All Exams Test series for 1 year @ ₹349 only
Question

P can finish a work in 18 days. When he had worked for 5 days, Q joined him. If both of them together completed the remaining work in \(\frac{13}{5} \) days, then in how many days can Q alone finish  \(66\frac{2}{3} \) % of the same work?

This question was previously asked in
SSC CGL 2020 Tier-II (English) Previous Year Paper (29-Jan-2022)
The correct answer is

3

Understanding the Work and Time Problem

This problem involves concepts of work and time, specifically how individuals (P and Q) complete a task alone and when working together. We are given the time P takes to complete the entire work, the duration P works alone, the time P and Q work together on the remaining part, and we need to find the time Q takes to complete a specific percentage of the work alone.

Calculating P's Work Contribution

P can finish the entire work in 18 days. This means P's daily work rate is \( \frac{1}{18} \) of the total work per day.

P worked alone for 5 days. The amount of work completed by P in these 5 days is:

Work done by P in 5 days = Work rate of P \(\times\) Number of days worked

Work done by P in 5 days = \( \frac{1}{18} \times 5 = \frac{5}{18} \) of the total work.

Determining the Remaining Work

After P worked for 5 days, the amount of work remaining is the total work minus the work done by P:

Remaining Work = Total Work - Work done by P

Remaining Work = \( 1 - \frac{5}{18} = \frac{18 - 5}{18} = \frac{13}{18} \) of the total work.

Calculating the Combined Work Rate of P and Q

The remaining \( \frac{13}{18} \) of the work was completed by both P and Q working together in \( \frac{13}{5} \) days.

Their combined daily work rate is the remaining work divided by the time taken to complete it:

Combined Work Rate of P and Q = \( \frac{\text{Remaining Work}}{\text{Time taken by P and Q together}} \)

Combined Work Rate of P and Q = \( \frac{\frac{13}{18}}{\frac{13}{5}} = \frac{13}{18} \times \frac{5}{13} = \frac{5}{18} \) of the total work per day.

Finding Q's Individual Work Rate

We know P's daily work rate is \( \frac{1}{18} \) and the combined daily work rate of P and Q is \( \frac{5}{18} \).

Q's daily work rate can be found by subtracting P's work rate from the combined work rate:

Q's Work Rate = Combined Work Rate of P and Q - P's Work Rate

Q's Work Rate = \( \frac{5}{18} - \frac{1}{18} = \frac{5-1}{18} = \frac{4}{18} = \frac{2}{9} \) of the total work per day.

Calculating Time for Q to Complete 66\( \frac{2}{3} \) % of the Work

First, let's convert the percentage to a fraction:

\( 66\frac{2}{3} \% = \frac{(66 \times 3) + 2}{3} \% = \frac{198 + 2}{3} \% = \frac{200}{3} \% \)

To convert percentage to fraction, divide by 100: \( \frac{200}{3} \times \frac{1}{100} = \frac{200}{300} = \frac{2}{3} \).

So, we need to find the time Q takes to finish \( \frac{2}{3} \) of the same work.

Q's daily work rate is \( \frac{2}{9} \) of the work. This means Q takes \( \frac{1}{2/9} = \frac{9}{2} \) days to complete the entire work (100%).

The time Q takes to complete \( \frac{2}{3} \) of the work is:

Time taken by Q = \( \frac{\text{Fraction of work to be done}}{\text{Q's daily work rate}} \)

Time taken by Q = \( \frac{\frac{2}{3}}{\frac{2}{9}} = \frac{2}{3} \times \frac{9}{2} = \frac{18}{6} = 3 \) days.

Therefore, Q alone can finish \( 66\frac{2}{3} \) % of the same work in 3 days.

Entity Information
P's total time 18 days
P's daily rate \( \frac{1}{18} \) work/day
P works alone 5 days
Work done by P \( 5 \times \frac{1}{18} = \frac{5}{18} \)
Remaining work \( 1 - \frac{5}{18} = \frac{13}{18} \)
Time P & Q together \( \frac{13}{5} \) days
Combined rate (P+Q) \( \frac{13/18}{13/5} = \frac{5}{18} \) work/day
Q's daily rate \( \frac{5}{18} - \frac{1}{18} = \frac{4}{18} = \frac{2}{9} \) work/day
Percentage for Q \( 66\frac{2}{3} \% = \frac{2}{3} \)
Time for Q (2/3 work) \( \frac{2/3}{2/9} = \frac{2}{3} \times \frac{9}{2} = 3 \) days

The final answer is 3 days.

