All Exams Test series for 1 year @ ₹349 only
Question

Raju and Rajat working together take 5 days to complete a piece of work. If Raju alone can do this work in 7 days, how long would Rajat take to complete the same work?

This question was previously asked in
SSC CGL 2023 (Tier-II) Paper 1 Previous Year Paper (26-Oct-2023) (Shift-1)
The correct answer is

17.5 days

Calculating Work and Time: Raju and Rajat's Task

This problem involves calculating individual work rates and combined work rates to find the time taken by one person when the combined time and another person's individual time are known. It's a classic work and time problem frequently seen in aptitude tests.

Understanding the Concept of Work Rate

The work rate of a person is the amount of work they can complete in one unit of time (usually one day). If a person completes a whole work in 'n' days, their work rate per day is \( \frac{1}{n} \).

Analyzing the Given Information

  • Raju and Rajat together complete the work in 5 days.
  • Raju alone completes the work in 7 days.
  • We need to find the time Rajat alone takes to complete the same work.

Calculating Individual and Combined Work Rates

  • The combined work rate of Raju and Rajat is \( \frac{1}{5} \) of the work per day.
  • Raju's individual work rate is \( \frac{1}{7} \) of the work per day.
  • Let Rajat take 'x' days to complete the work alone. Rajat's individual work rate is \( \frac{1}{x} \) of the work per day.

Setting up the Equation for Combined Work Rate

The combined work rate is the sum of the individual work rates. So, we can write the equation:

\( \text{Combined Work Rate} = \text{Raju's Work Rate} + \text{Rajat's Work Rate} \)

\( \frac{1}{5} = \frac{1}{7} + \frac{1}{x} \)

Solving for Rajat's Time

To find the time Rajat takes, we need to solve this equation for \( \frac{1}{x} \), which is Rajat's work rate.

  • Subtract Raju's work rate from the combined work rate:

    \( \frac{1}{x} = \frac{1}{5} - \frac{1}{7} \)

  • Find a common denominator for the fractions on the right side. The least common multiple of 5 and 7 is 35.

    \( \frac{1}{x} = \frac{1 \times 7}{5 \times 7} - \frac{1 \times 5}{7 \times 5} \)

    \( \frac{1}{x} = \frac{7}{35} - \frac{5}{35} \)

  • Subtract the fractions:

    \( \frac{1}{x} = \frac{7 - 5}{35} \)

    \( \frac{1}{x} = \frac{2}{35} \)

  • Since \( \frac{1}{x} \) is Rajat's work rate per day, 'x' is the number of days Rajat takes to complete the work. To find 'x', we take the reciprocal of \( \frac{2}{35} \).

    \( x = \frac{35}{2} \)

  • Convert the fraction to a decimal:

    \( x = 17.5 \)

Conclusion

Rajat would take 17.5 days to complete the same work alone.

Revision Table: Work and Time Calculation

Individual/Combined Time Taken (Days) Work Rate (Work/Day)
Raju and Rajat (Together) 5 \( \frac{1}{5} \)
Raju (Alone) 7 \( \frac{1}{7} \)
Rajat (Alone) \( x \) \( \frac{1}{x} \)
Relationship - \( \frac{1}{5} = \frac{1}{7} + \frac{1}{x} \)

Additional Information: Work and Time Concepts

Work and Time problems are common in competitive exams. Key concepts include:

  • Total Work: Often assumed to be 1 unit or a common multiple of the individual times to simplify calculations.
  • Efficiency: Work rate is directly proportional to efficiency. A more efficient person has a higher work rate and takes less time.
  • Relationship between Work, Rate, and Time: Work = Rate × Time. If work is constant, Rate is inversely proportional to Time.
  • Multiple Workers: When multiple people work together, their individual work rates are added to find the combined work rate.

Understanding these concepts helps in solving variations of work and time problems involving different scenarios like alternating days, different efficiencies, or partial work completion.

Was this answer helpful?

Similar Questions

  1. X and Y can complete a work in 9 days and 36 days, respectively. X begins to do the work and they work alternately one at a time for one day each. The whole work will be complete in:

  2. P is two times as efficient as Q. P is able to complete a piece of work in 40 days less than Q. Working together, the whole number of days taken by them to complete the work is:

    (Round off to the nearest integer)

  3. 4 women or 6 boys can finish a work in the same number of days. A boy can finish it in 60 days. In how many days can 5 women finish the work, working together every day?

  4. To do a certain work, Ajay and Bharat work on alternate days, with Bharat starting the work on the first day. Ajay can finish the work alone in 32 days. If the work gets completed in exactly 8 days, then Bharat alone can finish 7 times the same work in ____________ days.

  5. A, B and C can separately complete a work in 12, 15 and 20 days, respectively. They worked together 4 days. What will be the remaining work?

  6. A, B and C, working alone, can complete a job in 16, 24 and 36 days, respectively. In how many days can they complete the job if they work together?

  7. Rakshit, Ajay, and Satish are sanitation workers in a Municipal Corporation. Rakshit alone takes 20 hours to clean a drain while Ajay takes 12 hours when working alone to do the same. All three together take only 5 hours to clean the drain. In how many hours, can Satish complete the work alone?

  8. 15 men and 25 women can complete a piece of work in 9.6 days. If 16 women can complete the same work in 27 days, find the number of days in which 16 men can complete the same work.  

  9. A,B and C can do a piece of work in 30 days, 40 days and 50 days, respectively. Beginning with A, if A, B and C do the work alternatively then in how many days will the work be finished?

  10. Ravi can do a piece of work in 40 days and Sudha can do the same piece of work in 60 days. If they work on alternative days starting with Sudha on the first day, then in how many days will the work be completed?


Important Questions from Work Efficiency

  1. A and B working together can complete a job in 30 days. The ratio of their efficiencies is 3 : 2. In how many days can the faster person complete the job?

  2. A takes 15 days to complete \(\frac{5}{7} \)  of a work. With the help of B, they finish the whole work in 12 days. In how many days, B alone will complete the same work

  3. A alone can complete a work in 14 days and B alone can complete the same work in 21 days. A and B start the work together but A leaves the work after 4 days of the starting of work. In how many days B will complete the remaining work?

  4. For completing a certain work, A is 50% less efficient than B and B is 50% more efficient than C. Working together A, B and C can complete the work in 48 days. A alone can complete the same work in:

  5. 30 persons can do a piece of work in 24 days. How many more persons are required to complete the work in 20 days?

Need Expert Advice?
Upcoming Exams
SSC JHT
September 08, 2026
SSC Stenographer
September 09, 2026
SSC Selection Post
September 16, 2026
Test Series
SSC CGL img
SSC
SSC CGL (Tier I + Tier II) 2026 Mock Test Series - Latest Pattern
2500 Tests 6 Tests Free
3995 Attempts
4.2(838)
English, Hindi

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App