All Exams Test series for 1 year @ ₹349 only
Question

15 men and 25 women can complete a piece of work in 9.6 days. If 16 women can complete the same work in 27 days, find the number of days in which 16 men can complete the same work.  

This question was previously asked in
SSC CGL 2023 (Tier-II) Paper 1 Previous Year Paper (26-Oct-2023) (Shift-1)
The correct answer is

20.25  

Solving Work and Time Problems

This question involves a classic time and work problem where we need to determine the efficiency of men and women and then calculate the time taken by a certain number of men to complete the task.

Let's denote the amount of work one man can do in one day as \(m\) and the amount of work one woman can do in one day as \(w\). The total amount of work required to complete the task is constant.

Setting Up Equations based on Work Information

We are given two scenarios where the work is completed:

  1. 15 men and 25 women can complete the work in 9.6 days.
  2. 16 women can complete the same work in 27 days.

From the second statement, we can find the total amount of work in terms of the work rate of women (\(w\)).

Total Work = (Number of workers) $\times$ (Work rate per worker) $\times$ (Time taken)

Using the second statement:

Total Work = \(16 \text{ women} \times w \text{ (work per woman per day)} \times 27 \text{ days}\)

Total Work = \(16 \times 27 \times w = 432w\)

Now, using the first statement, we can express the total work in terms of both men's and women's work rates:

Total Work = \((15 \text{ men} \times m + 25 \text{ women} \times w) \times 9.6 \text{ days}\)

Total Work = \((15m + 25w) \times 9.6\)

Finding the Relationship between Man's and Woman's Work Rate

Since the total work is the same in both scenarios, we can equate the two expressions for total work:

\((15m + 25w) \times 9.6 = 432w\)

Let's simplify the equation:

\(15 \times 9.6 m + 25 \times 9.6 w = 432w\)

\(144m + 240w = 432w\)

Subtract \(240w\) from both sides to isolate the term with \(m\):

\(144m = 432w - 240w\)

\(144m = 192w\)

Now, we can find the ratio of \(m\) to \(w\) by dividing both sides by 144 and \(w\):

\(\frac{m}{w} = \frac{192}{144}\)

Simplifying the fraction \(\frac{192}{144}\) (by dividing both numerator and denominator by common factors like 48):

\(\frac{192 \div 48}{144 \div 48} = \frac{4}{3}\)

So, we have the relationship \(m = \frac{4}{3}w\). This means a man's work rate is 4/3 times a woman's work rate.

Calculating Time for 16 Men

We need to find the number of days it takes for 16 men to complete the same work. Let this be \(D\) days.

The total work done by 16 men in \(D\) days is:

Total Work = \(16 \text{ men} \times m \text{ (work per man per day)} \times D \text{ days}\)

Total Work = \(16mD\)

We know the Total Work is \(432w\) and we have the relationship \(m = \frac{4}{3}w\). Substitute these into the equation:

\(432w = 16 \times \left(\frac{4}{3}w\right) \times D\)

\(432w = \frac{64}{3}wD\)

Assuming \(w \neq 0\) (since work is being done), we can divide both sides by \(w\):

\(432 = \frac{64}{3}D\)

To find \(D\), multiply both sides by \(\frac{3}{64}\):

\(D = 432 \times \frac{3}{64}\)

\(D = \frac{432 \times 3}{64}\)

\(D = \frac{1296}{64}\)

Performing the division:

\(D = 20.25\)

So, 16 men can complete the work in 20.25 days.

Summary of Steps to Solve Work Problems

  • Identify the total work based on given information.
  • Use the total work to find the relationship between the efficiencies (work rates) of different types of workers (men and women in this case).
  • Use the derived efficiency relationship and the total work to calculate the time taken by the new group of workers.
Entity Quantity Time Total Work Rate Total Work
Men and Women 15 M + 25 W 9.6 days \(15m + 25w\) \((15m + 25w) \times 9.6\)
Women Only 16 W 27 days \(16w\) \(16w \times 27 = 432w\)
Men Only (Target) 16 M \(D\) days \(16m\) \(16m \times D\)

Equating Total Work: \((15m + 25w) \times 9.6 = 432w \implies 144m + 240w = 432w \implies 144m = 192w \implies m = \frac{192}{144}w = \frac{4}{3}w\)

Equating Total Work: \(16mD = 432w\)

Substitute \(m = \frac{4}{3}w\): \(16 \times \frac{4}{3}w \times D = 432w\)

\(\frac{64}{3}wD = 432w\)

\(D = 432 \times \frac{3}{64} = \frac{1296}{64} = 20.25\)

Final Answer Determination

The calculation shows that 16 men would take 20.25 days to complete the work.