Revision Table: Work and Time Concepts

Concept Formula/Explanation
Work Rate If a person completes a work in 'n' days, their daily work rate is \( \frac{1}{n} \) of the work per day.
Work Done Work Done = Work Rate \(\times\) Time
Time Taken Time Taken = \( \frac{\text{Total Work}}{\text{Work Rate}} \). If doing a fraction of work, Time = \( \frac{\text{Fraction of Work}}{\text{Work Rate}} \).
Combined Work Rate If A's rate is \(R_A\) and B's rate is \(R_B\), their combined rate is \(R_A + R_B\).
Remaining Work Remaining Work = Total Work - Work Done

Additional Information on Work and Time Problems

Work and Time problems are common in quantitative aptitude sections of various exams. They typically involve individuals or machines working at different rates to complete a task. The key is to convert the time taken to complete the whole work into a work rate (fraction of work done per unit time, usually a day).

  • If a person completes work in 'D' days, they do \( \frac{1}{D} \) of the work each day.
  • If multiple people work together, their individual work rates are added to find the combined work rate.
  • If someone leaves or joins, calculate the work done by each person or group during their specific time period.
  • Percentage of work can be converted into fractions for easier calculation. \(x\%\) of work is \( \frac{x}{100} \) of the work.
  • Always ensure that the units (days, hours, etc.) are consistent throughout the calculation.

Understanding these fundamental principles helps in solving various complex Work and Time scenarios effectively.

Was this answer helpful?

Similar Questions

  1. A and Btogether can do a piece of work in 12 days. Aalone can do it in 18 days. In how many days can Balone can do the work?
  2. A can complete a certain piece of work in 40 days. B is 25% more efficient than A and C is 28% more efficient than B. They work together for 5 days. The remaining work will be complete by B alone, in:

  3. 45 men or 60 boys can do a piece of work in 20 days. How many days will 15 men and 20 boys take to complete the work?

  4. A, B and C can finish a job working alone in 20, 30 and 60 days respectively. They all work together for 1 day, then A and B quit. How many days C working alone will take to finish the remaining part of the job?

  5. A can do a piece of work in 6 days, B can do it in 9 days. With the assistance of C they completed the work in 3 days. In how many days can C alone do the work?

  6. A piece of work was finished by A, B and C together. A and B together finished 60% of the work and B and C together finished 70% of the work. Who among the three is most efficient?

  7. A, B and C can individually complete a task in 24 days, 20 days and 18 days, respectively. B and C start the task, and they work for 6 days and leave. The number of days required by A alone to finish the remaining task is:

  8. Amar can complete a work in 30 days and Raman can complete the same work in 15 days. If both of them work together, then in 4 days what percent of the total work will be completed?

  9. The ratio of the efficiencies of A, B and C is 7 ∶ 5 ∶ 4. Working together, they can finish a work in 35 days. A and B work together for 28 days. The remaining work will be completed (in days) by C alone∶

  10. 3 men, 4 women and 6 boys together can complete a work in 6 days. A woman does triple the work a man does and a boy does half the work a man does. How many women alone will be able to complete this work in 4 days?


Important Questions from Work Efficiency

  1. M is thrice as efficient as workman as N and therefore is able to finish a job in 264 days less than N. Then in how many days can N finish the entire work?
  2. A can do a piece of work in $1455$ days. B is $25\%$ more efficient than A. Find the number of days taken by B to do the same piece of work.
  3. 45 people take 18 days to dig a pond. If the pond would have to be dug in 15 days, then the number of people to be employed will be
  4. A stock of food is enough for 240 men for 48 days. How long will the same stock last for 160 men?
  5. One contractor had undertaken a construction work. To complete the given job, he sought labour comprising 24 men for 12 days for working 10 hours a day. But due to festival season, as the labour had gone to their respective hometowns, he could get only 15 men and they too were willing to work 8 hours a day. With this much labour, in how many days would he be able to complete the same job?

Need Expert Advice?
Upcoming Exams
SSC CPO
November 23, 2026
SSC CHSL
November 30, 2026
SSC JE
November 30, 2026
Test Series
SSC CGL img
SSC
SSC CGL (Tier I + Tier II) 2026 Mock Test Series - Latest Pattern
2509 Tests 6 Tests Free
9153 Attempts
4.2(953)
English, Hindi
More Questions from SSC CGL

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App