Ravi can do a piece of work in 40 days and Sudha can do the same piece of work in 60 days. If they work on alternative days starting with Sudha on the first day, then in how many days will the work be completed?
48
This problem involves two individuals, Ravi and Sudha, working on the same task on alternate days. We need to determine the total time taken to complete the work when they follow this alternative day pattern, starting with Sudha.
First, let's figure out how much work each person can do in a single day.
They work on alternative days, starting with Sudha. A cycle consists of two days:
Let's calculate the total work done in one complete cycle (2 days):
Work done in 1 cycle = (Work done by Sudha on Day 1) + (Work done by Ravi on Day 2)
Work done in 1 cycle = \(\frac{1}{60} + \frac{1}{40}\)
To add these fractions, we find a common denominator, which is the LCM of 60 and 40. LCM(60, 40) = 120.
Work done in 1 cycle = \(\frac{2}{120} + \frac{3}{120} = \frac{2+3}{120} = \frac{5}{120} = \frac{1}{24}\)
So, in every 2-day cycle, they complete \(\frac{1}{24}\) of the total work.
The entire work is represented as 1. Since they complete \(\frac{1}{24}\) of the work in one cycle, to complete the full work (1), they would ideally need 24 cycles.
Total cycles required = \(\frac{1}{\text{Work done in 1 cycle}} = \frac{1}{\frac{1}{24}} = 24\) cycles.
Each cycle is 2 days long. So, if they complete the work in exactly 24 cycles, the total number of days would be:
Total days = Number of cycles \(\times\) Days per cycle
Total days = \(24 \times 2 = 48\) days.
Let's check how the work is completed over these 48 days:
Total work done by Sudha = 24 days \(\times\) \(\frac{1}{60}\) work/day = \(\frac{24}{60} = \frac{2}{5}\) of the work.
Total work done by Ravi = 24 days \(\times\) \(\frac{1}{40}\) work/day = \(\frac{24}{40} = \frac{3}{5}\) of the work.
Total work done together = \(\frac{2}{5} + \frac{3}{5} = \frac{5}{5} = 1\) (Complete work).
Since the total work is exactly completed at the end of an even number of days (which is Ravi's turn), the total time taken is indeed 48 days.
Let the total amount of work be the LCM of 40 and 60, which is 120 units.
They work on alternate days starting with Sudha:
Work done in a 2-day cycle = 2 units + 3 units = 5 units.
We need to complete 120 units of work. Let's find how many full 2-day cycles are needed.
Number of full cycles = \(\frac{\text{Total work}}{\text{Work per cycle}} = \frac{120 \text{ units}}{5 \text{ units/cycle}} = 24\) cycles.
Total days for 24 cycles = 24 cycles \(\times\) 2 days/cycle = 48 days.
At the end of 48 days (24 cycles), the total work done is \(24 \times 5 = 120\) units, which is the complete work.
| Worker | Time to Complete Work | Daily Work Rate |
|---|---|---|
| Ravi | 40 days | \(\frac{1}{40}\) |
| Sudha | 60 days | \(\frac{1}{60}\) |
| Day | Worker | Work Done on Day | Cumulative Work |
|---|---|---|---|
| 1 | Sudha | \(\frac{1}{60}\) | \(\frac{1}{60}\) |
| 2 | Ravi | \(\frac{1}{40}\) | \(\frac{1}{60} + \frac{1}{40} = \frac{5}{120} = \frac{1}{24}\) |
| ... (This 2-day pattern repeats) ... | |||
| 47 | Sudha | \(\frac{1}{60}\) | \(\frac{23}{24} + \frac{1}{60}\) (after 23 cycles) |
| 48 | Ravi | \(\frac{1}{40}\) | \(\frac{23}{24} + \frac{1}{60} + \frac{1}{40} = 1\) (after 24 cycles) |
The work is completed precisely at the end of 48 days.
| Concept | Explanation | Formula/Relation |
|---|---|---|
| Work Rate | Amount of work done per unit of time. | Work Rate = \(\frac{\text{Total Work}}{\text{Total Time}}\) |
| Total Work | The entire task to be completed, often considered as 1 unit or the LCM of individual times. | Total Work = Work Rate \(\times\) Total Time |
| Time Taken | The duration required to complete the work. | Time Taken = \(\frac{\text{Total Work}}{\text{Work Rate}}\) |
| Combined Work Rate | Sum of individual work rates when people work together. | Rate\(_{A+B}\) = Rate\(_A\) + Rate\(_B\) (when working together) |
| Alternative Days | Workers perform the task one after another on consecutive days. | Calculate work done in one full cycle (e.g., 2 days or more) |
Problems involving work done on alternate days require careful tracking of who works on which day and how much work is completed in each cycle. A cycle is typically formed by one turn of each worker involved. If there are two workers A and B, a cycle is A works, then B works (or vice versa). If there are three workers A, B, C, a cycle might be A, B, C in order.
Key steps often include:
In this specific problem, the work finished exactly at the end of a cycle, simplifying the last steps.
X and Y can complete a work in 9 days and 36 days, respectively. X begins to do the work and they work alternately one at a time for one day each. The whole work will be complete in:
P is two times as efficient as Q. P is able to complete a piece of work in 40 days less than Q. Working together, the whole number of days taken by them to complete the work is:
(Round off to the nearest integer)
4 women or 6 boys can finish a work in the same number of days. A boy can finish it in 60 days. In how many days can 5 women finish the work, working together every day?
To do a certain work, Ajay and Bharat work on alternate days, with Bharat starting the work on the first day. Ajay can finish the work alone in 32 days. If the work gets completed in exactly 8 days, then Bharat alone can finish 7 times the same work in ____________ days.
A, B and C can separately complete a work in 12, 15 and 20 days, respectively. They worked together 4 days. What will be the remaining work?
A, B and C, working alone, can complete a job in 16, 24 and 36 days, respectively. In how many days can they complete the job if they work together?
Rakshit, Ajay, and Satish are sanitation workers in a Municipal Corporation. Rakshit alone takes 20 hours to clean a drain while Ajay takes 12 hours when working alone to do the same. All three together take only 5 hours to clean the drain. In how many hours, can Satish complete the work alone?
15 men and 25 women can complete a piece of work in 9.6 days. If 16 women can complete the same work in 27 days, find the number of days in which 16 men can complete the same work.
A,B and C can do a piece of work in 30 days, 40 days and 50 days, respectively. Beginning with A, if A, B and C do the work alternatively then in how many days will the work be finished?
Working 5 hours a day, A can complete a task in 8 days and working 6 hours a day, B can finish the same task in 10 days, working 8 hours a day, they can jointly complete the task in __________.
A and B working together can complete a job in 30 days. The ratio of their efficiencies is 3 : 2. In how many days can the faster person complete the job?
A takes 15 days to complete \(\frac{5}{7} \) of a work. With the help of B, they finish the whole work in 12 days. In how many days, B alone will complete the same work
A alone can complete a work in 14 days and B alone can complete the same work in 21 days. A and B start the work together but A leaves the work after 4 days of the starting of work. In how many days B will complete the remaining work?
For completing a certain work, A is 50% less efficient than B and B is 50% more efficient than C. Working together A, B and C can complete the work in 48 days. A alone can complete the same work in:
30 persons can do a piece of work in 24 days. How many more persons are required to complete the work in 20 days?