Ram can complete a piece work in 15 days, Rohan in 25 days, and Rohit in 30 days. Rohan and Rohit worked together for 2 days and then Rohit was replaced by Ram. In how many days altogether was the work completed?
10 days
This question involves a classic work and time scenario where multiple people work at different rates, and the team composition changes over time. To solve this, we first need to determine the individual work rate or efficiency of each person. We can do this by assuming a total amount of work, which is typically the least common multiple (LCM) of the number of days each person takes to complete the work individually.
The given times to complete the work are:
Let's find the LCM of 15, 25, and 30. The LCM of these numbers is 150. We assume the total work is 150 units.
Now, we can calculate the efficiency (units of work per day) for each person:
Rohan and Rohit worked together for the first 2 days. We need to calculate their combined efficiency and the total work done during this period.
The total work is 150 units, and 22 units have been completed. The remaining work is:
After 2 days, Rohit is replaced by Ram. Now, Rohan and Ram work together to complete the remaining work. We calculate their combined efficiency.
The time taken by Rohan and Ram to complete the remaining 128 units of work is:
The work was done in two phases. The first phase lasted 2 days, and the second phase lasted 8 days. The total time taken to complete the work is the sum of the durations of these two phases.
| Worker | Days to complete alone | Efficiency (Units/day) |
|---|---|---|
| Ram | 15 | 10 |
| Rohan | 25 | 6 |
| Rohit | 30 | 5 |
| Phase | Workers | Combined Efficiency (Units/day) | Days worked | Work done (Units) |
|---|---|---|---|---|
| Phase 1 | Rohan & Rohit | 11 | 2 | $11 \times 2 = 22$ |
| Phase 2 | Rohan & Ram | 16 | Calculated below | Remaining work = $150 - 22 = 128$ |
Time taken in Phase 2 = Remaining Work / Combined Efficiency of Rohan & Ram = $128 / 16 = 8$ days.
Total time = Time in Phase 1 + Time in Phase 2 = $2 + 8 = 10$ days.
Therefore, the work was completed in a total of 10 days.
| Concept | Explanation |
|---|---|
| Individual Efficiency | The amount of work a person can do in one unit of time (e.g., one day). It's calculated as Total Work / Time taken. |
| Total Work (Assumed) | Often taken as the LCM of the individual times to complete the work. This makes calculations with efficiencies easier as they become integers. |
| Combined Efficiency | When multiple people work together, their efficiencies are added to find their combined efficiency per unit of time. |
| Time Taken | Calculated as Total Work / Combined Efficiency. If work is done in phases, calculate time for each phase and sum them up for total time. |
Work and time problems often involve understanding inverse proportionality. If a person takes more time, their work rate (efficiency) is lower, and vice versa. When solving these problems, consistency in units (e.g., units of work per day) is crucial. Problems can include scenarios with varying numbers of workers, workers leaving or joining, or workers working for different durations. The key is to break down the problem into steps, calculate the work done in each phase, find the remaining work, and then calculate the time needed for subsequent phases based on the new team's efficiency. Remember to always account for the time already spent when calculating the total time for the project.
Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?
To do a certain work, A and B work on alternate days with B beginning the work on the first day. A alone can complete the same work in 24 days. If the work gets completed in \(11 \frac{1}{3}\) days, then B alone can complete \(\rm \frac{7}{9}^{th}\) part of the original work in:
15 men and 25 women can complete a piece of work in 9.6 days. If 16 women can complete the same work in 27 days, find the number of days in which 16 men can complete the same work.
R, S and T can finish a work in 20, 15 and 10 days, respectively. R works on all days and S and T work on alternate days with T starting the work on the first day. In how many days is the work finished?
A can do \(1 \over 3\) of a piece of work in 32 days, B can do \(37{1 \over 2}\)% of the same work in 24 days, while C can do 60% of the same work in 48 days. B and C together started and worked for x days. After x days, B left the work and A joined C and both completed the remaining work in (x + 8) days. If the ratio of the work done by (B + C) together to the work done by (A + C) together is 9 ∶ 11, then what fraction of the same work can be completed by C alone in 3.5x days?
A group of college students had decided to complete a project in 10 days. As 2 students dropped out every day, the project got completed at the end of the 15th day. The number of students at the beginning of the project was:
Aarif, Arun and Abraham can do a work in 12, 20 and 24 days, respectively. They all begin together. Arun leaves the work 3 days and Abraham 6 days before its completion. In how many days is the work finished?
A,B and C can do a piece of work in 30 days, 40 days and 50 days, respectively. Beginning with A, if A, B and C do the work alternatively then in how many days will the work be finished?
15 men can complete a work in 25 days, and 25 women can complete the same work in 40 days. If all 15 men and 25 women work together, in how many days will the work get completed?
Working 5 hours a day, A can complete a task in 8 days and working 6 hours a day, B can finish the same task in 10 days, working 8 hours a day, they can jointly complete the task in __________.
Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?
A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?
24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?
A and B together can do a piece of work in 4 days, B and C can do it in 6 days, A and C can do it in 8 days. Then A, B and C together can do the same work in :-
A can complete 50% of a work in 9 days and B can do 25% of the work in 9 days, if they work alone. If they work together then how much work (in percentage) can be completed in 6 days?