X and Y can complete a work in 9 days and 36 days, respectively. X begins to do the work and they work alternately one at a time for one day each. The whole work will be complete in:
This problem involves two individuals, X and Y, working on a task alternately. To solve this type of work and time problem, we first need to determine their individual work rates and then calculate the amount of work done in one complete cycle of alternation.
The work rate of a person is the amount of work they can complete in one day. It is the reciprocal of the number of days they take to complete the whole work.
They work alternately, with X starting. A full cycle consists of X working for one day and then Y working for one day. This cycle spans two days.
Work done in one cycle (2 days) = Work done by X on Day 1 + Work done by Y on Day 2
Work done in one cycle = $\frac{1}{9} + \frac{1}{36}$
To add these fractions, we find a common denominator, which is 36.
$\frac{1}{9} = \frac{1 \times 4}{9 \times 4} = \frac{4}{36}$
Work done in one cycle = $\frac{4}{36} + \frac{1}{36} = \frac{4+1}{36} = \frac{5}{36}$ of the work.
So, $\frac{5}{36}$ of the work is completed in every 2-day cycle.
We need to find out how many full cycles are required to complete as much work as possible without exceeding the total work (which is 1). The work done per cycle is $\frac{5}{36}$.
Let $n$ be the number of cycles. The work done after $n$ cycles is $n \times \frac{5}{36}$. We want to find the largest integer $n$ such that $n \times \frac{5}{36} < 1$.
Multiply both sides by 36:
$5n < 36$
$n < \frac{36}{5} = 7.2$
The largest integer $n$ less than 7.2 is 7. So, 7 full cycles will be completed.
Time taken for 7 cycles = 7 cycles $\times$ 2 days/cycle = 14 days.
Work completed after 7 cycles = 7 $\times \frac{5}{36} = \frac{35}{36}$ of the work.
After 7 cycles, the remaining work is:
Remaining work = Total work - Work done after 7 cycles
Remaining work = $1 - \frac{35}{36} = \frac{36}{36} - \frac{35}{36} = \frac{1}{36}$ of the work.
After 7 full cycles (14 days), X just finished their turn as the last person in the 7th cycle (since X starts the first cycle). Thus, it is X's turn to work on the 15th day.
X's work rate is $\frac{1}{9}$ of the work per day.
The remaining work is $\frac{1}{36}$.
Time taken by X to complete the remaining work = $\frac{\text{Remaining Work}}{\text{X's Work Rate}}$
Time taken by X = $\frac{1/36}{1/9} = \frac{1}{36} \times \frac{9}{1} = \frac{9}{36} = \frac{1}{4}$ day.
The total time taken to complete the work is the time for 7 cycles plus the time taken by X to complete the remaining work.
Total time = Time for 7 cycles + Time for remaining work
Total time = 14 days + $\frac{1}{4}$ day = $14 \frac{1}{4}$ days.
Thus, the whole work will be complete in $14 \frac{1}{4}$ days.
| Day | Worker | Work Done on Day | Total Work Done |
|---|---|---|---|
| 1 | X | $\frac{1}{9}$ | $\frac{1}{9}$ |
| 2 | Y | $\frac{1}{36}$ | $\frac{1}{9} + \frac{1}{36} = \frac{5}{36}$ (End of Cycle 1) |
| 3 | X | $\frac{1}{9}$ | $\frac{5}{36} + \frac{1}{9} = \frac{5}{36} + \frac{4}{36} = \frac{9}{36}$ |
| 4 | Y | $\frac{1}{36}$ | $\frac{9}{36} + \frac{1}{36} = \frac{10}{36}$ (End of Cycle 2) |
| ... | ... | ... | ... |
| 13 | X | $\frac{1}{9}$ | (Work after 6 cycles) + $\frac{1}{9} = \frac{6 \times 5}{36} + \frac{1}{9} = \frac{30}{36} + \frac{4}{36} = \frac{34}{36}$ |
| 14 | Y | $\frac{1}{36}$ | $\frac{34}{36} + \frac{1}{36} = \frac{35}{36}$ (End of Cycle 7) |
| 15 | X | Work needed: $\frac{1}{36}$ | $\frac{35}{36} + \frac{1}{36} = \frac{36}{36} = 1$ (Work complete) |
| Time taken by X on Day 15 | $\frac{\text{Remaining Work}}{\text{X's Rate}} = \frac{1/36}{1/9} = \frac{1}{4}$ day | ||
| Total Time | 14 days (for 7 cycles) + $\frac{1}{4}$ day = $14 \frac{1}{4}$ days |
| Concept | Explanation | Formula |
|---|---|---|
| Work Rate | Amount of work done by a person in one unit of time (e.g., per day). | Work Rate = $\frac{1}{\text{Time taken to complete work}}$ |
| Total Work | Usually considered as 1 unit or a common multiple of individual times. | |
| Work Done | Work Done = Work Rate $\times$ Time | |
| Alternating Work | People work on consecutive days or time units. Calculate work done in one cycle of turns. | Work per cycle = Sum of work rates for one turn of each person in the cycle |
When solving alternating work problems, it is crucial to identify:
Always pay attention to who starts the work, as this determines whose turn it is after a certain number of days or cycles.
P is two times as efficient as Q. P is able to complete a piece of work in 40 days less than Q. Working together, the whole number of days taken by them to complete the work is:
(Round off to the nearest integer)
4 women or 6 boys can finish a work in the same number of days. A boy can finish it in 60 days. In how many days can 5 women finish the work, working together every day?
To do a certain work, Ajay and Bharat work on alternate days, with Bharat starting the work on the first day. Ajay can finish the work alone in 32 days. If the work gets completed in exactly 8 days, then Bharat alone can finish 7 times the same work in ____________ days.
A, B and C can separately complete a work in 12, 15 and 20 days, respectively. They worked together 4 days. What will be the remaining work?
A, B and C, working alone, can complete a job in 16, 24 and 36 days, respectively. In how many days can they complete the job if they work together?
Rakshit, Ajay, and Satish are sanitation workers in a Municipal Corporation. Rakshit alone takes 20 hours to clean a drain while Ajay takes 12 hours when working alone to do the same. All three together take only 5 hours to clean the drain. In how many hours, can Satish complete the work alone?
15 men and 25 women can complete a piece of work in 9.6 days. If 16 women can complete the same work in 27 days, find the number of days in which 16 men can complete the same work.
A,B and C can do a piece of work in 30 days, 40 days and 50 days, respectively. Beginning with A, if A, B and C do the work alternatively then in how many days will the work be finished?
Ravi can do a piece of work in 40 days and Sudha can do the same piece of work in 60 days. If they work on alternative days starting with Sudha on the first day, then in how many days will the work be completed?
Working 5 hours a day, A can complete a task in 8 days and working 6 hours a day, B can finish the same task in 10 days, working 8 hours a day, they can jointly complete the task in __________.
A and B working together can complete a job in 30 days. The ratio of their efficiencies is 3 : 2. In how many days can the faster person complete the job?
A takes 15 days to complete \(\frac{5}{7} \) of a work. With the help of B, they finish the whole work in 12 days. In how many days, B alone will complete the same work
A alone can complete a work in 14 days and B alone can complete the same work in 21 days. A and B start the work together but A leaves the work after 4 days of the starting of work. In how many days B will complete the remaining work?
For completing a certain work, A is 50% less efficient than B and B is 50% more efficient than C. Working together A, B and C can complete the work in 48 days. A alone can complete the same work in:
30 persons can do a piece of work in 24 days. How many more persons are required to complete the work in 20 days?