A can do \(1 \over 3\) of a piece of work in 32 days, B can do \(37{1 \over 2}\)% of the same work in 24 days, while C can do 60% of the same work in 48 days. B and C together started and worked for x days. After x days, B left the work and A joined C and both completed the remaining work in (x + 8) days. If the ratio of the work done by (B + C) together to the work done by (A + C) together is 9 ∶ 11, then what fraction of the same work can be completed by C alone in 3.5x days?
This question involves calculating the work rates of three individuals, A, B, and C, and then determining the fraction of work C can complete alone based on conditions involving their combined work and a specific time duration.
First, let's find the time each person takes to complete the entire work alone and their respective daily work rates.
A can do \( \frac{1}{3} \) of the work in 32 days.
Time taken by A to complete the whole work = \( 32 \text{ days} \div \frac{1}{3} = 32 \times 3 = 96 \text{ days} \).
A's daily work rate = \( \frac{1}{\text{Time taken by A}} = \frac{1}{96} \) of the work per day.
B can do \( 37\frac{1}{2}\)% of the work in 24 days.
\( 37\frac{1}{2}\)% as a fraction is \( \frac{37.5}{100} = \frac{75/2}{100} = \frac{75}{200} = \frac{3}{8} \).
So, B can do \( \frac{3}{8} \) of the work in 24 days.
Time taken by B to complete the whole work = \( 24 \text{ days} \div \frac{3}{8} = 24 \times \frac{8}{3} = 8 \times 8 = 64 \text{ days} \).
B's daily work rate = \( \frac{1}{\text{Time taken by B}} = \frac{1}{64} \) of the work per day.
C can do 60% of the work in 48 days.
60% as a fraction is \( \frac{60}{100} = \frac{3}{5} \).
So, C can do \( \frac{3}{5} \) of the work in 48 days.
Time taken by C to complete the whole work = \( 48 \text{ days} \div \frac{3}{5} = 48 \times \frac{5}{3} = 16 \times 5 = 80 \text{ days} \).
C's daily work rate = \( \frac{1}{\text{Time taken by C}} = \frac{1}{80} \) of the work per day.
| Person | Time to complete work alone | Daily Work Rate |
|---|---|---|
| A | 96 days | \( \frac{1}{96} \) |
| B | 64 days | \( \frac{1}{64} \) |
| C | 80 days | \( \frac{1}{80} \) |
The work is completed in two phases:
\( \text{Rate}_{B+C} = \text{Rate}_B + \text{Rate}_C = \frac{1}{64} + \frac{1}{80} \)
To add these fractions, find the Least Common Multiple (LCM) of 64 and 80. LCM(64, 80) = 320.
\( \text{Rate}_{B+C} = \frac{1 \times 5}{64 \times 5} + \frac{1 \times 4}{80 \times 4} = \frac{5}{320} + \frac{4}{320} = \frac{5+4}{320} = \frac{9}{320} \) of the work per day.
\( \text{Rate}_{A+C} = \text{Rate}_A + \text{Rate}_C = \frac{1}{96} + \frac{1}{80} \)
To add these fractions, find the LCM of 96 and 80. LCM(96, 80) = 480.
\( \text{Rate}_{A+C} = \frac{1 \times 5}{96 \times 5} + \frac{1 \times 6}{80 \times 6} = \frac{5}{480} + \frac{6}{480} = \frac{5+6}{480} = \frac{11}{480} \) of the work per day.
\( W_{B+C} = \text{Rate}_{B+C} \times x = \frac{9}{320} \times x = \frac{9x}{320} \)
\( W_{A+C} = \text{Rate}_{A+C} \times (x+8) = \frac{11}{480} \times (x+8) \)
The question states that the ratio of the work done by (B + C) together to the work done by (A + C) together is 9 : 11. Based on the problem structure, this ratio likely refers to the work done during the specific periods mentioned for each group (Phase 1 vs Phase 2).
So, \( W_{B+C} : W_{A+C} = 9 : 11 \).
\( \frac{9x}{320} : \frac{11(x+8)}{480} = 9 : 11 \)
\( \frac{\frac{9x}{320}}{\frac{11(x+8)}{480}} = \frac{9}{11} \)
\( \frac{9x}{320} \times \frac{480}{11(x+8)} = \frac{9}{11} \)
Cancel out 9 from both numerators and 11 from both denominators:
\( \frac{x}{320} \times \frac{480}{x+8} = 1 \)
\( \frac{480x}{320(x+8)} = 1 \)
Simplify the fraction \( \frac{480}{320} = \frac{48}{32} = \frac{3}{2} \).
