All Exams Test series for 1 year @ ₹349 only
Question

To do a certain work, A and B work on alternate days with B beginning the work on the first day. A alone can complete the same work in 24 days. If the work gets completed in  \(11 \frac{1}{3}\)  days, then B alone can complete  \(\rm \frac{7}{9}^{th}\)  part of the original work in:

This question was previously asked in
SSC CGL 2020 Tier-II (English) Previous Year Paper (29-Jan-2022)
The correct answer is

6 days

Understanding the Work and Time Problem

This problem involves two individuals, A and B, working on a task on alternate days. We are given the time A takes to complete the entire work alone, the total time taken for the work when they work alternately, and we need to find the time B takes to complete a specific fraction of the work alone.

Let's break down the information given:

  • A and B work on alternate days.
  • B starts the work on the first day.
  • A alone can complete the work in 24 days.
  • The work is completed in \(11 \frac{1}{3}\) days.
  • We need to find the time B alone takes to complete \(\rm \frac{7}{9}^{th}\) part of the original work.

Calculating Individual Work Rates

If A can complete the entire work in 24 days, A's work rate per day is the reciprocal of the total time taken.

  • A's 1 day work = \(\frac{1}{\text{Time taken by A alone}}\) = \(\frac{1}{24}\).

Let B's 1 day work be \(\frac{1}{b}\), where \(b\) is the number of days B takes to complete the work alone.

Determining the Number of Days A and B Worked

The work is completed in \(11 \frac{1}{3}\) days. B starts the work.

In 11 full days, since B starts, the sequence of work is B, A, B, A, ...

Days 1, 3, 5, 7, 9, 11 are working days for B.

Days 2, 4, 6, 8, 10 are working days for A.

  • Number of days B worked in the first 11 days = 6 days.
  • Number of days A worked in the first 11 days = 5 days.

The work continues for an additional \(\frac{1}{3}\) day. On the 12th day, it would be A's turn (since B worked on the 11th day). So, A works for the remaining \(\frac{1}{3}\) day.

  • Total number of days B worked = 6 days.
  • Total number of days A worked = 5 days + \(\frac{1}{3}\) day = \(5 \frac{1}{3}\) days = \(\frac{16}{3}\) days.

Calculating the Work Done by A

A's total work done is the product of A's daily work rate and the total number of days A worked.

A's total work = (A's 1 day work) \(\times\) (Total days A worked)

A's total work = \(\frac{1}{24} \times \frac{16}{3}\)

A's total work = \(\frac{16}{24 \times 3}\) = \(\frac{16}{72}\)

Simplifying the fraction:

A's total work = \(\frac{16 \div 8}{72 \div 8}\) = \(\frac{2}{9}\).

Calculating the Work Done by B

The total work done is 1 (representing the complete work). The total work is the sum of the work done by A and the work done by B.

Total work = Work done by A + Work done by B

\(1 = \frac{2}{9} + \text{Work done by B}\)

Work done by B = \(1 - \frac{2}{9}\)

Work done by B = \(\frac{9}{9} - \frac{2}{9} = \frac{7}{9}\).

So, B completed \(\frac{7}{9}\) of the total work in the 6 days B worked.

Finding B's Work Rate and Time for Full Work

We know B did \(\frac{7}{9}\) of the work in 6 days.

B's 1 day work = \(\frac{\text{Work done by B}}{\text{Days B worked}}\) = \(\frac{7/9}{6}\)

B's 1 day work = \(\frac{7}{9 \times 6} = \frac{7}{54}\).

If B does \(\frac{7}{54}\) of the work in 1 day, B can complete the full work (1) in \(\frac{1}{7/54}\) days.

Time taken by B alone for full work = \(\frac{54}{7}\) days.

Calculating Time Taken by B for \(\frac{7}{9}\) Part of Work

We need to find the time B alone takes to complete \(\frac{7}{9}\) part of the original work. We already found that B alone takes \(\frac{54}{7}\) days to complete the full work.

Time taken by B for \(\frac{7}{9}\) work = (Time taken by B for full work) \(\times\) \(\frac{7}{9}\)

Time taken by B for \(\frac{7}{9}\) work = \(\frac{54}{7} \times \frac{7}{9}\)

Time taken by B for \(\frac{7}{9}\) work = \(\frac{54}{9}\)

Time taken by B for \(\frac{7}{9}\) work = 6 days.

