To do a certain work, Ajay and Bharat work on alternate days, with Bharat starting the work on the first day. Ajay can finish the work alone in 32 days. If the work gets completed in exactly 8 days, then Bharat alone can finish 7 times the same work in ____________ days.
32
Let's break down this work and time problem involving Ajay and Bharat working on alternate days.
We are told that Ajay and Bharat work on a certain job on alternate days, with Bharat starting the work on the first day. The total time taken to complete the work is exactly 8 days.
The sequence of work days looks like this:
In a total duration of 8 days, each person works for 4 days.
We are given that Ajay can finish the entire work alone in 32 days. This means Ajay's per-day work rate is:
\( \text{Ajay's work rate} = \frac{1}{\text{Time Ajay takes alone}} = \frac{1}{32} \) of the work per day.
Since Ajay works for 4 days in the 8-day period, the amount of work done by Ajay is:
\( \text{Work done by Ajay in 4 days} = \text{Ajay's work rate} \times \text{Number of days Ajay worked} \)
\( \text{Work done by Ajay} = \frac{1}{32} \times 4 = \frac{4}{32} = \frac{1}{8} \) of the total work.
The total work completed in 8 days is the sum of the work done by Bharat and Ajay. Since the work is completed, the total work done is considered as 1 unit.
\( \text{Total Work} = \text{Work done by Bharat} + \text{Work done by Ajay} \)
\( 1 = \text{Work done by Bharat} + \frac{1}{8} \)
So, the work done by Bharat in his 4 days of work is:
\( \text{Work done by Bharat} = 1 - \frac{1}{8} = \frac{8}{8} - \frac{1}{8} = \frac{7}{8} \) of the total work.
Bharat completed \( \frac{7}{8} \) of the work by working for 4 days. We can now find Bharat's per-day work rate:
\( \text{Bharat's work rate} = \frac{\text{Work done by Bharat}}{\text{Number of days Bharat worked}} \)
\( \text{Bharat's work rate} = \frac{7/8}{4} = \frac{7}{8} \times \frac{1}{4} = \frac{7}{32} \) of the work per day.
If Bharat completes \( \frac{7}{32} \) of the work in 1 day, the time taken by Bharat to complete the entire work (1 unit) alone is the reciprocal of his work rate:
\( \text{Time Bharat takes alone} = \frac{1}{\text{Bharat's work rate}} = \frac{1}{7/32} = \frac{32}{7} \) days.
The question asks for the time Bharat alone can finish 7 times the same work. If Bharat takes \( \frac{32}{7} \) days to complete 1 unit of work, the time taken to complete 7 units of work will be:
\( \text{Time for 7 times work} = \text{Time Bharat takes for 1 unit} \times 7 \)
\( \text{Time for 7 times work} = \frac{32}{7} \times 7 = 32 \) days.
Therefore, Bharat alone can finish 7 times the same work in 32 days.
| Person | Time to complete 1 unit of work (alone) | Days worked in 8-day cycle | Work done in 8-day cycle | Per day work rate |
|---|---|---|---|---|
| Ajay | 32 days | 4 days | \( 4 \times \frac{1}{32} = \frac{1}{8} \) | \( \frac{1}{32} \) |
| Bharat | \( \frac{32}{7} \) days (Calculated) | 4 days | \( 1 - \frac{1}{8} = \frac{7}{8} \) | \( \frac{7/8}{4} = \frac{7}{32} \) |
| Ajay & Bharat (Alternate) | 8 days | - | 1 (Complete Work) | - |
The final answer is 32 days.
| Concept | Description | Formula |
|---|---|---|
| Work Rate | Amount of work done by a person in one unit of time (e.g., per day, per hour). | \( \text{Work Rate} = \frac{1}{\text{Total Time to complete work alone}} \) |
| Work Done | Work completed by a person in a given time. | \( \text{Work Done} = \text{Work Rate} \times \text{Time Worked} \) |
| Total Time (Individual) | Time taken by a person to complete the entire work alone. | \( \text{Total Time} = \frac{1}{\text{Work Rate}} \) |
| Alternate Days Work | Individuals work on consecutive days one after another. The work done in one cycle (e.g., 2 days for two people) is the sum of their individual work rates for that cycle. | Work done in a cycle = Sum of work done by each person in their turn during that cycle. |
Work and time problems often involve calculating the efficiency or work rate of individuals or groups and then determining the time required to complete a certain amount of work. Key steps often include:
Always pay attention to who starts the work and the total duration when dealing with alternate day problems, as this determines how many days each person contributes.
X and Y can complete a work in 9 days and 36 days, respectively. X begins to do the work and they work alternately one at a time for one day each. The whole work will be complete in:
P is two times as efficient as Q. P is able to complete a piece of work in 40 days less than Q. Working together, the whole number of days taken by them to complete the work is:
(Round off to the nearest integer)
4 women or 6 boys can finish a work in the same number of days. A boy can finish it in 60 days. In how many days can 5 women finish the work, working together every day?
A, B and C can separately complete a work in 12, 15 and 20 days, respectively. They worked together 4 days. What will be the remaining work?
A, B and C, working alone, can complete a job in 16, 24 and 36 days, respectively. In how many days can they complete the job if they work together?
Rakshit, Ajay, and Satish are sanitation workers in a Municipal Corporation. Rakshit alone takes 20 hours to clean a drain while Ajay takes 12 hours when working alone to do the same. All three together take only 5 hours to clean the drain. In how many hours, can Satish complete the work alone?
15 men and 25 women can complete a piece of work in 9.6 days. If 16 women can complete the same work in 27 days, find the number of days in which 16 men can complete the same work.
A,B and C can do a piece of work in 30 days, 40 days and 50 days, respectively. Beginning with A, if A, B and C do the work alternatively then in how many days will the work be finished?
Ravi can do a piece of work in 40 days and Sudha can do the same piece of work in 60 days. If they work on alternative days starting with Sudha on the first day, then in how many days will the work be completed?
Working 5 hours a day, A can complete a task in 8 days and working 6 hours a day, B can finish the same task in 10 days, working 8 hours a day, they can jointly complete the task in __________.
A and B working together can complete a job in 30 days. The ratio of their efficiencies is 3 : 2. In how many days can the faster person complete the job?
A takes 15 days to complete \(\frac{5}{7} \) of a work. With the help of B, they finish the whole work in 12 days. In how many days, B alone will complete the same work
A alone can complete a work in 14 days and B alone can complete the same work in 21 days. A and B start the work together but A leaves the work after 4 days of the starting of work. In how many days B will complete the remaining work?
For completing a certain work, A is 50% less efficient than B and B is 50% more efficient than C. Working together A, B and C can complete the work in 48 days. A alone can complete the same work in:
30 persons can do a piece of work in 24 days. How many more persons are required to complete the work in 20 days?