Working 5 hours a day, A can complete a task in 8 days and working 6 hours a day, B can finish the same task in 10 days, working 8 hours a day, they can jointly complete the task in __________.
3 days
This problem involves calculating the time taken by individuals and a group to complete a task, based on their working hours per day and total days. These are classic work and time problems, often encountered in quantitative aptitude sections of exams. The key is to determine the rate at which each person completes the work.
First, let's find the total number of hours each person works to complete the task individually.
Now, let's assume a 'Total Work Unit'. A common method is to take the Least Common Multiple (LCM) of the total hours worked by each person. The LCM of 40 and 60 is 120. Let's assume the total task is 120 units of work.
Now we can find the work rate of A and B per hour.
When A and B work together, their work rates add up. They work 8 hours a day jointly.
They work for 8 hours each day. So, their combined work per day is:
To find the number of days they will take to complete the total task (120 units) while working together 8 hours a day, we use the formula:
Number of days = Total Work Units / Combined daily rate
Number of days = \(120 \text{ units} / 40 \text{ units/day}\)
Number of days = 3 days
So, working 8 hours a day, A and B can jointly complete the task in 3 days.
| Person | Hours/Day | Days to Complete | Total Hours to Complete | Hourly Rate (units/hour) |
|---|---|---|---|---|
| A | 5 | 8 | 40 | 3 |
| B | 6 | 10 | 60 | 2 |
| A & B (Jointly) | 8 | ? | - | 5 (combined) |
| Concept | Explanation | Formula |
|---|---|---|
| Total Work | The total amount of work to be done (often assumed as 1 unit or an LCM value). | Rate × Time |
| Work Rate | The amount of work done per unit of time (e.g., per hour or per day). | Work / Time |
| Time Taken | The duration required to complete the work. | Work / Rate |
| Combined Rate | The sum of individual rates when people work together. | Rate\(_{A}\) + Rate\(_{B}\) + ... |
Work and time problems can come in many forms. Some variations include:
Understanding the basic principles of calculating individual and combined rates is essential for solving these variations. Always convert the given information into a standard rate (e.g., work per hour or work per day) relative to the total work.
Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?
To do a certain work, A and B work on alternate days with B beginning the work on the first day. A alone can complete the same work in 24 days. If the work gets completed in \(11 \frac{1}{3}\) days, then B alone can complete \(\rm \frac{7}{9}^{th}\) part of the original work in:
20 women and 15 men together can complete a work in 6 days. It takes 150 days for a single woman to complete the work. In how many days can a single man complete the work?
15 men and 25 women can complete a piece of work in 9.6 days. If 16 women can complete the same work in 27 days, find the number of days in which 16 men can complete the same work.
Ram can complete a piece work in 15 days, Rohan in 25 days, and Rohit in 30 days. Rohan and Rohit worked together for 2 days and then Rohit was replaced by Ram. In how many days altogether was the work completed?
R, S and T can finish a work in 20, 15 and 10 days, respectively. R works on all days and S and T work on alternate days with T starting the work on the first day. In how many days is the work finished?
A can do \(1 \over 3\) of a piece of work in 32 days, B can do \(37{1 \over 2}\)% of the same work in 24 days, while C can do 60% of the same work in 48 days. B and C together started and worked for x days. After x days, B left the work and A joined C and both completed the remaining work in (x + 8) days. If the ratio of the work done by (B + C) together to the work done by (A + C) together is 9 ∶ 11, then what fraction of the same work can be completed by C alone in 3.5x days?
A group of college students had decided to complete a project in 10 days. As 2 students dropped out every day, the project got completed at the end of the 15th day. The number of students at the beginning of the project was:
Aarif, Arun and Abraham can do a work in 12, 20 and 24 days, respectively. They all begin together. Arun leaves the work 3 days and Abraham 6 days before its completion. In how many days is the work finished?
A,B and C can do a piece of work in 30 days, 40 days and 50 days, respectively. Beginning with A, if A, B and C do the work alternatively then in how many days will the work be finished?
Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?
A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?
24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?
A and B together can do a piece of work in 4 days, B and C can do it in 6 days, A and C can do it in 8 days. Then A, B and C together can do the same work in :-
A can complete 50% of a work in 9 days and B can do 25% of the work in 9 days, if they work alone. If they work together then how much work (in percentage) can be completed in 6 days?