Rakshit, Ajay, and Satish are sanitation workers in a Municipal Corporation. Rakshit alone takes 20 hours to clean a drain while Ajay takes 12 hours when working alone to do the same. All three together take only 5 hours to clean the drain. In how many hours, can Satish complete the work alone?
15
This question involves calculating the individual work rate and time taken by Satish based on the combined work rates of Rakshit, Ajay, and Satish. Work rate is the amount of work done per unit of time. If someone takes \(T\) hours to complete a task, their work rate is \( \frac{1}{T} \) of the task per hour.
The sum of the individual work rates equals the combined work rate:
$$ \text{Rakshit's Rate} + \text{Ajay's Rate} + \text{Satish's Rate} = \text{Combined Rate} $$
$$ \frac{1}{20} + \frac{1}{12} + \frac{1}{S} = \frac{1}{5} $$
To find \( S \), we need to isolate \( \frac{1}{S} \):
$$ \frac{1}{S} = \frac{1}{5} - \frac{1}{20} - \frac{1}{12} $$
To subtract the fractions on the right side, we need a common denominator. The least common multiple (LCM) of 5, 20, and 12 is 60.
Convert each fraction to have a denominator of 60:
Now substitute these back into the equation:
$$ \frac{1}{S} = \frac{12}{60} - \frac{3}{60} - \frac{5}{60} $$
Combine the fractions on the right side:
$$ \frac{1}{S} = \frac{12 - 3 - 5}{60} $$
$$ \frac{1}{S} = \frac{4}{60} $$
Simplify the fraction on the right side:
$$ \frac{1}{S} = \frac{1}{15} $$
To find \( S \), take the reciprocal of both sides:
$$ S = 15 $$
So, Satish can complete the work alone in 15 hours.
| Person | Time Alone (Hours) | Work Rate (per hour) |
|---|---|---|
| Rakshit | 20 | \( \frac{1}{20} \) |
| Ajay | 12 | \( \frac{1}{12} \) |
| Satish | \( S \) | \( \frac{1}{S} \) |
| Rakshit, Ajay, & Satish (Combined) | 5 | \( \frac{1}{5} \) |
By calculating the work rates and setting up the equation based on the combined work rate, we found that Satish takes 15 hours to complete the drain cleaning work alone.
| Concept | Explanation | Formula |
|---|---|---|
| Work Rate | Amount of work done per unit of time. | Work Rate = \( \frac{1}{\text{Time Taken}} \) |
| Total Work | Usually considered as 1 unit (the complete task). | Work Rate \( \times \) Time = Total Work |
| Combined Work Rate | Sum of individual work rates when multiple people work together. | \( Rate_1 + Rate_2 + ... + Rate_n = Rate_{combined} \) |
Time and Work problems are common in quantitative aptitude. They often involve people or machines working together or separately to complete a task. Key principles include:
Understanding how to find the LCM to add or subtract fractions is crucial for solving these types of problems efficiently.
X and Y can complete a work in 9 days and 36 days, respectively. X begins to do the work and they work alternately one at a time for one day each. The whole work will be complete in:
P is two times as efficient as Q. P is able to complete a piece of work in 40 days less than Q. Working together, the whole number of days taken by them to complete the work is:
(Round off to the nearest integer)
4 women or 6 boys can finish a work in the same number of days. A boy can finish it in 60 days. In how many days can 5 women finish the work, working together every day?
To do a certain work, Ajay and Bharat work on alternate days, with Bharat starting the work on the first day. Ajay can finish the work alone in 32 days. If the work gets completed in exactly 8 days, then Bharat alone can finish 7 times the same work in ____________ days.
A, B and C can separately complete a work in 12, 15 and 20 days, respectively. They worked together 4 days. What will be the remaining work?
A, B and C, working alone, can complete a job in 16, 24 and 36 days, respectively. In how many days can they complete the job if they work together?
15 men and 25 women can complete a piece of work in 9.6 days. If 16 women can complete the same work in 27 days, find the number of days in which 16 men can complete the same work.
A,B and C can do a piece of work in 30 days, 40 days and 50 days, respectively. Beginning with A, if A, B and C do the work alternatively then in how many days will the work be finished?
Ravi can do a piece of work in 40 days and Sudha can do the same piece of work in 60 days. If they work on alternative days starting with Sudha on the first day, then in how many days will the work be completed?
Working 5 hours a day, A can complete a task in 8 days and working 6 hours a day, B can finish the same task in 10 days, working 8 hours a day, they can jointly complete the task in __________.
A and B working together can complete a job in 30 days. The ratio of their efficiencies is 3 : 2. In how many days can the faster person complete the job?
A takes 15 days to complete \(\frac{5}{7} \) of a work. With the help of B, they finish the whole work in 12 days. In how many days, B alone will complete the same work
A alone can complete a work in 14 days and B alone can complete the same work in 21 days. A and B start the work together but A leaves the work after 4 days of the starting of work. In how many days B will complete the remaining work?
For completing a certain work, A is 50% less efficient than B and B is 50% more efficient than C. Working together A, B and C can complete the work in 48 days. A alone can complete the same work in:
30 persons can do a piece of work in 24 days. How many more persons are required to complete the work in 20 days?