All Exams Test series for 1 year @ ₹349 only
Question

R, S and T can finish a work in 20, 15 and 10 days, respectively. R works on all days and S and T work on alternate days with T starting the work on the first day. In how many days is the work finished?

This question was previously asked in
SSC CGL 2023 (Tier-II) Paper 1 Previous Year Paper (26-Oct-2023) (Shift-1)
The correct answer is

52/7

Work and Time Problem Solution

This problem involves calculating the total time taken by R, S, and T to complete a piece of work, given their individual efficiencies and a specific work pattern.

Understanding Individual Work Rates

First, we need to determine the amount of work each person can complete in one day. This is their work rate.

  • R can finish the work in 20 days. So, R's work rate is $\frac{1}{20}$ of the work per day.
  • S can finish the work in 15 days. So, S's work rate is $\frac{1}{15}$ of the work per day.
  • T can finish the work in 10 days. So, T's work rate is $\frac{1}{10}$ of the work per day.

Analyzing the Work Pattern and Cycle

R works on all days. S and T work on alternate days, with T starting on the first day.

The work pattern is as follows:

  • Day 1: R and T work together.
  • Day 2: R and S work together.
  • Day 3: R and T work together (repeats Day 1).
  • Day 4: R and S work together (repeats Day 2).

This establishes a 2-day cycle involving (R+T) on Day 1 of the cycle and (R+S) on Day 2 of the cycle.

Calculating Work Done in One Cycle

Let's calculate the total work done in one complete 2-day cycle:

  • Work done on Day 1 (R + T): $R's\ rate + T's\ rate = \frac{1}{20} + \frac{1}{10}$
  • To add these fractions, we find a common denominator, which is 20.
  • $\frac{1}{20} + \frac{1}{10} = \frac{1}{20} + \frac{1 \times 2}{10 \times 2} = \frac{1}{20} + \frac{2}{20} = \frac{1+2}{20} = \frac{3}{20}$
  • So, R and T together complete $\frac{3}{20}$ of the work on Day 1 of the cycle.
  • Work done on Day 2 (R + S): $R's\ rate + S's\ rate = \frac{1}{20} + \frac{1}{15}$
  • To add these fractions, we find a common denominator, which is 60.
  • $\frac{1}{20} + \frac{1}{15} = \frac{1 \times 3}{20 \times 3} + \frac{1 \times 4}{15 \times 4} = \frac{3}{60} + \frac{4}{60} = \frac{3+4}{60} = \frac{7}{60}$
  • So, R and S together complete $\frac{7}{60}$ of the work on Day 2 of the cycle.

Total work done in one 2-day cycle:

  • Work per cycle = Work on Day 1 + Work on Day 2
  • Work per cycle = $\frac{3}{20} + \frac{7}{60}$
  • Common denominator is 60.
  • $\frac{3}{20} + \frac{7}{60} = \frac{3 \times 3}{20 \times 3} + \frac{7}{60} = \frac{9}{60} + \frac{7}{60} = \frac{9+7}{60} = \frac{16}{60}$
  • Simplify the fraction: $\frac{16}{60} = \frac{4 \times 4}{15 \times 4} = \frac{4}{15}$
  • In one 2-day cycle, $\frac{4}{15}$ of the work is completed.

Progress Towards Completing the Work

We need to find how many full cycles are completed before the remaining work can be finished in a fraction of a day or one more day. The total work is 1 (or 100%).

Work done after 'n' cycles is $n \times \frac{4}{15}$. We want this value to be close to 1 but not exceed it for full cycles.

