P can finish a work in 18 days. When he had worked for 5 days, Q joined him. If both of them together completed the remaining work in \(\frac{13}{5} \) days, then in how many days can Q alone finish \(66\frac{2}{3} \) % of the same work?
3
This problem involves concepts of work and time, specifically how individuals (P and Q) complete a task alone and when working together. We are given the time P takes to complete the entire work, the duration P works alone, the time P and Q work together on the remaining part, and we need to find the time Q takes to complete a specific percentage of the work alone.
P can finish the entire work in 18 days. This means P's daily work rate is \( \frac{1}{18} \) of the total work per day.
P worked alone for 5 days. The amount of work completed by P in these 5 days is:
Work done by P in 5 days = Work rate of P \(\times\) Number of days worked
Work done by P in 5 days = \( \frac{1}{18} \times 5 = \frac{5}{18} \) of the total work.
After P worked for 5 days, the amount of work remaining is the total work minus the work done by P:
Remaining Work = Total Work - Work done by P
Remaining Work = \( 1 - \frac{5}{18} = \frac{18 - 5}{18} = \frac{13}{18} \) of the total work.
The remaining \( \frac{13}{18} \) of the work was completed by both P and Q working together in \( \frac{13}{5} \) days.
Their combined daily work rate is the remaining work divided by the time taken to complete it:
Combined Work Rate of P and Q = \( \frac{\text{Remaining Work}}{\text{Time taken by P and Q together}} \)
Combined Work Rate of P and Q = \( \frac{\frac{13}{18}}{\frac{13}{5}} = \frac{13}{18} \times \frac{5}{13} = \frac{5}{18} \) of the total work per day.
We know P's daily work rate is \( \frac{1}{18} \) and the combined daily work rate of P and Q is \( \frac{5}{18} \).
Q's daily work rate can be found by subtracting P's work rate from the combined work rate:
Q's Work Rate = Combined Work Rate of P and Q - P's Work Rate
Q's Work Rate = \( \frac{5}{18} - \frac{1}{18} = \frac{5-1}{18} = \frac{4}{18} = \frac{2}{9} \) of the total work per day.
First, let's convert the percentage to a fraction:
\( 66\frac{2}{3} \% = \frac{(66 \times 3) + 2}{3} \% = \frac{198 + 2}{3} \% = \frac{200}{3} \% \)
To convert percentage to fraction, divide by 100: \( \frac{200}{3} \times \frac{1}{100} = \frac{200}{300} = \frac{2}{3} \).
So, we need to find the time Q takes to finish \( \frac{2}{3} \) of the same work.
Q's daily work rate is \( \frac{2}{9} \) of the work. This means Q takes \( \frac{1}{2/9} = \frac{9}{2} \) days to complete the entire work (100%).
The time Q takes to complete \( \frac{2}{3} \) of the work is:
Time taken by Q = \( \frac{\text{Fraction of work to be done}}{\text{Q's daily work rate}} \)
Time taken by Q = \( \frac{\frac{2}{3}}{\frac{2}{9}} = \frac{2}{3} \times \frac{9}{2} = \frac{18}{6} = 3 \) days.
Therefore, Q alone can finish \( 66\frac{2}{3} \) % of the same work in 3 days.
| Entity | Information |
|---|---|
| P's total time | 18 days |
| P's daily rate | \( \frac{1}{18} \) work/day |
| P works alone | 5 days |
| Work done by P | \( 5 \times \frac{1}{18} = \frac{5}{18} \) |
| Remaining work | \( 1 - \frac{5}{18} = \frac{13}{18} \) |
| Time P & Q together | \( \frac{13}{5} \) days |
| Combined rate (P+Q) | \( \frac{13/18}{13/5} = \frac{5}{18} \) work/day |
| Q's daily rate | \( \frac{5}{18} - \frac{1}{18} = \frac{4}{18} = \frac{2}{9} \) work/day |
| Percentage for Q | \( 66\frac{2}{3} \% = \frac{2}{3} \) |
| Time for Q (2/3 work) | \( \frac{2/3}{2/9} = \frac{2}{3} \times \frac{9}{2} = 3 \) days |
The final answer is 3 days.
| Concept | Formula/Explanation |
|---|---|
| Work Rate | If a person completes a work in 'n' days, their daily work rate is \( \frac{1}{n} \) of the work per day. |
| Work Done | Work Done = Work Rate \(\times\) Time |
| Time Taken | Time Taken = \( \frac{\text{Total Work}}{\text{Work Rate}} \). If doing a fraction of work, Time = \( \frac{\text{Fraction of Work}}{\text{Work Rate}} \). |
| Combined Work Rate | If A's rate is \(R_A\) and B's rate is \(R_B\), their combined rate is \(R_A + R_B\). |
| Remaining Work | Remaining Work = Total Work - Work Done |
Work and Time problems are common in quantitative aptitude sections of various exams. They typically involve individuals or machines working at different rates to complete a task. The key is to convert the time taken to complete the whole work into a work rate (fraction of work done per unit time, usually a day).
Understanding these fundamental principles helps in solving various complex Work and Time scenarios effectively.
X and Y can complete a work in 9 days and 36 days, respectively. X begins to do the work and they work alternately one at a time for one day each. The whole work will be complete in:
P is two times as efficient as Q. P is able to complete a piece of work in 40 days less than Q. Working together, the whole number of days taken by them to complete the work is:
(Round off to the nearest integer)
4 women or 6 boys can finish a work in the same number of days. A boy can finish it in 60 days. In how many days can 5 women finish the work, working together every day?
To do a certain work, Ajay and Bharat work on alternate days, with Bharat starting the work on the first day. Ajay can finish the work alone in 32 days. If the work gets completed in exactly 8 days, then Bharat alone can finish 7 times the same work in ____________ days.
A, B and C can separately complete a work in 12, 15 and 20 days, respectively. They worked together 4 days. What will be the remaining work?
A, B and C, working alone, can complete a job in 16, 24 and 36 days, respectively. In how many days can they complete the job if they work together?
Rakshit, Ajay, and Satish are sanitation workers in a Municipal Corporation. Rakshit alone takes 20 hours to clean a drain while Ajay takes 12 hours when working alone to do the same. All three together take only 5 hours to clean the drain. In how many hours, can Satish complete the work alone?
15 men and 25 women can complete a piece of work in 9.6 days. If 16 women can complete the same work in 27 days, find the number of days in which 16 men can complete the same work.
A,B and C can do a piece of work in 30 days, 40 days and 50 days, respectively. Beginning with A, if A, B and C do the work alternatively then in how many days will the work be finished?
Ravi can do a piece of work in 40 days and Sudha can do the same piece of work in 60 days. If they work on alternative days starting with Sudha on the first day, then in how many days will the work be completed?
A and B working together can complete a job in 30 days. The ratio of their efficiencies is 3 : 2. In how many days can the faster person complete the job?
A takes 15 days to complete \(\frac{5}{7} \) of a work. With the help of B, they finish the whole work in 12 days. In how many days, B alone will complete the same work
A alone can complete a work in 14 days and B alone can complete the same work in 21 days. A and B start the work together but A leaves the work after 4 days of the starting of work. In how many days B will complete the remaining work?
For completing a certain work, A is 50% less efficient than B and B is 50% more efficient than C. Working together A, B and C can complete the work in 48 days. A alone can complete the same work in:
30 persons can do a piece of work in 24 days. How many more persons are required to complete the work in 20 days?