A, B and C can separately complete a work in 12, 15 and 20 days, respectively. They worked together 4 days. What will be the remaining work?
This problem involves calculating the portion of work remaining after multiple individuals have worked together for a certain period. We need to first determine the individual work rates, then their combined rate, the total work done, and finally, the remaining work.
The work rate of a person is the amount of work they can complete in one day. If a person can complete a total work in 'n' days, their daily work rate is \(\frac{1}{n}\) of the total work.
When A, B, and C work together, their daily work rates add up to find their combined daily work rate.
Combined daily work rate = (A's daily rate) + (B's daily rate) + (C's daily rate)
Combined daily work rate = \(\frac{1}{12} + \frac{1}{15} + \frac{1}{20}\)
To add these fractions, we find a common denominator. The least common multiple (LCM) of 12, 15, and 20 is 60.
Convert each fraction to have a denominator of 60:
Now, add the fractions:
Combined daily work rate = \(\frac{5}{60} + \frac{4}{60} + \frac{3}{60} = \frac{5 + 4 + 3}{60} = \frac{12}{60}\)
Simplify the combined daily work rate:
Combined daily work rate = \(\frac{12}{60} = \frac{1}{5}\) of the work per day.
A, B, and C worked together for 4 days. To find the total work done in 4 days, we multiply their combined daily work rate by the number of days they worked.
Work done in 4 days = (Combined daily work rate) \(\times\) (Number of days worked)
Work done in 4 days = \(\frac{1}{5} \times 4 = \frac{4}{5}\) of the work.
The total work is considered as 1 unit. The remaining work is the total work minus the work that has already been done.
Remaining work = Total work - Work done in 4 days
Remaining work = \(1 - \frac{4}{5}\)
To subtract the fraction from 1, write 1 as a fraction with the same denominator as the work done:
Remaining work = \(\frac{5}{5} - \frac{4}{5} = \frac{5 - 4}{5} = \frac{1}{5}\) of the work.
So, the remaining work is \(\frac{1}{5}\).
| Entity | Time to Complete Work | Daily Work Rate |
|---|---|---|
| A | 12 days | \(\frac{1}{12}\) |
| B | 15 days | \(\frac{1}{15}\) |
| C | 20 days | \(\frac{1}{20}\) |
| A, B, C (Combined) | - | \(\frac{1}{12} + \frac{1}{15} + \frac{1}{20} = \frac{12}{60} = \frac{1}{5}\) |
Work done in 4 days = Combined rate \(\times\) Days worked = \(\frac{1}{5} \times 4 = \frac{4}{5}\)
Remaining work = Total work - Work done = \(1 - \frac{4}{5} = \frac{1}{5}\)
The remaining work is \(\frac{1}{5}\).
| Concept | Explanation | Formula/Relation |
|---|---|---|
| Work Rate | The amount of work done per unit of time (e.g., per day, per hour). | Work Rate = \(\frac{1}{\text{Time taken to complete total work}}\) |
| Total Work | Usually considered as 1 unit when calculating fractions of work. Can also be the LCM of individual times. | Total Work = Work Rate \(\times\) Time |
| Combined Work Rate | The sum of individual work rates when multiple people work together. | Rate\(_{A+B}\) = Rate\(_A\) + Rate\(_B\) |
| Work Done | The portion of the total work completed in a given time. | Work Done = Combined Rate \(\times\) Time Worked |
| Remaining Work | The portion of work yet to be completed. | Remaining Work = Total Work - Work Done |
Work and time problems are common in quantitative aptitude. They typically involve calculating how quickly individuals or groups can complete a task based on their rates of work. Key principles include:
Practicing different variations of work and time problems helps in understanding the application of fractions, ratios, and LCM in real-world scenarios.
X and Y can complete a work in 9 days and 36 days, respectively. X begins to do the work and they work alternately one at a time for one day each. The whole work will be complete in:
P is two times as efficient as Q. P is able to complete a piece of work in 40 days less than Q. Working together, the whole number of days taken by them to complete the work is:
(Round off to the nearest integer)
4 women or 6 boys can finish a work in the same number of days. A boy can finish it in 60 days. In how many days can 5 women finish the work, working together every day?
To do a certain work, Ajay and Bharat work on alternate days, with Bharat starting the work on the first day. Ajay can finish the work alone in 32 days. If the work gets completed in exactly 8 days, then Bharat alone can finish 7 times the same work in ____________ days.
A, B and C, working alone, can complete a job in 16, 24 and 36 days, respectively. In how many days can they complete the job if they work together?
Rakshit, Ajay, and Satish are sanitation workers in a Municipal Corporation. Rakshit alone takes 20 hours to clean a drain while Ajay takes 12 hours when working alone to do the same. All three together take only 5 hours to clean the drain. In how many hours, can Satish complete the work alone?
15 men and 25 women can complete a piece of work in 9.6 days. If 16 women can complete the same work in 27 days, find the number of days in which 16 men can complete the same work.
A,B and C can do a piece of work in 30 days, 40 days and 50 days, respectively. Beginning with A, if A, B and C do the work alternatively then in how many days will the work be finished?
Ravi can do a piece of work in 40 days and Sudha can do the same piece of work in 60 days. If they work on alternative days starting with Sudha on the first day, then in how many days will the work be completed?
Working 5 hours a day, A can complete a task in 8 days and working 6 hours a day, B can finish the same task in 10 days, working 8 hours a day, they can jointly complete the task in __________.
A and B working together can complete a job in 30 days. The ratio of their efficiencies is 3 : 2. In how many days can the faster person complete the job?
A takes 15 days to complete \(\frac{5}{7} \) of a work. With the help of B, they finish the whole work in 12 days. In how many days, B alone will complete the same work
A alone can complete a work in 14 days and B alone can complete the same work in 21 days. A and B start the work together but A leaves the work after 4 days of the starting of work. In how many days B will complete the remaining work?
For completing a certain work, A is 50% less efficient than B and B is 50% more efficient than C. Working together A, B and C can complete the work in 48 days. A alone can complete the same work in:
30 persons can do a piece of work in 24 days. How many more persons are required to complete the work in 20 days?