A,B and C can do a piece of work in 30 days, 40 days and 50 days, respectively. Beginning with A, if A, B and C do the work alternatively then in how many days will the work be finished?
This problem involves calculating the total time taken to complete a piece of work when three individuals, A, B, and C, work on it alternatively. Each person takes a different amount of time to finish the entire work individually. They work in a specific order: A first, then B, then C, and this sequence repeats until the work is done.
To solve problems like this, we first need a common unit for the total work. This is usually done by finding the Least Common Multiple (LCM) of the individual times taken by each person. The LCM represents the total number of work units that need to be completed.
Total work units = \( \text{LCM}(30, 40, 50) \)
Let's find the prime factors:
LCM is found by taking the highest power of all prime factors involved:
\(\text{LCM}(30, 40, 50) = 2^3 \times 3 \times 5^2 = 8 \times 3 \times 25 = 24 \times 25 = 600\)
So, let the total work be 600 units.
Now that we have the total work units, we can find out how many units each person completes per day. This is their work rate or efficiency.
The individuals A, B, and C work alternatively, starting with A. One full cycle consists of A working on day 1, B working on day 2, and C working on day 3. After 3 days, the cycle repeats.
Work done in one cycle (3 days) = Work by A in 1 day + Work by B in 1 day + Work by C in 1 day
Work done in one cycle = \( 20 + 15 + 12 = 47 \) units.
We need to find out how many full cycles of A, B, C are completed before the work is almost finished. We divide the total work by the work done in one cycle.
Number of full cycles = \( \lfloor \frac{\text{Total Work}}{\text{Work done in one cycle}} \rfloor = \lfloor \frac{600}{47} \rfloor \)
\(600 \div 47\)
| Operation | Result | Remainder |
|---|---|---|
| \(47 \times 10\) | 470 | \(600 - 470 = 130\) |
| \(47 \times 2\) | 94 | \(130 - 94 = 36\) |
| Total (10+2) | \(47 \times 12 = 564\) | 36 |
\(600 = 47 \times 12 + 36\)
This means 12 full cycles of A, B, C working are completed.
Days taken for 12 full cycles = \(12 \text{ cycles} \times 3 \text{ days/cycle} = 36 \text{ days}\).
Work done in 12 full cycles = \(12 \times 47 = 564\) units.
Remaining work = Total work - Work done in full cycles = \(600 - 564 = 36\) units.
After 36 days, 564 units of work are done, and 36 units remain. The work starts with A again for the 13th cycle.
Time taken by C to finish the remaining 1 unit of work = \( \frac{\text{Remaining work}}{\text{C's work rate}} = \frac{1}{12} \) days.
Total days = Days for 12 full cycles + Days A worked on remaining + Days B worked on remaining + Days C worked on remaining
Total days = \( 36 \text{ days} + 1 \text{ day (by A)} + 1 \text{ day (by B)} + \frac{1}{12} \text{ days (by C)} \)
Total days = \( 36 + 1 + 1 + \frac{1}{12} = 38 + \frac{1}{12} = 38\frac{1}{12} \) days.
So, the work will be finished in \(38\frac{1}{12}\) days.
| Worker | Days to Finish Alone | Work Rate (units/day) |
|---|---|---|
| A | 30 | 20 |
| B | 40 | 15 |
| C | 50 | 12 |
| Stage | Days Taken | Work Done | Cumulative Work | Remaining Work |
|---|---|---|---|---|
| 1 Cycle (A, B, C) | 3 | 47 | 47 | \(600 - 47 = 553\) |
| 12 Cycles (A, B, C) | \(12 \times 3 = 36\) | \(12 \times 47 = 564\) | 564 | \(600 - 564 = 36\) |
| Day 37 (A) | 1 | 20 | \(564 + 20 = 584\) | \(36 - 20 = 16\) |
| Day 38 (B) | 1 | 15 | \(584 + 15 = 599\) | \(16 - 15 = 1\) |
| Day 39 (C) | \(1/12\) | 1 | \(599 + 1 = 600\) | \(1 - 1 = 0\) |
| Total | \(36 + 1 + 1 + 1/12 = 38\frac{1}{12}\) | 600 | 600 | 0 |
| Concept | Description | Formula/Method |
|---|---|---|
| Total Work | Represented as a quantity, often LCM of individual times. | \( \text{LCM}(\text{Time}_1, \text{Time}_2, ...) \) |
| Work Rate (Efficiency) | Amount of work done by a person in one unit of time (e.g., 1 day). | \( \text{Work Rate} = \frac{\text{Total Work}}{\text{Time Taken}} \) |
| Alternative Work | Individuals work in sequence, not simultaneously. | Calculate work done per cycle of workers. |
| Work Done | Work Rate × Time | \( W = R \times T \) |
| Time Taken | Total Work / Work Rate | \( T = \frac{W}{R} \) |
Work and Time problems are a common topic in quantitative aptitude. Understanding the relationship between work, time, and efficiency (work rate) is key. Here are some points to remember:
These principles help in solving various types of work and time problems, whether involving individuals, groups, or machines working together or alternatively.
Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?
To do a certain work, A and B work on alternate days with B beginning the work on the first day. A alone can complete the same work in 24 days. If the work gets completed in \(11 \frac{1}{3}\) days, then B alone can complete \(\rm \frac{7}{9}^{th}\) part of the original work in:
20 women and 15 men together can complete a work in 6 days. It takes 150 days for a single woman to complete the work. In how many days can a single man complete the work?
15 men and 25 women can complete a piece of work in 9.6 days. If 16 women can complete the same work in 27 days, find the number of days in which 16 men can complete the same work.
Ram can complete a piece work in 15 days, Rohan in 25 days, and Rohit in 30 days. Rohan and Rohit worked together for 2 days and then Rohit was replaced by Ram. In how many days altogether was the work completed?
R, S and T can finish a work in 20, 15 and 10 days, respectively. R works on all days and S and T work on alternate days with T starting the work on the first day. In how many days is the work finished?
A can do \(1 \over 3\) of a piece of work in 32 days, B can do \(37{1 \over 2}\)% of the same work in 24 days, while C can do 60% of the same work in 48 days. B and C together started and worked for x days. After x days, B left the work and A joined C and both completed the remaining work in (x + 8) days. If the ratio of the work done by (B + C) together to the work done by (A + C) together is 9 ∶ 11, then what fraction of the same work can be completed by C alone in 3.5x days?
A group of college students had decided to complete a project in 10 days. As 2 students dropped out every day, the project got completed at the end of the 15th day. The number of students at the beginning of the project was:
Aarif, Arun and Abraham can do a work in 12, 20 and 24 days, respectively. They all begin together. Arun leaves the work 3 days and Abraham 6 days before its completion. In how many days is the work finished?
15 men can complete a work in 25 days, and 25 women can complete the same work in 40 days. If all 15 men and 25 women work together, in how many days will the work get completed?
Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?
A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?
24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?
A and B together can do a piece of work in 4 days, B and C can do it in 6 days, A and C can do it in 8 days. Then A, B and C together can do the same work in :-
A can complete 50% of a work in 9 days and B can do 25% of the work in 9 days, if they work alone. If they work together then how much work (in percentage) can be completed in 6 days?