To do a certain work, A and B work on alternate days with B beginning the work on the first day. A alone can complete the same work in 24 days. If the work gets completed in \(11 \frac{1}{3}\) days, then B alone can complete \(\rm \frac{7}{9}^{th}\) part of the original work in:
6 days
This problem involves two individuals, A and B, working on a task on alternate days. We are given the time A takes to complete the entire work alone, the total time taken for the work when they work alternately, and we need to find the time B takes to complete a specific fraction of the work alone.
Let's break down the information given:
If A can complete the entire work in 24 days, A's work rate per day is the reciprocal of the total time taken.
Let B's 1 day work be \(\frac{1}{b}\), where \(b\) is the number of days B takes to complete the work alone.
The work is completed in \(11 \frac{1}{3}\) days. B starts the work.
In 11 full days, since B starts, the sequence of work is B, A, B, A, ...
Days 1, 3, 5, 7, 9, 11 are working days for B.
Days 2, 4, 6, 8, 10 are working days for A.
The work continues for an additional \(\frac{1}{3}\) day. On the 12th day, it would be A's turn (since B worked on the 11th day). So, A works for the remaining \(\frac{1}{3}\) day.
A's total work done is the product of A's daily work rate and the total number of days A worked.
A's total work = (A's 1 day work) \(\times\) (Total days A worked)
A's total work = \(\frac{1}{24} \times \frac{16}{3}\)
A's total work = \(\frac{16}{24 \times 3}\) = \(\frac{16}{72}\)
Simplifying the fraction:
A's total work = \(\frac{16 \div 8}{72 \div 8}\) = \(\frac{2}{9}\).
The total work done is 1 (representing the complete work). The total work is the sum of the work done by A and the work done by B.
Total work = Work done by A + Work done by B
\(1 = \frac{2}{9} + \text{Work done by B}\)
Work done by B = \(1 - \frac{2}{9}\)
Work done by B = \(\frac{9}{9} - \frac{2}{9} = \frac{7}{9}\).
So, B completed \(\frac{7}{9}\) of the total work in the 6 days B worked.
We know B did \(\frac{7}{9}\) of the work in 6 days.
B's 1 day work = \(\frac{\text{Work done by B}}{\text{Days B worked}}\) = \(\frac{7/9}{6}\)
B's 1 day work = \(\frac{7}{9 \times 6} = \frac{7}{54}\).
If B does \(\frac{7}{54}\) of the work in 1 day, B can complete the full work (1) in \(\frac{1}{7/54}\) days.
Time taken by B alone for full work = \(\frac{54}{7}\) days.
We need to find the time B alone takes to complete \(\frac{7}{9}\) part of the original work. We already found that B alone takes \(\frac{54}{7}\) days to complete the full work.
Time taken by B for \(\frac{7}{9}\) work = (Time taken by B for full work) \(\times\) \(\frac{7}{9}\)
Time taken by B for \(\frac{7}{9}\) work = \(\frac{54}{7} \times \frac{7}{9}\)
Time taken by B for \(\frac{7}{9}\) work = \(\frac{54}{9}\)
Time taken by B for \(\frac{7}{9}\) work = 6 days.
| Parameter | Value |
|---|---|
| A's time for full work | 24 days |
| A's 1 day work | \(\frac{1}{24}\) |
| Total time for alternate work | \(11 \frac{1}{3}\) days |
| Days B worked | 6 days |
| Days A worked | \(5 \frac{1}{3}\) days (\(\frac{16}{3}\) days) |
| Work done by A | \(\frac{16}{3} \times \frac{1}{24} = \frac{2}{9}\) |
| Work done by B | \(1 - \frac{2}{9} = \frac{7}{9}\) |
| B's 1 day work | \(\frac{7/9}{6} = \frac{7}{54}\) |
| B's time for full work | \(\frac{1}{7/54} = \frac{54}{7}\) days |
| Time for B to complete \(\frac{7}{9}\) work | \(\frac{54}{7} \times \frac{7}{9} = 6\) days |
Based on the calculations, B alone can complete \(\frac{7}{9}^{th}\) part of the original work in 6 days.
| Concept | Explanation | Formula/Relation |
|---|---|---|
| Work Rate | The amount of work done by a person in one unit of time (e.g., per day). | Work Rate = \(\frac{\text{Total Work}}{\text{Time Taken}}\) |
| Time Taken | The total time required to complete the work. | Time Taken = \(\frac{\text{Total Work}}{\text{Work Rate}}\) |
| Total Work | Often considered as 1 unit for calculation purposes. If work rate is per day, Total Work = Work Rate \(\times\) Total Days. | Total Work = Sum of work done by individuals |
| Work Done in 'x' days | Work Rate \(\times\) Number of days worked. | Part of Work = Work Rate \(\times\) Days |
| Alternate Days Work | Individuals work on consecutive days, alternating turns. The total work done in a cycle (usually 2 days) is the sum of their individual work rates for one day each. | Cycle Work = Work Rate A \(\times\) 1 day + Work Rate B \(\times\) 1 day (if A and B work in a cycle) |
Problems involving work done on alternate days require careful accounting of who works on which day and for how long. Key steps usually include:
Understanding the pattern of who works on which day is crucial for solving these types of problems accurately.
A and B together can complete a certain work in 20 days whereas B and C together can complete it in 24 days. If A is twice as good a workman as C, then in what time will B alone do 40% of the same work?
14 men can complete a work in 15 days. If 21 men are employed, then in how many days will they complete the same work?
A can do a certain work in 15 days, while B can do the same work in 21 days. If they work together, then in how many days will the same work be completed?
Two men and 7 women can complete a work in 28 days whereas 6 men and 16 women can do the same work in 11 days. In how many days can 7 men complete the same work?
Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?