All Exams Test series for 1 year @ ₹349 only
Question

20 women and 15 men together can complete a work in 6 days. It takes 150 days for a single woman to complete the work. In how many days can a single man complete the work?

This question was previously asked in
SSC CGL 2023 (Tier-II) Paper 1 Previous Year Paper (26-Oct-2023) (Shift-1)
The correct answer is

450

This problem involves understanding the concept of work rate and how it applies to multiple individuals working together. We are given information about the time it takes for individuals and groups to complete a certain amount of work, and we need to find the time it takes for a single man to complete the same work.

Understanding Work Rate

Work rate is the amount of work done by a person or group in a unit of time, usually one day. If a person takes $D$ days to complete a work, their daily work rate is $\frac{1}{D}$ of the total work.

  • Work Rate = $\frac{\text{Amount of Work}}{\text{Time Taken}}$
  • If the total work is considered as 1 unit, then Work Rate = $\frac{1}{\text{Time Taken}}$
  • Total Work = Work Rate $\times$ Time Taken

Calculating Individual and Group Work Rates

We are given the following information:

  • A single woman takes 150 days to complete the work.
  • 20 women and 15 men together complete the work in 6 days.

Let's define the work rates:

  • Let the daily work rate of a single woman be $W$.
  • Let the daily work rate of a single man be $M$.

From the first piece of information:

The daily work rate of a single woman ($W$) is $\frac{1}{150}$ of the work per day.

So, $W = \frac{1}{150}$.

Now, consider the group working together:

  • The combined daily work rate of 20 women is $20 \times W = 20 \times \frac{1}{150}$.
  • The combined daily work rate of 15 men is $15 \times M$.

When they work together, their total combined daily work rate is the sum of their individual combined rates:

Total combined daily work rate = $20W + 15M$

We know that this group completes the work in 6 days. This means their total combined daily work rate is $\frac{1}{6}$ of the total work per day.

So, we can set up the equation:

$20W + 15M = \frac{1}{6}$

Solving for the Man's Work Rate

Now, substitute the value of $W$ into the equation:

$20 \left(\frac{1}{150}\right) + 15M = \frac{1}{6}$

Simplify the term for women's work:

$\frac{20}{150} + 15M = \frac{1}{6}$

Reduce the fraction $\frac{20}{150}$:

$\frac{20}{150} = \frac{2}{15}$

The equation becomes:

$\frac{2}{15} + 15M = \frac{1}{6}$

To find $15M$, subtract $\frac{2}{15}$ from both sides of the equation:

$15M = \frac{1}{6} - \frac{2}{15}$

To subtract the fractions on the right side, find a common denominator for 6 and 15. The least common multiple (LCM) of 6 and 15 is 30.

  • $\frac{1}{6} = \frac{1 \times 5}{6 \times 5} = \frac{5}{30}$
  • $\frac{2}{15} = \frac{2 \times 2}{15 \times 2} = \frac{4}{30}$

Now perform the subtraction:

$15M = \frac{5}{30} - \frac{4}{30}$

$15M = \frac{1}{30}$

To find $M$ (the daily work rate of a single man), divide both sides by 15:

$M = \frac{1}{30 \times 15}$

$M = \frac{1}{450}$

Determining the Time for a Single Man

The daily work rate of a single man is $M = \frac{1}{450}$. This means a single man completes $\frac{1}{450}$ of the total work in one day.

The time taken for a single man to complete the entire work is the reciprocal of his daily work rate:

Time Taken for Single Man = $\frac{1}{M} = \frac{1}{1/450} = 450$ days.

Therefore, a single man can complete the work in 450 days.

Summary of Steps

  1. Identify the daily work rate of a single woman based on the time given.
  2. Set up an equation for the combined daily work rate of the group (20 women and 15 men) based on the total time they take.
  3. Substitute the woman's work rate into the equation.
  4. Solve the equation to find the daily work rate of a single man.
  5. Calculate the time taken for a single man by taking the reciprocal of his daily work rate.

