Question

A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?

The correct answer is

15

Given;

Time taken to complete 7/8 of a job = 21 days

Quantum of work further increased by 50%

Calculation:

Time required to complete the job =  \(\frac {21}{7/8} \)  = 24 days

So time taken by the man to complete 50% work, t 1= 24/2 = 12 days

Also, remaining work after 21 days = 1 - 7/8 = 1/8 and

time required to complete 1/8 of the job, t 2= Time required to complete whole work - time taken to complete 7/8 of the job i.e.

= 24 - 21 = 3 days

Now the number of days required = t 1 + t 2

= 12 + 3 = 15days

Hence, option 4 is correct.

Was this answer helpful?

Important Questions from Work Efficiency

  1. Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?

  2. 24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?

  3. A and B together can do a piece of work in 4 days, B and C can do it in 6 days, A and C can do it in 8 days. Then A, B and C together can do the same work in :-

  4. A can complete 50% of a work in 9 days and B can do 25% of the work in 9 days, if they work alone. If they work together then how much work (in percentage) can be completed in 6 days?

  5. The efficiency of Genelia is 25% more than that of Jessica and Jessica can complete a work in 25 days. Genelia started the work alone and Jessica joined him just five days before the work was completed. For how many days did Genelia work alone?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App