All Exams Test series for 1 year @ ₹349 only
Question

A,B and C can do a piece of work in 30 days, 40 days and 50 days, respectively. Beginning with A, if A, B and C do the work alternatively then in how many days will the work be finished?

This question was previously asked in
SSC CGL 2023 (Tier-II) Paper 1 Previous Year Paper (26-Oct-2023) (Shift-1)
The correct answer is \(38\frac{1}{12}\)

Understanding the Work and Time Problem

This problem involves calculating the total time taken to complete a piece of work when three individuals, A, B, and C, work on it alternatively. Each person takes a different amount of time to finish the entire work individually. They work in a specific order: A first, then B, then C, and this sequence repeats until the work is done.

Calculating Total Work Units (LCM Method)

To solve problems like this, we first need a common unit for the total work. This is usually done by finding the Least Common Multiple (LCM) of the individual times taken by each person. The LCM represents the total number of work units that need to be completed.

  • A completes the work in 30 days.
  • B completes the work in 40 days.
  • C completes the work in 50 days.

Total work units = \( \text{LCM}(30, 40, 50) \)

Let's find the prime factors:

  • \(30 = 2 \times 3 \times 5\)
  • \(40 = 2^3 \times 5\)
  • \(50 = 2 \times 5^2\)

LCM is found by taking the highest power of all prime factors involved:

\(\text{LCM}(30, 40, 50) = 2^3 \times 3 \times 5^2 = 8 \times 3 \times 25 = 24 \times 25 = 600\)

So, let the total work be 600 units.

Determining Individual Work Rates (Efficiency)

Now that we have the total work units, we can find out how many units each person completes per day. This is their work rate or efficiency.

  • A's work rate = Total work / Days A takes = \( \frac{600}{30} = 20 \) units/day
  • B's work rate = Total work / Days B takes = \( \frac{600}{40} = 15 \) units/day
  • C's work rate = Total work / Days C takes = \( \frac{600}{50} = 12 \) units/day

Calculating Work Done in One Alternative Cycle

The individuals A, B, and C work alternatively, starting with A. One full cycle consists of A working on day 1, B working on day 2, and C working on day 3. After 3 days, the cycle repeats.

Work done in one cycle (3 days) = Work by A in 1 day + Work by B in 1 day + Work by C in 1 day

Work done in one cycle = \( 20 + 15 + 12 = 47 \) units.

Calculating Full Cycles and Remaining Work

We need to find out how many full cycles of A, B, C are completed before the work is almost finished. We divide the total work by the work done in one cycle.

Number of full cycles = \( \lfloor \frac{\text{Total Work}}{\text{Work done in one cycle}} \rfloor = \lfloor \frac{600}{47} \rfloor \)

\(600 \div 47\)

Operation Result Remainder
\(47 \times 10\) 470 \(600 - 470 = 130\)
\(47 \times 2\) 94 \(130 - 94 = 36\)
Total (10+2) \(47 \times 12 = 564\) 36

\(600 = 47 \times 12 + 36\)

This means 12 full cycles of A, B, C working are completed.

Days taken for 12 full cycles = \(12 \text{ cycles} \times 3 \text{ days/cycle} = 36 \text{ days}\).

Work done in 12 full cycles = \(12 \times 47 = 564\) units.

Remaining work = Total work - Work done in full cycles = \(600 - 564 = 36\) units.

Completing the Remaining Work

After 36 days, 564 units of work are done, and 36 units remain. The work starts with A again for the 13th cycle.

  • Day 37: A works. A does 20 units. Remaining work = \(36 - 20 = 16\) units.
  • Day 38: B works. B does 15 units. Remaining work = \(16 - 15 = 1\) unit.
  • Day 39: C is scheduled to work. C's work rate is 12 units/day. The remaining work is 1 unit.

Time taken by C to finish the remaining 1 unit of work = \( \frac{\text{Remaining work}}{\text{C's work rate}} = \frac{1}{12} \) days.

Total Time Taken to Finish the Work

Total days = Days for 12 full cycles + Days A worked on remaining + Days B worked on remaining + Days C worked on remaining

Total days = \( 36 \text{ days} + 1 \text{ day (by A)} + 1 \text{ day (by B)} + \frac{1}{12} \text{ days (by C)} \)

Total days = \( 36 + 1 + 1 + \frac{1}{12} = 38 + \frac{1}{12} = 38\frac{1}{12} \) days.

So, the work will be finished in \(38\frac{1}{12}\) days.