The calculation shows that a single man takes 450 days to complete the work.

Worker Type Time Taken (Days) Daily Work Rate
Single Woman 150 $\frac{1}{150}$
Single Man ? $M = \frac{1}{450}$
20 Women & 15 Men 6 $\frac{1}{6}$

Revision Table: Work and Time Concepts

Understanding the relationship between work, rate, and time is key to solving these types of problems.

Concept Formula Explanation
Work Rate Rate = Work / Time Amount of work done per unit of time. Often expressed as a fraction of total work per day.
Total Work Work = Rate $\times$ Time The total amount of work to be completed (often normalized to 1).
Combined Rate Rate$_{total}$ = Rate$_1$ + Rate$_2$ + ... When multiple people work together, their individual rates are added to find the total combined rate.
Time Taken Time = Work / Rate The time needed to complete a certain amount of work at a given rate. If work is 1, Time = 1 / Rate.

Additional Information: Solving Work Problems

Work and time problems often involve multiple people or machines working at different rates. Here are some common strategies:

  • Assume Total Work as 1: It's standard to consider the total work to be completed as '1 unit'. This simplifies calculations as rates become fractions like 1/Time.
  • Calculate Daily Rates: Always convert the given time into a daily rate (or rate per hour, etc., depending on the time unit).
  • Combine Rates: If people work together, add their individual rates to find their combined rate. This is only true if they work simultaneously on the same task and their efficiency doesn't change.
  • Use Equations: Set up equations based on the fact that the sum of the work done by each person or group equals the total work (usually 1) when they work for a certain time.
  • Solve for Unknown Rate/Time: Use algebraic methods to solve the equation for the unknown work rate or the unknown time taken.

These problems are a common application of inverse proportionality, as rate and time are inversely proportional (higher rate means less time to complete the same work).

Was this answer helpful?

Similar Questions

  1. Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?

  2. A man can do a piece of work in 30 hours. If he works with his son then the same piece of work is finished in 20 hours. If the son works alone, he can do the work in:

  3. To do a certain work, A and B work on alternate days with B beginning the work on the first day. A alone can complete the same work in 24 days. If the work gets completed in  \(11 \frac{1}{3}\)  days, then B alone can complete  \(\rm \frac{7}{9}^{th}\)  part of the original work in:

  4. Two men and 7 women can complete a work in 28 days whereas 6 men and 16 women can do the same work in 11 days. In how many days can 7 men complete the same work?

  5. 4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 25 women complete it?

  6. Raju and Rajat working together take 5 days to complete a piece of work. If Raju alone can do this work in 7 days, how long would Rajat take to complete the same work?

  7. P and Q together can complete a piece of work in 6 days. If P can alone complete the work in 18 days, then the number of days required for Q to finish the work is:

  8. If Mohit can complete \(\frac{2}{3}\)rd of a work in 24 days, then in how many days can \(\rm\frac{1}{9}^{th}\) of the work be complete by him?

  9. A is 50% more efficient then B. B worked to finish the same work in 20 days. If A and B worked together, then how much time will they take to finish the same work?

  10. A worker completes \(\frac{3}{5}\) of a work in 12 days. In how many days will he complete \(\frac{3}{4}\) of the work? 


Important Questions from Work Efficiency

  1. Sumi can complete a job working 5 hours per day in 2 days. If she doubles her working hours per day, then in how many days will she complete the work?

  2. Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?

  3. A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?

  4. 24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?

  5. 3 men working 7 hours a day can complete a piece of work in 45 days. In how many days will 9 men working 6 hours a day complete the same work?

Need Expert Advice?
Upcoming Exams
SSC JHT
September 08, 2026
SSC Stenographer
September 09, 2026
SSC Selection Post
September 16, 2026
Test Series
SSC CGL img
SSC
SSC CGL (Tier I + Tier II) 2026 Mock Test Series - Latest Pattern
2501 Tests 6 Tests Free
4063 Attempts
4.2(839)
English, Hindi

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App