All Exams Test series for 1 year @ ₹349 only
Question

P and Q together can complete a piece of work in 6 days. If P can alone complete the work in 18 days, then the number of days required for Q to finish the work is:

This question was previously asked in
SSC CGL 2023 (Tier-II) Paper 1 Previous Year Paper (26-Oct-2023) (Shift-1)
The correct answer is

9 days

Understanding the Work and Time Problem

This problem involves the concept of work and time, specifically dealing with the rates at which individuals or groups complete a task. The key idea is that if someone can complete a work in \( d \) days, their work rate is \( \frac{1}{d} \) of the work per day. When people work together, their individual work rates add up to form the combined work rate.

Setting up the Problem Equations

We are given the following information:

  • P and Q together can complete the work in 6 days.
  • P alone can complete the work in 18 days.

Let's denote the number of days Q takes to complete the work alone as \( Q_{days} \).

Based on the work rate concept:

  • Work rate of (P + Q) together = \( \frac{1}{6} \) of the work per day.
  • Work rate of P alone = \( \frac{1}{18} \) of the work per day.
  • Work rate of Q alone = \( \frac{1}{Q_{days}} \) of the work per day.

Calculating the Work Rate of Q

When P and Q work together, their combined work rate is the sum of their individual work rates. So, we can write the equation:

Work rate of P + Work rate of Q = Work rate of (P + Q)

Substituting the values we know:

\( \frac{1}{18} + \frac{1}{Q_{days}} = \frac{1}{6} \)

To find the work rate of Q, we need to isolate \( \frac{1}{Q_{days}} \):

\( \frac{1}{Q_{days}} = \frac{1}{6} - \frac{1}{18} \)

To subtract the fractions, we find a common denominator, which is 18. We convert \( \frac{1}{6} \) to an equivalent fraction with a denominator of 18:

\( \frac{1}{6} = \frac{1 \times 3}{6 \times 3} = \frac{3}{18} \)

Now, substitute this back into the equation:

\( \frac{1}{Q_{days}} = \frac{3}{18} - \frac{1}{18} \)

Subtract the fractions:

\( \frac{1}{Q_{days}} = \frac{3 - 1}{18} = \frac{2}{18} \)

Simplify the fraction \( \frac{2}{18} \):

\( \frac{2}{18} = \frac{1}{9} \)

So, we have:

\( \frac{1}{Q_{days}} = \frac{1}{9} \)

This means that Q's work rate is \( \frac{1}{9} \) of the work per day. If Q completes \( \frac{1}{9} \) of the work in one day, Q will take 9 days to complete the entire work alone.

Therefore, the number of days required for Q to finish the work alone is 9 days.

Summary of Work Rates
Entity Time Taken (Days) Work Rate (Work/Day)
P + Q 6 \( \frac{1}{6} \)
P 18 \( \frac{1}{18} \)
Q \( Q_{days} \) \( \frac{1}{Q_{days}} \)

Conclusion on Q's Time to Finish Work

Based on our calculation, Q takes 9 days to complete the work alone. This matches one of the given options.

Revision Table: Key Concepts

Work and Time Concepts
Concept Description Formula
Work Rate Amount of work done per unit of time (e.g., per day). Work Rate = \( \frac{1}{\text{Time Taken}} \)
Combined Work Rate The sum of individual work rates when multiple people work together. Rate\(_{1}\) + Rate\(_{2}\) + ... = Rate\(_{Combined}\)
Time from Work Rate If the work rate is \( r \) per day, the time taken to complete the work is \( \frac{1}{r} \) days. Time Taken = \( \frac{1}{\text{Work Rate}} \)

Additional Information on Work Problems

Work and time problems often involve calculating rates and combining them. Understanding fractions is crucial, as work rates are typically expressed as fractions of the total work completed per unit of time. Problems can become more complex with varying work rates, breaks, or multiple groups working simultaneously.

  • Always ensure the time units are consistent (e.g., all in days or all in hours).
  • The total work is often considered '1 unit' or 'the whole work'.
  • If someone works for \( t \) days at a rate of \( r \) per day, the amount of work done is \( r \times t \).
Was this answer helpful?

Similar Questions

  1. Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?

  2. A man can do a piece of work in 30 hours. If he works with his son then the same piece of work is finished in 20 hours. If the son works alone, he can do the work in:

  3. To do a certain work, A and B work on alternate days with B beginning the work on the first day. A alone can complete the same work in 24 days. If the work gets completed in  \(11 \frac{1}{3}\)  days, then B alone can complete  \(\rm \frac{7}{9}^{th}\)  part of the original work in:

  4. Two men and 7 women can complete a work in 28 days whereas 6 men and 16 women can do the same work in 11 days. In how many days can 7 men complete the same work?

  5. 4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 25 women complete it?

  6. Raju and Rajat working together take 5 days to complete a piece of work. If Raju alone can do this work in 7 days, how long would Rajat take to complete the same work?

  7. If Mohit can complete \(\frac{2}{3}\)rd of a work in 24 days, then in how many days can \(\rm\frac{1}{9}^{th}\) of the work be complete by him?

  8. A is 50% more efficient then B. B worked to finish the same work in 20 days. If A and B worked together, then how much time will they take to finish the same work?

  9. 20 women and 15 men together can complete a work in 6 days. It takes 150 days for a single woman to complete the work. In how many days can a single man complete the work?

  10. A worker completes \(\frac{3}{5}\) of a work in 12 days. In how many days will he complete \(\frac{3}{4}\) of the work? 


Important Questions from Work Efficiency

  1. Sumi can complete a job working 5 hours per day in 2 days. If she doubles her working hours per day, then in how many days will she complete the work?

  2. Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?

  3. A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?

  4. 24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?

  5. 3 men working 7 hours a day can complete a piece of work in 45 days. In how many days will 9 men working 6 hours a day complete the same work?

Need Expert Advice?
Upcoming Exams
SSC JHT
September 08, 2026
SSC Stenographer
September 09, 2026
SSC Selection Post
September 16, 2026
Test Series
SSC CGL img
SSC
SSC CGL (Tier I + Tier II) 2026 Mock Test Series - Latest Pattern
2501 Tests 6 Tests Free
4031 Attempts
4.2(839)
English, Hindi

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App