The efficiency of Genelia is 25% more than that of Jessica and Jessica can complete a work in 25 days. Genelia started the work alone and Jessica joined him just five days before the work was completed. For how many days did Genelia work alone?
11 days
This question is about time and work, involving two people, Genelia and Jessica, with different efficiencies. Jessica's work rate is given indirectly by the time she takes to complete the work alone. Genelia's efficiency is related to Jessica's. Genelia starts the work alone, and Jessica joins later for the final few days. We need to find out how many days Genelia worked by herself.
First, let's figure out the work rate of each person. Work rate is the amount of work done per day.
The work happens in two phases:
Let $D$ be the number of days Genelia worked alone. The total number of days the work took is $D + 5$.
The total work done is the sum of the work done in each phase, which equals the total work (represented as 1 unit).
The total work done is the sum of the work in phase 1 and phase 2:
Work in Phase 1 + Work in Phase 2 = Total Work
$\frac{D}{20} + \frac{9}{20} = 1$
Now, we solve the equation for $D$:
$\frac{D + 9}{20} = 1$
Multiply both sides by 20:
$D + 9 = 20$
Subtract 9 from both sides:
$D = 20 - 9$
$D = 11$
So, Genelia worked alone for 11 days.
| Person | Time to Complete Alone (Days) | Daily Work Rate (Work/Day) |
|---|---|---|
| Jessica | 25 | $\frac{1}{25}$ |
| Genelia | 20 | $\frac{1}{20}$ |
The number of days Genelia worked alone is 11 days.
| Concept | Explanation | Formula/Relation |
|---|---|---|
| Work Rate | Amount of work done per unit of time. | Work Rate = $\frac{\text{Total Work}}{\text{Time Taken}}$ |
| Efficiency | Often directly proportional to work rate. Higher efficiency means higher work rate. | If A is $x\%$ more efficient than B, A's Rate = $(1 + \frac{x}{100}) \times$ B's Rate |
| Total Work | Sum of work done by individuals or groups over their respective times. | Total Work = Rate $\times$ Time |
| Combined Rate | Sum of individual rates when working together. | Rate$_{A+B}$ = Rate$_A$ + Rate$_B$ |
Time and work problems often rely on the concept that the total work is constant, usually taken as 1 unit. The relationship between time, work rate, and total work is fundamental.
Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?
A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?
24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?
A and B together can do a piece of work in 4 days, B and C can do it in 6 days, A and C can do it in 8 days. Then A, B and C together can do the same work in :-
A can complete 50% of a work in 9 days and B can do 25% of the work in 9 days, if they work alone. If they work together then how much work (in percentage) can be completed in 6 days?