All Exams Test series for 1 year @ ₹349 only
Question

Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?

This question was previously asked in
SSC CGL 2020 (Tier-2) Statistics Previous Year Paper 3 (28-Jan-2022)
The correct answer is

10

Understanding the Time and Work Problem

This question is a classic example of a time and work problem where the work rates of different individuals (men and boys) are related. We are given two scenarios where a certain amount of work is completed by different combinations of men and boys in different amounts of time. Our goal is to find the relationship between the work rate of a man and a boy and then use that relationship to determine the number of boys needed in a third scenario.

Establishing the Relationship Between Men and Boys' Work Rates

Let's denote the work rate of one man per day as $M$ and the work rate of one boy per day as $B$. The total work done is the product of the number of workers (adjusted for their individual rates) and the time taken.

According to the first part of the question:

  • 5 men and 2 boys can do a certain amount of work in 30 days.
  • The total work done by this group is $(5M + 2B) \times 30$.

Also, in the same timeframe:

  • 7 men and 10 boys can do the same amount of work in 15 days.
  • The total work done by this group is $(7M + 10B) \times 15$.

Since the work done is the same in both cases, we can set up the following equation:

$(5M + 2B) \times 30 = (7M + 10B) \times 15$

Now, let's solve this equation to find the relationship between $M$ and $B$:

$(5M + 2B) \times 2 = (7M + 10B) \times 1 \quad \text{(Dividing both sides by 15)}$
$10M + 4B = 7M + 10B$

Rearranging the terms to group $M$ and $B$:

$10M - 7M = 10B - 4B$
$3M = 6B$

Dividing both sides by 3:

$M = 2B$

This tells us that the work rate of one man is equivalent to the work rate of two boys.

Calculating the Total Work

Now that we know the relationship between $M$ and $B$, we can calculate the total amount of work. We can use either of the initial scenarios. Let's use the first one (5 men and 2 boys in 30 days) and express the total work in terms of boy-days ($B$).

Total Work $= (5M + 2B) \times 30$

Substitute $M = 2B$ into the equation:

Total Work $= (5 \times (2B) + 2B) \times 30$
Total Work $= (10B + 2B) \times 30$
Total Work $= (12B) \times 30$
Total Work $= 360B$

So, the total work is equivalent to 360 boy-days.

Determining the Number of Boys Required

The question asks how many boys should join 40 men to do the same work (360B) in 4 days. Let the number of boys needed be $x$.

The group consists of 40 men and $x$ boys. Their combined work rate per day is $(40M + xB)$.

They need to complete the total work (360B) in 4 days. So, the total work done by this group in 4 days is:

$(40M + xB) \times 4$

We know that $M = 2B$. Substitute this into the equation:

Total Work $= (40 \times (2B) + xB) \times 4$
Total Work $= (80B + xB) \times 4$
Total Work $= (80 + x)B \times 4$

This total work must be equal to 360B:

$(80 + x)B \times 4 = 360B$

Since $B$ represents a work rate, it's a non-zero value. We can divide both sides by $B$:

$(80 + x) \times 4 = 360$

Now, solve for $x$:

$80 + x = \frac{360}{4}$
$80 + x = 90$
$x = 90 - 80$
$x = 10$

Therefore, 10 boys should join the 40 men to complete the work in 4 days.

Summary of Steps

  1. Define variables for the work rates of men ($M$) and boys ($B$).
  2. Set up an equation based on the first two scenarios where the work done is equal.
  3. Solve the equation to find the relationship between $M$ and $B$.
  4. Calculate the total amount of work using the relationship found and one of the initial scenarios.
  5. Set up an equation for the third scenario (40 men and $x$ boys in 4 days) and equate it to the total work.
  6. Solve the final equation for $x$ to find the number of boys needed.
Scenario Workers Time (days) Total Work Rate Total Work Done
1 5 Men + 2 Boys 30 $5M + 2B$ $(5M + 2B) \times 30$
2 7 Men + 10 Boys 15 $7M + 10B$ $(7M + 10B) \times 15$
Relationship $M = 2B$
Scenario 3 40 Men + $x$ Boys 4 $40M + xB$ $(40M + xB) \times 4$