  • After 1 cycle (2 days): Work done = $1 \times \frac{4}{15} = \frac{4}{15}$. Remaining work = $1 - \frac{4}{15} = \frac{11}{15}$.
  • After 2 cycles (4 days): Work done = $2 \times \frac{4}{15} = \frac{8}{15}$. Remaining work = $1 - \frac{8}{15} = \frac{7}{15}$.
  • After 3 cycles (6 days): Work done = $3 \times \frac{4}{15} = \frac{12}{15} = \frac{4}{5}$. Remaining work = $1 - \frac{4}{5} = \frac{1}{5}$.
  • After 4 cycles (8 days): Work done = $4 \times \frac{4}{15} = \frac{16}{15}$. This is more than 1, so work finishes before 4 full cycles are completed.

So, 3 full cycles are completed in 6 days. After 6 days, $\frac{4}{5}$ of the work is done, and $\frac{1}{5}$ of the work remains.

Finishing the Remaining Work

After 6 days, the work remaining is $\frac{1}{5}$. The 6 days complete 3 full cycles. The 7th day is the start of the next cycle (Day 1 of the cycle), which means R and T work together.

  • Work remaining = $\frac{1}{5}$.
  • Work rate of R and T together = $\frac{3}{20}$ per day.

Can R and T finish the remaining $\frac{1}{5}$ work in a full day?

  • Work R+T can do in 1 day = $\frac{3}{20}$.
  • Compare remaining work ($\frac{1}{5} = \frac{4}{20}$) with work R+T can do in 1 day ($\frac{3}{20}$).
  • Since $\frac{4}{20} > \frac{3}{20}$, R and T cannot finish the remaining work in one full 7th day. They will complete $\frac{3}{20}$ of the work on Day 7.

Work remaining after 7 days (6 days from cycles + 1 full day of R+T):

  • Work done after 6 days = $\frac{4}{5}$.
  • Work done on Day 7 (R+T) = $\frac{3}{20}$.
  • Total work done after 7 days = $\frac{4}{5} + \frac{3}{20} = \frac{16}{20} + \frac{3}{20} = \frac{19}{20}$.
  • Remaining work after 7 days = $1 - \frac{19}{20} = \frac{1}{20}$.

Now, it's the start of Day 8. This is Day 2 of the work cycle, meaning R and S work together.

  • Work remaining = $\frac{1}{20}$.
  • Work rate of R and S together = $\frac{7}{60}$ per day.

Time taken by R and S to finish the remaining $\frac{1}{20}$ work:

  • Time = $\frac{\text{Remaining Work}}{\text{Rate}} = \frac{\frac{1}{20}}{\frac{7}{60}}$
  • Time = $\frac{1}{20} \times \frac{60}{7} = \frac{60}{140} = \frac{6}{14} = \frac{3}{7}$ days.

So, on the 8th day, R and S work for $\frac{3}{7}$ of the day to finish the remaining work.

Calculating Total Time

Total time taken to finish the work is the sum of the full days worked and the fraction of the last day.

  • Full days worked = 7 days (6 days from 3 cycles + 1 full Day 7)
  • Fraction of the 8th day worked = $\frac{3}{7}$ days
  • Total time = $7 + \frac{3}{7}$ days
  • Total time = $\frac{7 \times 7 + 3}{7} = \frac{49 + 3}{7} = \frac{52}{7}$ days.

The work is finished in $\frac{52}{7}$ days.

Step-by-Step Work Calculation Summary

  • R's rate = $1/20$ work/day
  • S's rate = $1/15$ work/day
  • T's rate = $1/10$ work/day
  • Work on Day 1 (R+T) = $1/20 + 1/10 = 3/20$
  • Work on Day 2 (R+S) = $1/20 + 1/15 = 7/60$
  • Work in 1 cycle (2 days) = $3/20 + 7/60 = 9/60 + 7/60 = 16/60 = 4/15$
  • Work after 3 cycles (6 days) = $3 \times 4/15 = 12/15 = 4/5$
  • Remaining work after 6 days = $1 - 4/5 = 1/5$
  • Day 7 is an R+T day. Work done on Day 7 = $3/20$
  • Remaining work after 7 days = $1/5 - 3/20 = 4/20 - 3/20 = 1/20$
  • Day 8 is an R+S day. Their rate = $7/60$ work/day
  • Time on Day 8 to finish $1/20$ work = $(1/20) / (7/60) = (1/20) \times (60/7) = 3/7$ days
  • Total time = 7 full days + $3/7$ days = $7 + 3/7 = 52/7$ days.
Revision Table: Key Work and Time Concepts
Concept Formula/Explanation
Work Rate If a person finishes work in 'n' days, their rate is $\frac{1}{n}$ per day.
Total Work Usually considered as 1 unit.
Time Taken $\frac{\text{Total Work}}{\text{Work Rate}}$ (if rate is constant).
Work Done Rate $\times$ Time
Combined Rate Sum of individual rates when working together.
Alternate Day Work Calculate work done over a cycle (usually 2 days) and find how many cycles are needed. Address remaining work separately.