\( \frac{3x}{2(x+8)} = 1 \)
\( 3x = 2(x+8) \)
\( 3x = 2x + 16 \)
\( 3x - 2x = 16 \)
\( x = 16 \)
If \( x = 16 \) days:
Total work done = Work in Phase 1 + Work in Phase 2 = \( \frac{9}{20} + \frac{11}{20} = \frac{20}{20} = 1 \). This confirms that \( x=16 \) is correct as the total work is completed.
The ratio of work done in Phase 1 to Phase 2 is \( \frac{9}{20} : \frac{11}{20} = 9 : 11 \), which matches the condition given in the question.
We need to find the fraction of work C can complete alone in \( 3.5x \) days.
Simplify the fraction \( \frac{56}{80} \). Both numerator and denominator are divisible by 8.
\( \frac{56 \div 8}{80 \div 8} = \frac{7}{10} \).
So, C alone can complete \( \frac{7}{10} \) of the work in \( 3.5x \) days.
The fraction of the same work that can be completed by C alone in \( 3.5x \) days is \( \frac{7}{10} \).
| Description | Calculation | Result |
|---|---|---|
| A's time to complete work | \( 32 / (1/3) \) | 96 days |
| B's time to complete work | \( 24 / (3/8) \) | 64 days |
| C's time to complete work | \( 48 / (3/5) \) | 80 days |
| B + C daily work rate | \( 1/64 + 1/80 \) | \( 9/320 \) |
| A + C daily work rate | \( 1/96 + 1/80 \) | \( 11/480 \) |
| Equation from ratio | \( \frac{9x/320}{11(x+8)/480} = \frac{9}{11} \) | \( x = 16 \) |
| Time for C alone | \( 3.5 \times x \) | 56 days |
| Work by C in 56 days | \( 1/80 \times 56 \) | \( 7/10 \) |
Time and work problems often involve calculating individual efficiency and then combining or comparing the work done by multiple individuals over specific periods.
Understanding these basic principles is key to solving complex time and work problems like the one discussed here.
To do a certain work, A and B work on alternate days with B beginning the work on the first day. A alone can complete the same work in 24 days. If the work gets completed in \(11 \frac{1}{3}\) days, then B alone can complete \(\rm \frac{7}{9}^{th}\) part of the original work in:
R, S and T can finish a work in 20, 15 and 10 days, respectively. R works on all days and S and T work on alternate days with T starting the work on the first day. In how many days is the work finished?
A group of college students had decided to complete a project in 10 days. As 2 students dropped out every day, the project got completed at the end of the 15th day. The number of students at the beginning of the project was:
A group of men decided to do a job in 13 days but 9 men left the work after each day. The work, as a result, got completed in 16 days. How many men were initially in the group?
Three men and 4 women can do a piece of work in 7 days, whereas 2 men and 1 woman can do it in 14 days. Seven women will complete the same work in:
Five men can complete a work in 20 days. Ten women can complete the same work in 15 days. Two men and six women started working together. After 5 days, three women left the work a new man joined the work. The group continued working together till the end of the work. In how many days will they be able to do the remaining work?
4 men and 5 women can complete a work in 15 days, whereas 9 men and 6 women can do it in 10 days. To complete the same work in 7 days, how many women should assist 4 men?
Four men and 6 women can complete a certain piece of work in 5 days whereas three men and 4 women can complete it in 7 days. How many men should assist 25 women to complete \(2\frac{1}{2}\) times the same work in 5 days?
A can complete a work in 60 days. B is 25% more efficient than A. They work together for 15 days. C alone completes the remaining work in 14 days. B and C together will complete \(\frac{5}{8}\)th part of the original work in:
P can finish a work in 18 days. When he had worked for 5 days, Q joined him. If both of them together completed the remaining work in \(\frac{13}{5} \) days, then in how many days can Q alone finish \(66\frac{2}{3} \) % of the same work?
A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?
24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?
A and B together can do a piece of work in 4 days, B and C can do it in 6 days, A and C can do it in 8 days. Then A, B and C together can do the same work in :-
A can complete 50% of a work in 9 days and B can do 25% of the work in 9 days, if they work alone. If they work together then how much work (in percentage) can be completed in 6 days?
A is thrice as good a workman as B. C alone takes 48 days to paint a house. All three A, B and C working together take 16 days to paint the house. It will take how many days for A alone to paint the house?