Revision Table: Key Concepts in Time and Work Problems

Concept Explanation Formula/Idea
Work Rate The amount of work a person or group can do in a unit of time (e.g., per day). Work Done / Time Taken
Total Work The total amount of task to be completed. Can be represented as 1 unit or in terms of work-days/hours. Work Rate × Time Taken
Combined Work Rate When multiple people work together, their individual work rates add up. Sum of individual work rates
Efficiency Relationship If person A is twice as efficient as person B, then A does twice the work of B in the same time, or takes half the time to do the same work. Efficiency $\propto$ Work Rate $\propto 1 / \text{Time}$

Additional Information on Time and Work Calculations

Time and work problems often involve inverse proportionality. If a group of workers increases, the time required to complete the same amount of work decreases, assuming their individual work rates remain constant. Conversely, if the work to be done increases, the time required will also increase for the same group of workers.

Problems involving different types of workers (like men and boys) require you to first establish a common unit of work or a relationship between their efficiencies, as we did by finding $M = 2B$. Once this relationship is known, the problem simplifies into a standard time and work calculation.

Always ensure you are consistent with the units. If work rates are per day, time should be in days. The total work will then be in units of 'worker-days' or similar.

For solving such problems efficiently during exams, practice establishing the work rate relationship quickly and converting all workers into equivalent units of the worker with the base efficiency (usually the one assumed to be less efficient, like boys in this case).

Was this answer helpful?

Similar Questions

  1. To do a certain work, A and B work on alternate days with B beginning the work on the first day. A alone can complete the same work in 24 days. If the work gets completed in  \(11 \frac{1}{3}\)  days, then B alone can complete  \(\rm \frac{7}{9}^{th}\)  part of the original work in:

  2. 15 men and 25 women can complete a piece of work in 9.6 days. If 16 women can complete the same work in 27 days, find the number of days in which 16 men can complete the same work.  

  3. R, S and T can finish a work in 20, 15 and 10 days, respectively. R works on all days and S and T work on alternate days with T starting the work on the first day. In how many days is the work finished?

  4. A can do \(1 \over 3\) of a piece of work in 32 days, B can do \(37{1 \over 2}\)% of the same work in 24 days, while C can do 60% of the same work in 48 days. B and C together started and worked for x days. After x days, B left the work and A joined C and both completed the remaining work in (x + 8) days. If the ratio of the work done by (B + C) together to the work done by (A + C) together is 9 ∶ 11, then what fraction of the same work can be completed by C alone in 3.5x days?

  5. A group of college students had decided to complete a project in 10 days. As 2 students dropped out every day, the project got completed at the end of the 15th day. The number of students at the beginning of the project was:

  6. Aarif, Arun and Abraham can do a work in 12, 20 and 24 days, respectively. They all begin together. Arun leaves the work 3 days and Abraham 6 days before its completion. In how many days is the work finished?

  7. A,B and C can do a piece of work in 30 days, 40 days and 50 days, respectively. Beginning with A, if A, B and C do the work alternatively then in how many days will the work be finished?

  8. 15 men can complete a work in 25 days, and 25 women can complete the same work in 40 days. If all 15 men and 25 women work together, in how many days will the work get completed?

  9. Working 5 hours a day, A can complete a task in 8 days and working 6 hours a day, B can finish the same task in 10 days, working 8 hours a day, they can jointly complete the task in __________.

  10. A can do 20% of a job in 7 days and B can do 25% of the job in 7 days if they worked alone. How much of the job (in percentage) can they complete in 7 days if they worked together?


Important Questions from Work Efficiency

  1. A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?

  2. 24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?

  3. A and B together can do a piece of work in 4 days, B and C can do it in 6 days, A and C can do it in 8 days. Then A, B and C together can do the same work in :-

  4. A can complete 50% of a work in 9 days and B can do 25% of the work in 9 days, if they work alone. If they work together then how much work (in percentage) can be completed in 6 days?

  5. The efficiency of Genelia is 25% more than that of Jessica and Jessica can complete a work in 25 days. Genelia started the work alone and Jessica joined him just five days before the work was completed. For how many days did Genelia work alone?

Need Expert Advice?
Upcoming Exams
SSC CGL
September 30, 2026
UPSSSC PET
October 23, 2026
Test Series
SSC CGL img
SSC
SSC CGL (Tier I + Tier II) 2026 Mock Test Series - Latest Pattern
2503 Tests 6 Tests Free
5410 Attempts
4.2(868)
English, Hindi

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App