Additional Information: Alternate Day Work Problems

Alternate day work problems are a common type in time and work. The key is to identify the repeating cycle of workers and calculate the work done in one such cycle. Then, determine how many full cycles are completed and deal with the remaining work by considering the work rate of the individuals scheduled for the day(s) following the last full cycle. Pay close attention to who starts the work, as this determines the sequence of workers in the cycle.

Was this answer helpful?

Similar Questions

  1. Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?

  2. To do a certain work, A and B work on alternate days with B beginning the work on the first day. A alone can complete the same work in 24 days. If the work gets completed in  \(11 \frac{1}{3}\)  days, then B alone can complete  \(\rm \frac{7}{9}^{th}\)  part of the original work in:

  3. 15 men and 25 women can complete a piece of work in 9.6 days. If 16 women can complete the same work in 27 days, find the number of days in which 16 men can complete the same work.  

  4. A can do \(1 \over 3\) of a piece of work in 32 days, B can do \(37{1 \over 2}\)% of the same work in 24 days, while C can do 60% of the same work in 48 days. B and C together started and worked for x days. After x days, B left the work and A joined C and both completed the remaining work in (x + 8) days. If the ratio of the work done by (B + C) together to the work done by (A + C) together is 9 ∶ 11, then what fraction of the same work can be completed by C alone in 3.5x days?

  5. A group of college students had decided to complete a project in 10 days. As 2 students dropped out every day, the project got completed at the end of the 15th day. The number of students at the beginning of the project was:

  6. Aarif, Arun and Abraham can do a work in 12, 20 and 24 days, respectively. They all begin together. Arun leaves the work 3 days and Abraham 6 days before its completion. In how many days is the work finished?

  7. A,B and C can do a piece of work in 30 days, 40 days and 50 days, respectively. Beginning with A, if A, B and C do the work alternatively then in how many days will the work be finished?

  8. 15 men can complete a work in 25 days, and 25 women can complete the same work in 40 days. If all 15 men and 25 women work together, in how many days will the work get completed?

  9. Working 5 hours a day, A can complete a task in 8 days and working 6 hours a day, B can finish the same task in 10 days, working 8 hours a day, they can jointly complete the task in __________.

  10. A can do 20% of a job in 7 days and B can do 25% of the job in 7 days if they worked alone. How much of the job (in percentage) can they complete in 7 days if they worked together?


Important Questions from Work Efficiency

  1. Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?

  2. A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?

  3. 24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?

  4. A and B together can do a piece of work in 4 days, B and C can do it in 6 days, A and C can do it in 8 days. Then A, B and C together can do the same work in :-

  5. A can complete 50% of a work in 9 days and B can do 25% of the work in 9 days, if they work alone. If they work together then how much work (in percentage) can be completed in 6 days?

Need Expert Advice?
Upcoming Exams
SSC CGL
September 30, 2026
UPSSSC PET
October 23, 2026
Test Series
SSC CGL img
SSC
SSC CGL (Tier I + Tier II) 2026 Mock Test Series - Latest Pattern
2503 Tests 6 Tests Free
5389 Attempts
4.2(868)
English, Hindi

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App