R, S and T can finish a work in 20, 15 and 10 days, respectively. R works on all days and S and T work on alternate days with T starting the work on the first day. In how many days is the work finished?
52/7
This problem involves calculating the total time taken by R, S, and T to complete a piece of work, given their individual efficiencies and a specific work pattern.
First, we need to determine the amount of work each person can complete in one day. This is their work rate.
R works on all days. S and T work on alternate days, with T starting on the first day.
The work pattern is as follows:
This establishes a 2-day cycle involving (R+T) on Day 1 of the cycle and (R+S) on Day 2 of the cycle.
Let's calculate the total work done in one complete 2-day cycle:
Total work done in one 2-day cycle:
We need to find how many full cycles are completed before the remaining work can be finished in a fraction of a day or one more day. The total work is 1 (or 100%).
Work done after 'n' cycles is $n \times \frac{4}{15}$. We want this value to be close to 1 but not exceed it for full cycles.
So, 3 full cycles are completed in 6 days. After 6 days, $\frac{4}{5}$ of the work is done, and $\frac{1}{5}$ of the work remains.
After 6 days, the work remaining is $\frac{1}{5}$. The 6 days complete 3 full cycles. The 7th day is the start of the next cycle (Day 1 of the cycle), which means R and T work together.
Can R and T finish the remaining $\frac{1}{5}$ work in a full day?
Work remaining after 7 days (6 days from cycles + 1 full day of R+T):
Now, it's the start of Day 8. This is Day 2 of the work cycle, meaning R and S work together.
Time taken by R and S to finish the remaining $\frac{1}{20}$ work:
So, on the 8th day, R and S work for $\frac{3}{7}$ of the day to finish the remaining work.
Total time taken to finish the work is the sum of the full days worked and the fraction of the last day.
The work is finished in $\frac{52}{7}$ days.
| Concept | Formula/Explanation |
|---|---|
| Work Rate | If a person finishes work in 'n' days, their rate is $\frac{1}{n}$ per day. |
| Total Work | Usually considered as 1 unit. |
| Time Taken | $\frac{\text{Total Work}}{\text{Work Rate}}$ (if rate is constant). |
| Work Done | Rate $\times$ Time |
| Combined Rate | Sum of individual rates when working together. |
| Alternate Day Work | Calculate work done over a cycle (usually 2 days) and find how many cycles are needed. Address remaining work separately. |
Alternate day work problems are a common type in time and work. The key is to identify the repeating cycle of workers and calculate the work done in one such cycle. Then, determine how many full cycles are completed and deal with the remaining work by considering the work rate of the individuals scheduled for the day(s) following the last full cycle. Pay close attention to who starts the work, as this determines the sequence of workers in the cycle.
Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?
To do a certain work, A and B work on alternate days with B beginning the work on the first day. A alone can complete the same work in 24 days. If the work gets completed in \(11 \frac{1}{3}\) days, then B alone can complete \(\rm \frac{7}{9}^{th}\) part of the original work in:
15 men and 25 women can complete a piece of work in 9.6 days. If 16 women can complete the same work in 27 days, find the number of days in which 16 men can complete the same work.
A can do \(1 \over 3\) of a piece of work in 32 days, B can do \(37{1 \over 2}\)% of the same work in 24 days, while C can do 60% of the same work in 48 days. B and C together started and worked for x days. After x days, B left the work and A joined C and both completed the remaining work in (x + 8) days. If the ratio of the work done by (B + C) together to the work done by (A + C) together is 9 ∶ 11, then what fraction of the same work can be completed by C alone in 3.5x days?
A group of college students had decided to complete a project in 10 days. As 2 students dropped out every day, the project got completed at the end of the 15th day. The number of students at the beginning of the project was:
Aarif, Arun and Abraham can do a work in 12, 20 and 24 days, respectively. They all begin together. Arun leaves the work 3 days and Abraham 6 days before its completion. In how many days is the work finished?
A,B and C can do a piece of work in 30 days, 40 days and 50 days, respectively. Beginning with A, if A, B and C do the work alternatively then in how many days will the work be finished?
15 men can complete a work in 25 days, and 25 women can complete the same work in 40 days. If all 15 men and 25 women work together, in how many days will the work get completed?
Working 5 hours a day, A can complete a task in 8 days and working 6 hours a day, B can finish the same task in 10 days, working 8 hours a day, they can jointly complete the task in __________.
A can do 20% of a job in 7 days and B can do 25% of the job in 7 days if they worked alone. How much of the job (in percentage) can they complete in 7 days if they worked together?
Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?
A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?
24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?
A and B together can do a piece of work in 4 days, B and C can do it in 6 days, A and C can do it in 8 days. Then A, B and C together can do the same work in :-
A can complete 50% of a work in 9 days and B can do 25% of the work in 9 days, if they work alone. If they work together then how much work (in percentage) can be completed in 6 days?