Time taken by B for remaining work $\frac{11/21}{1/21} = 11$ days

Revision Table: Work and Time Concepts

Concept Explanation Formula
Individual Work Rate Amount of work done by one person in one unit of time. If a person finishes work in 'd' days, rate = $\frac{1}{d}$ per day.
Total Work The entire task to be completed, usually represented as 1 unit. $-$
Work Done Rate $\times$ Time Work = Rate $\times$ Time
Time Taken $\frac{\text{Total Work}}{\text{Rate}}$ or $\frac{\text{Amount of Work}}{\text{Rate}}$ Time = $\frac{\text{Work}}{\text{Rate}}$
Combined Rate Sum of individual rates when multiple people work together. Rate(A+B) = Rate(A) + Rate(B)

Additional Information on Work and Time Problems

Work and time problems are a common topic in quantitative aptitude. They often involve scenarios where multiple people work on a task, sometimes starting or leaving at different times. Understanding the concept of work rate is key to solving these problems.

  • The total work is usually treated as a single unit (1).
  • If a person works for 't' days at a rate of 'r' per day, the work done is 'r $\times$ t'.
  • If multiple people work together, their rates add up to find the combined rate.
  • Problems might involve efficiency (how fast someone works), which is directly related to their work rate. Higher efficiency means a higher work rate and less time taken.
  • Sometimes, the work is measured in units (like pages typed, articles made), but often it's just considered a total task to be completed.
Was this answer helpful?

Important Questions from Work Efficiency

  1. A and B working together can complete a job in 30 days. The ratio of their efficiencies is 3 : 2. In how many days can the faster person complete the job?

  2. A takes 15 days to complete \(\frac{5}{7} \)  of a work. With the help of B, they finish the whole work in 12 days. In how many days, B alone will complete the same work

  3. For completing a certain work, A is 50% less efficient than B and B is 50% more efficient than C. Working together A, B and C can complete the work in 48 days. A alone can complete the same work in:

  4. 30 persons can do a piece of work in 24 days. How many more persons are required to complete the work in 20 days?

  5. X is twice as good as workman as Y. Together, they finish the work in 18 days. In how many days can it be done by each separately?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App