All Exams Test series for 1 year @ ₹349 only
Question

P can finish a work in 18 days. When he had worked for 5 days, Q joined him. If both of them together completed the remaining work in \(\frac{13}{5} \) days, then in how many days can Q alone finish  \(66\frac{2}{3} \) % of the same work?

The correct answer is

3

Understanding the Work and Time Problem

This problem involves concepts of work and time, specifically how individuals (P and Q) complete a task alone and when working together. We are given the time P takes to complete the entire work, the duration P works alone, the time P and Q work together on the remaining part, and we need to find the time Q takes to complete a specific percentage of the work alone.

Calculating P's Work Contribution

P can finish the entire work in 18 days. This means P's daily work rate is \( \frac{1}{18} \) of the total work per day.

P worked alone for 5 days. The amount of work completed by P in these 5 days is:

Work done by P in 5 days = Work rate of P \(\times\) Number of days worked

Work done by P in 5 days = \( \frac{1}{18} \times 5 = \frac{5}{18} \) of the total work.

Determining the Remaining Work

After P worked for 5 days, the amount of work remaining is the total work minus the work done by P:

Remaining Work = Total Work - Work done by P

Remaining Work = \( 1 - \frac{5}{18} = \frac{18 - 5}{18} = \frac{13}{18} \) of the total work.

Calculating the Combined Work Rate of P and Q

The remaining \( \frac{13}{18} \) of the work was completed by both P and Q working together in \( \frac{13}{5} \) days.

Their combined daily work rate is the remaining work divided by the time taken to complete it:

Combined Work Rate of P and Q = \( \frac{\text{Remaining Work}}{\text{Time taken by P and Q together}} \)

Combined Work Rate of P and Q = \( \frac{\frac{13}{18}}{\frac{13}{5}} = \frac{13}{18} \times \frac{5}{13} = \frac{5}{18} \) of the total work per day.

Finding Q's Individual Work Rate

We know P's daily work rate is \( \frac{1}{18} \) and the combined daily work rate of P and Q is \( \frac{5}{18} \).

Q's daily work rate can be found by subtracting P's work rate from the combined work rate:

Q's Work Rate = Combined Work Rate of P and Q - P's Work Rate

Q's Work Rate = \( \frac{5}{18} - \frac{1}{18} = \frac{5-1}{18} = \frac{4}{18} = \frac{2}{9} \) of the total work per day.

Calculating Time for Q to Complete 66\( \frac{2}{3} \) % of the Work

First, let's convert the percentage to a fraction:

\( 66\frac{2}{3} \% = \frac{(66 \times 3) + 2}{3} \% = \frac{198 + 2}{3} \% = \frac{200}{3} \% \)

To convert percentage to fraction, divide by 100: \( \frac{200}{3} \times \frac{1}{100} = \frac{200}{300} = \frac{2}{3} \).

So, we need to find the time Q takes to finish \( \frac{2}{3} \) of the same work.

Q's daily work rate is \( \frac{2}{9} \) of the work. This means Q takes \( \frac{1}{2/9} = \frac{9}{2} \) days to complete the entire work (100%).

The time Q takes to complete \( \frac{2}{3} \) of the work is:

Time taken by Q = \( \frac{\text{Fraction of work to be done}}{\text{Q's daily work rate}} \)

Time taken by Q = \( \frac{\frac{2}{3}}{\frac{2}{9}} = \frac{2}{3} \times \frac{9}{2} = \frac{18}{6} = 3 \) days.

Therefore, Q alone can finish \( 66\frac{2}{3} \) % of the same work in 3 days.

Entity Information
P's total time 18 days
P's daily rate \( \frac{1}{18} \) work/day
P works alone 5 days
Work done by P \( 5 \times \frac{1}{18} = \frac{5}{18} \)
Remaining work \( 1 - \frac{5}{18} = \frac{13}{18} \)
Time P & Q together \( \frac{13}{5} \) days
Combined rate (P+Q) \( \frac{13/18}{13/5} = \frac{5}{18} \) work/day
Q's daily rate \( \frac{5}{18} - \frac{1}{18} = \frac{4}{18} = \frac{2}{9} \) work/day
Percentage for Q \( 66\frac{2}{3} \% = \frac{2}{3} \)
Time for Q (2/3 work) \( \frac{2/3}{2/9} = \frac{2}{3} \times \frac{9}{2} = 3 \) days

The final answer is 3 days.

Revision Table: Work and Time Concepts

Concept Formula/Explanation
Work Rate If a person completes a work in 'n' days, their daily work rate is \( \frac{1}{n} \) of the work per day.
Work Done Work Done = Work Rate \(\times\) Time
Time Taken Time Taken = \( \frac{\text{Total Work}}{\text{Work Rate}} \). If doing a fraction of work, Time = \( \frac{\text{Fraction of Work}}{\text{Work Rate}} \).
Combined Work Rate If A's rate is \(R_A\) and B's rate is \(R_B\), their combined rate is \(R_A + R_B\).
Remaining Work Remaining Work = Total Work - Work Done

Additional Information on Work and Time Problems

Work and Time problems are common in quantitative aptitude sections of various exams. They typically involve individuals or machines working at different rates to complete a task. The key is to convert the time taken to complete the whole work into a work rate (fraction of work done per unit time, usually a day).

  • If a person completes work in 'D' days, they do \( \frac{1}{D} \) of the work each day.
  • If multiple people work together, their individual work rates are added to find the combined work rate.
  • If someone leaves or joins, calculate the work done by each person or group during their specific time period.
  • Percentage of work can be converted into fractions for easier calculation. \(x\%\) of work is \( \frac{x}{100} \) of the work.
  • Always ensure that the units (days, hours, etc.) are consistent throughout the calculation.

Understanding these fundamental principles helps in solving various complex Work and Time scenarios effectively.

Was this answer helpful?

Important Questions from Work Efficiency

  1. A and B together can complete a certain work in 20 days whereas B and C together can complete it in 24 days. If A is twice as good a workman as C, then in what time will B alone do 40% of the same work?

  2. 14 men can complete a work in 15 days. If 21 men are employed, then in how many days will they complete the same work?

  3. A can do a certain work in 15 days, while B can do the same work in 21 days. If they work together, then in how many days will the same work be completed?

  4. To do a certain work, A and B work on alternate days with B beginning the work on the first day. A alone can complete the same work in 24 days. If the work gets completed in  \(11 \frac{1}{3}\)  days, then B alone can complete  \(\rm \frac{7}{9}^{th}\)  part of the original work in:

  5. Two men and 7 women can complete a work in 28 days whereas 6 men and 16 women can do the same work in 11 days. In how many days can 7 men complete the same work?

Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App