Revision Table: Work and Time Concepts

Concept Explanation Formula
Work Rate Amount of work done by a person or group in a unit of time. Work Rate = Total Work / Time Taken
Total Work The entire task to be completed. It's often treated as 1 unit or a calculated value based on workers and time. Total Work = Work Rate $\times$ Time Taken
Efficiency Related to work rate; higher efficiency means higher work rate. Often compared between different types of workers (like men vs. women). Efficiency Ratio = Ratio of Work Rates
Men, Women, and Work Problems involving different genders or types of workers contributing to the same task, usually at different efficiencies. Total Work = (Combined Work Rate of Group) $\times$ Time Taken

Additional Information on Efficiency Problems

Problems involving men, women, and work often test your ability to manage multiple variables (the individual work rates) and set up simultaneous equations or ratio-based solutions. The key idea is that the 'total work' remains constant regardless of who does it or how long it takes them collectively.

Efficiency is inversely proportional to the time taken to complete the same work. If a man is more efficient than a woman (i.e., has a higher work rate \(m > w\)), he will take less time to complete the same amount of work individually compared to the woman.

In problems like this, finding the relationship between the efficiencies (like \(m = \frac{4}{3}w\)) is a crucial intermediate step. This relationship allows you to express all work rates in terms of a single variable, simplifying the calculation of the total work and the final required time.

Remember that units must be consistent. If work rate is per day, time should be in days. If work rate is per hour, time should be in hours, and so on.

Was this answer helpful?

Similar Questions

  1. Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?

  2. To do a certain work, A and B work on alternate days with B beginning the work on the first day. A alone can complete the same work in 24 days. If the work gets completed in  \(11 \frac{1}{3}\)  days, then B alone can complete  \(\rm \frac{7}{9}^{th}\)  part of the original work in:

  3. R, S and T can finish a work in 20, 15 and 10 days, respectively. R works on all days and S and T work on alternate days with T starting the work on the first day. In how many days is the work finished?

  4. A can do \(1 \over 3\) of a piece of work in 32 days, B can do \(37{1 \over 2}\)% of the same work in 24 days, while C can do 60% of the same work in 48 days. B and C together started and worked for x days. After x days, B left the work and A joined C and both completed the remaining work in (x + 8) days. If the ratio of the work done by (B + C) together to the work done by (A + C) together is 9 ∶ 11, then what fraction of the same work can be completed by C alone in 3.5x days?

  5. A group of college students had decided to complete a project in 10 days. As 2 students dropped out every day, the project got completed at the end of the 15th day. The number of students at the beginning of the project was:

  6. Aarif, Arun and Abraham can do a work in 12, 20 and 24 days, respectively. They all begin together. Arun leaves the work 3 days and Abraham 6 days before its completion. In how many days is the work finished?

  7. A,B and C can do a piece of work in 30 days, 40 days and 50 days, respectively. Beginning with A, if A, B and C do the work alternatively then in how many days will the work be finished?

  8. 15 men can complete a work in 25 days, and 25 women can complete the same work in 40 days. If all 15 men and 25 women work together, in how many days will the work get completed?

  9. Working 5 hours a day, A can complete a task in 8 days and working 6 hours a day, B can finish the same task in 10 days, working 8 hours a day, they can jointly complete the task in __________.

  10. A can do 20% of a job in 7 days and B can do 25% of the job in 7 days if they worked alone. How much of the job (in percentage) can they complete in 7 days if they worked together?


Important Questions from Work Efficiency

  1. Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?

  2. A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?

  3. 24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?

  4. A and B together can do a piece of work in 4 days, B and C can do it in 6 days, A and C can do it in 8 days. Then A, B and C together can do the same work in :-

  5. A can complete 50% of a work in 9 days and B can do 25% of the work in 9 days, if they work alone. If they work together then how much work (in percentage) can be completed in 6 days?

Need Expert Advice?
Upcoming Exams
SSC CGL
September 30, 2026
UPSSSC PET
October 23, 2026
Test Series
SSC CGL img
SSC
SSC CGL (Tier I + Tier II) 2026 Mock Test Series - Latest Pattern
2503 Tests 6 Tests Free
5392 Attempts
4.2(868)
English, Hindi

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App