Worker Days to Finish Alone Work Rate (units/day)
A 30 20
B 40 15
C 50 12

Stage Days Taken Work Done Cumulative Work Remaining Work
1 Cycle (A, B, C) 3 47 47 \(600 - 47 = 553\)
12 Cycles (A, B, C) \(12 \times 3 = 36\) \(12 \times 47 = 564\) 564 \(600 - 564 = 36\)
Day 37 (A) 1 20 \(564 + 20 = 584\) \(36 - 20 = 16\)
Day 38 (B) 1 15 \(584 + 15 = 599\) \(16 - 15 = 1\)
Day 39 (C) \(1/12\) 1 \(599 + 1 = 600\) \(1 - 1 = 0\)
Total \(36 + 1 + 1 + 1/12 = 38\frac{1}{12}\) 600 600 0

Work and Time Revision Table

Concept Description Formula/Method
Total Work Represented as a quantity, often LCM of individual times. \( \text{LCM}(\text{Time}_1, \text{Time}_2, ...) \)
Work Rate (Efficiency) Amount of work done by a person in one unit of time (e.g., 1 day). \( \text{Work Rate} = \frac{\text{Total Work}}{\text{Time Taken}} \)
Alternative Work Individuals work in sequence, not simultaneously. Calculate work done per cycle of workers.
Work Done Work Rate × Time \( W = R \times T \)
Time Taken Total Work / Work Rate \( T = \frac{W}{R} \)

Additional Information on Work and Time Problems

Work and Time problems are a common topic in quantitative aptitude. Understanding the relationship between work, time, and efficiency (work rate) is key. Here are some points to remember:

  • Work is generally considered constant in a specific problem unless stated otherwise.
  • Efficiency and Time are inversely proportional. If a person is more efficient, they take less time to complete the same amount of work.
  • When people work together simultaneously, their work rates are added up.
  • When people work alternatively, you calculate the work done in one cycle (which spans over the number of days equal to the number of workers in the cycle) and then find out how many cycles are needed.
  • Always handle the remaining work carefully after full cycles, as the next person in the sequence will start the remainder.

These principles help in solving various types of work and time problems, whether involving individuals, groups, or machines working together or alternatively.

Was this answer helpful?

Similar Questions

  1. X and Y can complete a work in 9 days and 36 days, respectively. X begins to do the work and they work alternately one at a time for one day each. The whole work will be complete in:

  2. P is two times as efficient as Q. P is able to complete a piece of work in 40 days less than Q. Working together, the whole number of days taken by them to complete the work is:

    (Round off to the nearest integer)

  3. 4 women or 6 boys can finish a work in the same number of days. A boy can finish it in 60 days. In how many days can 5 women finish the work, working together every day?

  4. To do a certain work, Ajay and Bharat work on alternate days, with Bharat starting the work on the first day. Ajay can finish the work alone in 32 days. If the work gets completed in exactly 8 days, then Bharat alone can finish 7 times the same work in ____________ days.

  5. A, B and C can separately complete a work in 12, 15 and 20 days, respectively. They worked together 4 days. What will be the remaining work?

  6. A, B and C, working alone, can complete a job in 16, 24 and 36 days, respectively. In how many days can they complete the job if they work together?

  7. Rakshit, Ajay, and Satish are sanitation workers in a Municipal Corporation. Rakshit alone takes 20 hours to clean a drain while Ajay takes 12 hours when working alone to do the same. All three together take only 5 hours to clean the drain. In how many hours, can Satish complete the work alone?

  8. 15 men and 25 women can complete a piece of work in 9.6 days. If 16 women can complete the same work in 27 days, find the number of days in which 16 men can complete the same work.  

  9. Ravi can do a piece of work in 40 days and Sudha can do the same piece of work in 60 days. If they work on alternative days starting with Sudha on the first day, then in how many days will the work be completed?

  10. Working 5 hours a day, A can complete a task in 8 days and working 6 hours a day, B can finish the same task in 10 days, working 8 hours a day, they can jointly complete the task in __________.


Important Questions from Work Efficiency

  1. A and B working together can complete a job in 30 days. The ratio of their efficiencies is 3 : 2. In how many days can the faster person complete the job?

  2. A takes 15 days to complete \(\frac{5}{7} \)  of a work. With the help of B, they finish the whole work in 12 days. In how many days, B alone will complete the same work

  3. A alone can complete a work in 14 days and B alone can complete the same work in 21 days. A and B start the work together but A leaves the work after 4 days of the starting of work. In how many days B will complete the remaining work?

  4. For completing a certain work, A is 50% less efficient than B and B is 50% more efficient than C. Working together A, B and C can complete the work in 48 days. A alone can complete the same work in:

  5. 30 persons can do a piece of work in 24 days. How many more persons are required to complete the work in 20 days?

Need Expert Advice?
Upcoming Exams
SSC JHT
September 08, 2026
SSC Stenographer
September 09, 2026
SSC Selection Post
September 16, 2026
Test Series
SSC CGL img
SSC
SSC CGL (Tier I + Tier II) 2026 Mock Test Series - Latest Pattern
2500 Tests 6 Tests Free
3981 Attempts
4.2(838)
English, Hindi

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App