Summary of Calculations

Parameter Value
A's time for full work 24 days
A's 1 day work \(\frac{1}{24}\)
Total time for alternate work \(11 \frac{1}{3}\) days
Days B worked 6 days
Days A worked \(5 \frac{1}{3}\) days (\(\frac{16}{3}\) days)
Work done by A \(\frac{16}{3} \times \frac{1}{24} = \frac{2}{9}\)
Work done by B \(1 - \frac{2}{9} = \frac{7}{9}\)
B's 1 day work \(\frac{7/9}{6} = \frac{7}{54}\)
B's time for full work \(\frac{1}{7/54} = \frac{54}{7}\) days
Time for B to complete \(\frac{7}{9}\) work \(\frac{54}{7} \times \frac{7}{9} = 6\) days

Conclusion

Based on the calculations, B alone can complete \(\frac{7}{9}^{th}\) part of the original work in 6 days.

Revision Table: Work and Time Concepts

Concept Explanation Formula/Relation
Work Rate The amount of work done by a person in one unit of time (e.g., per day). Work Rate = \(\frac{\text{Total Work}}{\text{Time Taken}}\)
Time Taken The total time required to complete the work. Time Taken = \(\frac{\text{Total Work}}{\text{Work Rate}}\)
Total Work Often considered as 1 unit for calculation purposes. If work rate is per day, Total Work = Work Rate \(\times\) Total Days. Total Work = Sum of work done by individuals
Work Done in 'x' days Work Rate \(\times\) Number of days worked. Part of Work = Work Rate \(\times\) Days
Alternate Days Work Individuals work on consecutive days, alternating turns. The total work done in a cycle (usually 2 days) is the sum of their individual work rates for one day each. Cycle Work = Work Rate A \(\times\) 1 day + Work Rate B \(\times\) 1 day (if A and B work in a cycle)

Additional Information: Alternate Day Problems

Problems involving work done on alternate days require careful accounting of who works on which day and for how long. Key steps usually include:

  1. Determine the work done in one complete cycle (e.g., Day 1 by A, Day 2 by B).
  2. Calculate how many full cycles are completed within the total time, considering who starts the work.
  3. Calculate the work done in the full cycles.
  4. Determine the remaining work.
  5. Calculate the time taken to complete the remaining work by the person whose turn it is.
  6. Add the time for full cycles and the time for the remaining work to get the total time, or use the total time to deduce individual contributions as done in this problem.
  7. Always remember that if the total time is not an integer, the last fraction of a day is worked by only one person.
  8. The person who starts the work will work on days 1, 3, 5, ... and the other person on days 2, 4, 6, ...

Understanding the pattern of who works on which day is crucial for solving these types of problems accurately.

Was this answer helpful?

Similar Questions

  1. Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?

  2. A man can do a piece of work in 30 hours. If he works with his son then the same piece of work is finished in 20 hours. If the son works alone, he can do the work in:

  3. Two men and 7 women can complete a work in 28 days whereas 6 men and 16 women can do the same work in 11 days. In how many days can 7 men complete the same work?

  4. 4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 25 women complete it?

  5. Raju and Rajat working together take 5 days to complete a piece of work. If Raju alone can do this work in 7 days, how long would Rajat take to complete the same work?

  6. P and Q together can complete a piece of work in 6 days. If P can alone complete the work in 18 days, then the number of days required for Q to finish the work is:

  7. If Mohit can complete \(\frac{2}{3}\)rd of a work in 24 days, then in how many days can \(\rm\frac{1}{9}^{th}\) of the work be complete by him?

  8. A is 50% more efficient then B. B worked to finish the same work in 20 days. If A and B worked together, then how much time will they take to finish the same work?

  9. 20 women and 15 men together can complete a work in 6 days. It takes 150 days for a single woman to complete the work. In how many days can a single man complete the work?

  10. A worker completes \(\frac{3}{5}\) of a work in 12 days. In how many days will he complete \(\frac{3}{4}\) of the work? 


Important Questions from Work Efficiency

  1. Sumi can complete a job working 5 hours per day in 2 days. If she doubles her working hours per day, then in how many days will she complete the work?

  2. Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?

  3. A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?

  4. 24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?

  5. 3 men working 7 hours a day can complete a piece of work in 45 days. In how many days will 9 men working 6 hours a day complete the same work?

Need Expert Advice?
Upcoming Exams
SSC JHT
September 08, 2026
SSC Stenographer
September 09, 2026
SSC Selection Post
September 16, 2026
Test Series
SSC CGL img
SSC
SSC CGL (Tier I + Tier II) 2026 Mock Test Series - Latest Pattern
2501 Tests 6 Tests Free
4031 Attempts
4.2(839)
English, Hindi

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App