All Exams Test series for 1 year @ ₹349 only
Question

A,B and C can do a piece of work in 30 days, 40 days and 50 days, respectively. Beginning with A, if A, B and C do the work alternatively then in how many days will the work be finished?

This question was previously asked in
SSC CGL 2023 (Tier-II) Paper 1 Previous Year Paper (26-Oct-2023) (Shift-1)
The correct answer is \(38\frac{1}{12}\)

Understanding the Work and Time Problem

This problem involves calculating the total time taken to complete a piece of work when three individuals, A, B, and C, work on it alternatively. Each person takes a different amount of time to finish the entire work individually. They work in a specific order: A first, then B, then C, and this sequence repeats until the work is done.

Calculating Total Work Units (LCM Method)

To solve problems like this, we first need a common unit for the total work. This is usually done by finding the Least Common Multiple (LCM) of the individual times taken by each person. The LCM represents the total number of work units that need to be completed.

  • A completes the work in 30 days.
  • B completes the work in 40 days.
  • C completes the work in 50 days.

Total work units = \( \text{LCM}(30, 40, 50) \)

Let's find the prime factors:

  • \(30 = 2 \times 3 \times 5\)
  • \(40 = 2^3 \times 5\)
  • \(50 = 2 \times 5^2\)

LCM is found by taking the highest power of all prime factors involved:

\(\text{LCM}(30, 40, 50) = 2^3 \times 3 \times 5^2 = 8 \times 3 \times 25 = 24 \times 25 = 600\)

So, let the total work be 600 units.

Determining Individual Work Rates (Efficiency)

Now that we have the total work units, we can find out how many units each person completes per day. This is their work rate or efficiency.

  • A's work rate = Total work / Days A takes = \( \frac{600}{30} = 20 \) units/day
  • B's work rate = Total work / Days B takes = \( \frac{600}{40} = 15 \) units/day
  • C's work rate = Total work / Days C takes = \( \frac{600}{50} = 12 \) units/day

Calculating Work Done in One Alternative Cycle

The individuals A, B, and C work alternatively, starting with A. One full cycle consists of A working on day 1, B working on day 2, and C working on day 3. After 3 days, the cycle repeats.

Work done in one cycle (3 days) = Work by A in 1 day + Work by B in 1 day + Work by C in 1 day

Work done in one cycle = \( 20 + 15 + 12 = 47 \) units.

Calculating Full Cycles and Remaining Work

We need to find out how many full cycles of A, B, C are completed before the work is almost finished. We divide the total work by the work done in one cycle.

Number of full cycles = \( \lfloor \frac{\text{Total Work}}{\text{Work done in one cycle}} \rfloor = \lfloor \frac{600}{47} \rfloor \)

\(600 \div 47\)

Operation Result Remainder
\(47 \times 10\) 470 \(600 - 470 = 130\)
\(47 \times 2\) 94 \(130 - 94 = 36\)
Total (10+2) \(47 \times 12 = 564\) 36

\(600 = 47 \times 12 + 36\)

This means 12 full cycles of A, B, C working are completed.

Days taken for 12 full cycles = \(12 \text{ cycles} \times 3 \text{ days/cycle} = 36 \text{ days}\).

Work done in 12 full cycles = \(12 \times 47 = 564\) units.

Remaining work = Total work - Work done in full cycles = \(600 - 564 = 36\) units.

Completing the Remaining Work

After 36 days, 564 units of work are done, and 36 units remain. The work starts with A again for the 13th cycle.

  • Day 37: A works. A does 20 units. Remaining work = \(36 - 20 = 16\) units.
  • Day 38: B works. B does 15 units. Remaining work = \(16 - 15 = 1\) unit.
  • Day 39: C is scheduled to work. C's work rate is 12 units/day. The remaining work is 1 unit.

Time taken by C to finish the remaining 1 unit of work = \( \frac{\text{Remaining work}}{\text{C's work rate}} = \frac{1}{12} \) days.

Total Time Taken to Finish the Work

Total days = Days for 12 full cycles + Days A worked on remaining + Days B worked on remaining + Days C worked on remaining

Total days = \( 36 \text{ days} + 1 \text{ day (by A)} + 1 \text{ day (by B)} + \frac{1}{12} \text{ days (by C)} \)

Total days = \( 36 + 1 + 1 + \frac{1}{12} = 38 + \frac{1}{12} = 38\frac{1}{12} \) days.

So, the work will be finished in \(38\frac{1}{12}\) days.

