P can finish a work in 18 days. When he had worked for 5 days, Q joined him. If both of them together completed the remaining work in \(\frac{13}{5} \) days, then in how many days can Q alone finish \(66\frac{2}{3} \) % of the same work?
3
This problem involves concepts of work and time, specifically how individuals (P and Q) complete a task alone and when working together. We are given the time P takes to complete the entire work, the duration P works alone, the time P and Q work together on the remaining part, and we need to find the time Q takes to complete a specific percentage of the work alone.
P can finish the entire work in 18 days. This means P's daily work rate is \( \frac{1}{18} \) of the total work per day.
P worked alone for 5 days. The amount of work completed by P in these 5 days is:
Work done by P in 5 days = Work rate of P \(\times\) Number of days worked
Work done by P in 5 days = \( \frac{1}{18} \times 5 = \frac{5}{18} \) of the total work.
After P worked for 5 days, the amount of work remaining is the total work minus the work done by P:
Remaining Work = Total Work - Work done by P
Remaining Work = \( 1 - \frac{5}{18} = \frac{18 - 5}{18} = \frac{13}{18} \) of the total work.
The remaining \( \frac{13}{18} \) of the work was completed by both P and Q working together in \( \frac{13}{5} \) days.
Their combined daily work rate is the remaining work divided by the time taken to complete it:
Combined Work Rate of P and Q = \( \frac{\text{Remaining Work}}{\text{Time taken by P and Q together}} \)
Combined Work Rate of P and Q = \( \frac{\frac{13}{18}}{\frac{13}{5}} = \frac{13}{18} \times \frac{5}{13} = \frac{5}{18} \) of the total work per day.
We know P's daily work rate is \( \frac{1}{18} \) and the combined daily work rate of P and Q is \( \frac{5}{18} \).
Q's daily work rate can be found by subtracting P's work rate from the combined work rate:
Q's Work Rate = Combined Work Rate of P and Q - P's Work Rate
Q's Work Rate = \( \frac{5}{18} - \frac{1}{18} = \frac{5-1}{18} = \frac{4}{18} = \frac{2}{9} \) of the total work per day.
First, let's convert the percentage to a fraction:
\( 66\frac{2}{3} \% = \frac{(66 \times 3) + 2}{3} \% = \frac{198 + 2}{3} \% = \frac{200}{3} \% \)
To convert percentage to fraction, divide by 100: \( \frac{200}{3} \times \frac{1}{100} = \frac{200}{300} = \frac{2}{3} \).
So, we need to find the time Q takes to finish \( \frac{2}{3} \) of the same work.
Q's daily work rate is \( \frac{2}{9} \) of the work. This means Q takes \( \frac{1}{2/9} = \frac{9}{2} \) days to complete the entire work (100%).
The time Q takes to complete \( \frac{2}{3} \) of the work is:
Time taken by Q = \( \frac{\text{Fraction of work to be done}}{\text{Q's daily work rate}} \)
Time taken by Q = \( \frac{\frac{2}{3}}{\frac{2}{9}} = \frac{2}{3} \times \frac{9}{2} = \frac{18}{6} = 3 \) days.
Therefore, Q alone can finish \( 66\frac{2}{3} \) % of the same work in 3 days.
| Entity | Information |
|---|---|
| P's total time | 18 days |
| P's daily rate | \( \frac{1}{18} \) work/day |
| P works alone | 5 days |
| Work done by P | \( 5 \times \frac{1}{18} = \frac{5}{18} \) |
| Remaining work | \( 1 - \frac{5}{18} = \frac{13}{18} \) |
| Time P & Q together | \( \frac{13}{5} \) days |
| Combined rate (P+Q) | \( \frac{13/18}{13/5} = \frac{5}{18} \) work/day |
| Q's daily rate | \( \frac{5}{18} - \frac{1}{18} = \frac{4}{18} = \frac{2}{9} \) work/day |
| Percentage for Q | \( 66\frac{2}{3} \% = \frac{2}{3} \) |
| Time for Q (2/3 work) | \( \frac{2/3}{2/9} = \frac{2}{3} \times \frac{9}{2} = 3 \) days |
The final answer is 3 days.
| Concept | Formula/Explanation |
|---|---|
| Work Rate | If a person completes a work in 'n' days, their daily work rate is \( \frac{1}{n} \) of the work per day. |
| Work Done | Work Done = Work Rate \(\times\) Time |
| Time Taken | Time Taken = \( \frac{\text{Total Work}}{\text{Work Rate}} \). If doing a fraction of work, Time = \( \frac{\text{Fraction of Work}}{\text{Work Rate}} \). |
| Combined Work Rate | If A's rate is \(R_A\) and B's rate is \(R_B\), their combined rate is \(R_A + R_B\). |
| Remaining Work | Remaining Work = Total Work - Work Done |
Work and Time problems are common in quantitative aptitude sections of various exams. They typically involve individuals or machines working at different rates to complete a task. The key is to convert the time taken to complete the whole work into a work rate (fraction of work done per unit time, usually a day).
Understanding these fundamental principles helps in solving various complex Work and Time scenarios effectively.
Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?
To do a certain work, A and B work on alternate days with B beginning the work on the first day. A alone can complete the same work in 24 days. If the work gets completed in \(11 \frac{1}{3}\) days, then B alone can complete \(\rm \frac{7}{9}^{th}\) part of the original work in:
15 men and 25 women can complete a piece of work in 9.6 days. If 16 women can complete the same work in 27 days, find the number of days in which 16 men can complete the same work.
R, S and T can finish a work in 20, 15 and 10 days, respectively. R works on all days and S and T work on alternate days with T starting the work on the first day. In how many days is the work finished?
A can do \(1 \over 3\) of a piece of work in 32 days, B can do \(37{1 \over 2}\)% of the same work in 24 days, while C can do 60% of the same work in 48 days. B and C together started and worked for x days. After x days, B left the work and A joined C and both completed the remaining work in (x + 8) days. If the ratio of the work done by (B + C) together to the work done by (A + C) together is 9 ∶ 11, then what fraction of the same work can be completed by C alone in 3.5x days?
A group of college students had decided to complete a project in 10 days. As 2 students dropped out every day, the project got completed at the end of the 15th day. The number of students at the beginning of the project was:
Aarif, Arun and Abraham can do a work in 12, 20 and 24 days, respectively. They all begin together. Arun leaves the work 3 days and Abraham 6 days before its completion. In how many days is the work finished?
A,B and C can do a piece of work in 30 days, 40 days and 50 days, respectively. Beginning with A, if A, B and C do the work alternatively then in how many days will the work be finished?
15 men can complete a work in 25 days, and 25 women can complete the same work in 40 days. If all 15 men and 25 women work together, in how many days will the work get completed?
Working 5 hours a day, A can complete a task in 8 days and working 6 hours a day, B can finish the same task in 10 days, working 8 hours a day, they can jointly complete the task in __________.
Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?
A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?
24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?
A and B together can do a piece of work in 4 days, B and C can do it in 6 days, A and C can do it in 8 days. Then A, B and C together can do the same work in :-
A can complete 50% of a work in 9 days and B can do 25% of the work in 9 days, if they work alone. If they work together then how much work (in percentage) can be completed in 6 days?