All Exams Test series for 1 year @ ₹349 only
Question

4 men and 5 women can complete a work in 15 days, whereas 9 men and 6 women can do it in 10 days. To complete the same work in 7 days, how many women should assist 4 men?

This question was previously asked in
SSC CGL 2018 (Tier 2) Statistics Previous Year Paper (22-feb-2018)
The correct answer is

13

Step 1 — Equate the two work expressions:

Let one man's daily work be \(M\) and one woman's be \(W\). Since the same work is done in both cases:

\[(4M+5W)\times 15 = (9M+6W)\times 10\]

Step 2 — Find the man-woman ratio:

\[60M+75W = 90M+60W \implies 15W = 30M \implies W = 2M\]

Step 3 — Total work in man-units:

\[(4M+5\cdot 2M)\times 15 = 14M\times 15 = 210M\]

Step 4 — Set up the 7-day scenario:

Let \(x\) women assist 4 men. Then:

\[(4M + x\cdot 2M)\times 7 = 210M\]

\[(4+2x)\times 7 = 210 \implies 4+2x = 30 \implies x = 13\]

Therefore 13 women are required.

Was this answer helpful?

Similar Questions

  1. Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?

  2. To do a certain work, A and B work on alternate days with B beginning the work on the first day. A alone can complete the same work in 24 days. If the work gets completed in  \(11 \frac{1}{3}\)  days, then B alone can complete  \(\rm \frac{7}{9}^{th}\)  part of the original work in:

  3. R, S and T can finish a work in 20, 15 and 10 days, respectively. R works on all days and S and T work on alternate days with T starting the work on the first day. In how many days is the work finished?

  4. A can do \(1 \over 3\) of a piece of work in 32 days, B can do \(37{1 \over 2}\)% of the same work in 24 days, while C can do 60% of the same work in 48 days. B and C together started and worked for x days. After x days, B left the work and A joined C and both completed the remaining work in (x + 8) days. If the ratio of the work done by (B + C) together to the work done by (A + C) together is 9 ∶ 11, then what fraction of the same work can be completed by C alone in 3.5x days?

  5. A group of college students had decided to complete a project in 10 days. As 2 students dropped out every day, the project got completed at the end of the 15th day. The number of students at the beginning of the project was:

  6. A group of men decided to do a job in 13 days but 9 men left the work after each day. The work, as a result, got completed in 16 days. How many men were initially in the group?

  7. Working alone A can do a work in 72 days and B in 90 days. If they work on it together for 10 days, then what fraction of work is left?

  8. To do a certain work, A and B work on alternate days, with B beginning the work on the first day. A can finish the work alone in 48 days. If the work gets completed in \(11\frac{1}{3}\) days, then B alone can finish 4 times the same work in:

  9. Three men and 4 women can do a piece of work in 7 days, whereas 2 men and 1 woman can do it in 14 days. Seven women will complete the same work in:

  10. Five men can complete a work in 20 days. Ten women can complete the same work in 15 days. Two men and six women started working together. After 5 days, three women left the work a new man joined the work. The group continued working together till the end of the work. In how many days will they be able to do the remaining work?


Important Questions from Work Efficiency

  1. Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?

  2. A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?

  3. 24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?

  4. A and B together can do a piece of work in 4 days, B and C can do it in 6 days, A and C can do it in 8 days. Then A, B and C together can do the same work in :-

  5. A can complete 50% of a work in 9 days and B can do 25% of the work in 9 days, if they work alone. If they work together then how much work (in percentage) can be completed in 6 days?

Need Expert Advice?
Upcoming Exams
UPSSSC PET
October 25, 2026
SSC JE
November 02, 2026
SSC CPO
November 20, 2026
SSC CHSL
November 30, 2026
Test Series
SSC CGL img
SSC
SSC CGL (Tier I + Tier II) 2026 Mock Test Series - Latest Pattern
2503 Tests 6 Tests Free
7933 Attempts
4.2(908)
English, Hindi

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App