Worker Days to Finish Alone Work Rate (units/day)
A 30 20
B 40 15
C 50 12

Stage Days Taken Work Done Cumulative Work Remaining Work
1 Cycle (A, B, C) 3 47 47 \(600 - 47 = 553\)
12 Cycles (A, B, C) \(12 \times 3 = 36\) \(12 \times 47 = 564\) 564 \(600 - 564 = 36\)
Day 37 (A) 1 20 \(564 + 20 = 584\) \(36 - 20 = 16\)
Day 38 (B) 1 15 \(584 + 15 = 599\) \(16 - 15 = 1\)
Day 39 (C) \(1/12\) 1 \(599 + 1 = 600\) \(1 - 1 = 0\)
Total \(36 + 1 + 1 + 1/12 = 38\frac{1}{12}\) 600 600 0

Work and Time Revision Table

Concept Description Formula/Method
Total Work Represented as a quantity, often LCM of individual times. \( \text{LCM}(\text{Time}_1, \text{Time}_2, ...) \)
Work Rate (Efficiency) Amount of work done by a person in one unit of time (e.g., 1 day). \( \text{Work Rate} = \frac{\text{Total Work}}{\text{Time Taken}} \)
Alternative Work Individuals work in sequence, not simultaneously. Calculate work done per cycle of workers.
Work Done Work Rate × Time \( W = R \times T \)
Time Taken Total Work / Work Rate \( T = \frac{W}{R} \)

Additional Information on Work and Time Problems

Work and Time problems are a common topic in quantitative aptitude. Understanding the relationship between work, time, and efficiency (work rate) is key. Here are some points to remember:

  • Work is generally considered constant in a specific problem unless stated otherwise.
  • Efficiency and Time are inversely proportional. If a person is more efficient, they take less time to complete the same amount of work.
  • When people work together simultaneously, their work rates are added up.
  • When people work alternatively, you calculate the work done in one cycle (which spans over the number of days equal to the number of workers in the cycle) and then find out how many cycles are needed.
  • Always handle the remaining work carefully after full cycles, as the next person in the sequence will start the remainder.

These principles help in solving various types of work and time problems, whether involving individuals, groups, or machines working together or alternatively.

Was this answer helpful?

Similar Questions

  1. Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?

  2. To do a certain work, A and B work on alternate days with B beginning the work on the first day. A alone can complete the same work in 24 days. If the work gets completed in  \(11 \frac{1}{3}\)  days, then B alone can complete  \(\rm \frac{7}{9}^{th}\)  part of the original work in:

  3. 20 women and 15 men together can complete a work in 6 days. It takes 150 days for a single woman to complete the work. In how many days can a single man complete the work?

  4. 15 men and 25 women can complete a piece of work in 9.6 days. If 16 women can complete the same work in 27 days, find the number of days in which 16 men can complete the same work.  

  5. Ram can complete a piece work in 15 days, Rohan in 25 days, and Rohit in 30 days. Rohan and Rohit worked together for 2 days and then Rohit was replaced by Ram. In how many days altogether was the work completed?

  6. R, S and T can finish a work in 20, 15 and 10 days, respectively. R works on all days and S and T work on alternate days with T starting the work on the first day. In how many days is the work finished?

  7. A can do \(1 \over 3\) of a piece of work in 32 days, B can do \(37{1 \over 2}\)% of the same work in 24 days, while C can do 60% of the same work in 48 days. B and C together started and worked for x days. After x days, B left the work and A joined C and both completed the remaining work in (x + 8) days. If the ratio of the work done by (B + C) together to the work done by (A + C) together is 9 ∶ 11, then what fraction of the same work can be completed by C alone in 3.5x days?

  8. A group of college students had decided to complete a project in 10 days. As 2 students dropped out every day, the project got completed at the end of the 15th day. The number of students at the beginning of the project was:

  9. Aarif, Arun and Abraham can do a work in 12, 20 and 24 days, respectively. They all begin together. Arun leaves the work 3 days and Abraham 6 days before its completion. In how many days is the work finished?

  10. 15 men can complete a work in 25 days, and 25 women can complete the same work in 40 days. If all 15 men and 25 women work together, in how many days will the work get completed?


Important Questions from Work Efficiency

  1. Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?

  2. A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?

  3. 24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?

  4. A and B together can do a piece of work in 4 days, B and C can do it in 6 days, A and C can do it in 8 days. Then A, B and C together can do the same work in :-

  5. A can complete 50% of a work in 9 days and B can do 25% of the work in 9 days, if they work alone. If they work together then how much work (in percentage) can be completed in 6 days?

Need Expert Advice?
Upcoming Exams
SSC CGL
September 30, 2026
UPSSSC PET
October 23, 2026
Test Series
SSC CGL img
SSC
SSC CGL (Tier I + Tier II) 2026 Mock Test Series - Latest Pattern
2503 Tests 6 Tests Free
5326 Attempts
4.2(866)
English, Hindi

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App