Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?
10
This question is a classic example of a time and work problem where the work rates of different individuals (men and boys) are related. We are given two scenarios where a certain amount of work is completed by different combinations of men and boys in different amounts of time. Our goal is to find the relationship between the work rate of a man and a boy and then use that relationship to determine the number of boys needed in a third scenario.
Let's denote the work rate of one man per day as $M$ and the work rate of one boy per day as $B$. The total work done is the product of the number of workers (adjusted for their individual rates) and the time taken.
According to the first part of the question:
Also, in the same timeframe:
Since the work done is the same in both cases, we can set up the following equation:
$(5M + 2B) \times 30 = (7M + 10B) \times 15$
Now, let's solve this equation to find the relationship between $M$ and $B$:
$(5M + 2B) \times 2 = (7M + 10B) \times 1 \quad \text{(Dividing both sides by 15)}$
$10M + 4B = 7M + 10B$
Rearranging the terms to group $M$ and $B$:
$10M - 7M = 10B - 4B$
$3M = 6B$
Dividing both sides by 3:
$M = 2B$
This tells us that the work rate of one man is equivalent to the work rate of two boys.
Now that we know the relationship between $M$ and $B$, we can calculate the total amount of work. We can use either of the initial scenarios. Let's use the first one (5 men and 2 boys in 30 days) and express the total work in terms of boy-days ($B$).
Total Work $= (5M + 2B) \times 30$
Substitute $M = 2B$ into the equation:
Total Work $= (5 \times (2B) + 2B) \times 30$
Total Work $= (10B + 2B) \times 30$
Total Work $= (12B) \times 30$
Total Work $= 360B$
So, the total work is equivalent to 360 boy-days.
The question asks how many boys should join 40 men to do the same work (360B) in 4 days. Let the number of boys needed be $x$.
The group consists of 40 men and $x$ boys. Their combined work rate per day is $(40M + xB)$.
They need to complete the total work (360B) in 4 days. So, the total work done by this group in 4 days is:
$(40M + xB) \times 4$
We know that $M = 2B$. Substitute this into the equation:
Total Work $= (40 \times (2B) + xB) \times 4$
Total Work $= (80B + xB) \times 4$
Total Work $= (80 + x)B \times 4$
This total work must be equal to 360B:
$(80 + x)B \times 4 = 360B$
Since $B$ represents a work rate, it's a non-zero value. We can divide both sides by $B$:
$(80 + x) \times 4 = 360$
Now, solve for $x$:
$80 + x = \frac{360}{4}$
$80 + x = 90$
$x = 90 - 80$
$x = 10$
Therefore, 10 boys should join the 40 men to complete the work in 4 days.
| Scenario | Workers | Time (days) | Total Work Rate | Total Work Done |
|---|---|---|---|---|
| 1 | 5 Men + 2 Boys | 30 | $5M + 2B$ | $(5M + 2B) \times 30$ |
| 2 | 7 Men + 10 Boys | 15 | $7M + 10B$ | $(7M + 10B) \times 15$ |
| Relationship | $M = 2B$ | |||
| Scenario 3 | 40 Men + $x$ Boys | 4 | $40M + xB$ | $(40M + xB) \times 4$ |
| Concept | Explanation | Formula/Idea |
|---|---|---|
| Work Rate | The amount of work a person or group can do in a unit of time (e.g., per day). | Work Done / Time Taken |
| Total Work | The total amount of task to be completed. Can be represented as 1 unit or in terms of work-days/hours. | Work Rate × Time Taken |
| Combined Work Rate | When multiple people work together, their individual work rates add up. | Sum of individual work rates |
| Efficiency Relationship | If person A is twice as efficient as person B, then A does twice the work of B in the same time, or takes half the time to do the same work. | Efficiency $\propto$ Work Rate $\propto 1 / \text{Time}$ |
Time and work problems often involve inverse proportionality. If a group of workers increases, the time required to complete the same amount of work decreases, assuming their individual work rates remain constant. Conversely, if the work to be done increases, the time required will also increase for the same group of workers.
Problems involving different types of workers (like men and boys) require you to first establish a common unit of work or a relationship between their efficiencies, as we did by finding $M = 2B$. Once this relationship is known, the problem simplifies into a standard time and work calculation.
Always ensure you are consistent with the units. If work rates are per day, time should be in days. The total work will then be in units of 'worker-days' or similar.
For solving such problems efficiently during exams, practice establishing the work rate relationship quickly and converting all workers into equivalent units of the worker with the base efficiency (usually the one assumed to be less efficient, like boys in this case).
A and B together can complete a certain work in 20 days whereas B and C together can complete it in 24 days. If A is twice as good a workman as C, then in what time will B alone do 40% of the same work?
14 men can complete a work in 15 days. If 21 men are employed, then in how many days will they complete the same work?
A can do a certain work in 15 days, while B can do the same work in 21 days. If they work together, then in how many days will the same work be completed?
To do a certain work, A and B work on alternate days with B beginning the work on the first day. A alone can complete the same work in 24 days. If the work gets completed in \(11 \frac{1}{3}\) days, then B alone can complete \(\rm \frac{7}{9}^{th}\) part of the original work in:
Two men and 7 women can complete a work in 28 days whereas 6 men and 16 women can do the same work in 11 days. In how many days can 7 men complete the same work?