A can do 20% of a job in 7 days and B can do 25% of the job in 7 days if they worked alone. How much of the job (in percentage) can they complete in 7 days if they worked together?
45%
This question asks us to determine the combined percentage of a job that two individuals, A and B, can complete in a specific time period (7 days), given the percentage of the job each can complete individually in the same time period.
We are given the following information:
The question specifically asks how much of the job they can complete together in 7 days. Since the time period is the same for both individuals and for the combined work, we can simply add the percentages of the job they complete individually within that time frame.
To find the total percentage of the job they complete together in 7 days, we add the percentage of work A does in 7 days and the percentage of work B does in 7 days.
Combined work in 7 days = Work done by A in 7 days + Work done by B in 7 days
Combined work in 7 days = $$20\% + 25\%$$
Combined work in 7 days = $$45\%$$
Therefore, if A and B work together, they can complete 45% of the job in 7 days.
Here is a quick summary:
The percentage of the job they can complete together in 7 days is 45%.
| Concept | Explanation | Formula (Example: A does work in D days) |
|---|---|---|
| Work Rate | The amount of work done per unit of time. | If A completes $$1$$ job in $$D$$ days, A's daily work rate is $$\frac{1}{D}$$ job per day. |
| Total Work | Usually considered as 1 unit or 100%. | Work = Rate × Time |
| Combined Work Rate | Sum of individual work rates. | If A's rate is $$R_A$$ and B's rate is $$R_B$$, combined rate is $$R_A + R_B$$. |
| Time to Complete Together | Time taken by individuals working together to complete the total work. | Time = $$\frac{\text{Total Work}}{\text{Combined Rate}}$$ |
Work and time problems often involve calculating the time taken to complete a task based on individual work rates. The fundamental principle is that the total work done is the product of the work rate and the time spent working. Work rates are usually expressed as the fraction or percentage of work done per unit of time (e.g., per day, per hour).
In this specific problem, since the time period (7 days) was fixed and the same for individual and combined work, we could directly add the percentages of work completed. If the question had asked for the time taken to complete the *entire* job (100%) together, we would first calculate their daily work rates from the given information and then use the combined daily rate to find the total time.
Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?
To do a certain work, A and B work on alternate days with B beginning the work on the first day. A alone can complete the same work in 24 days. If the work gets completed in \(11 \frac{1}{3}\) days, then B alone can complete \(\rm \frac{7}{9}^{th}\) part of the original work in:
15 men and 25 women can complete a piece of work in 9.6 days. If 16 women can complete the same work in 27 days, find the number of days in which 16 men can complete the same work.
R, S and T can finish a work in 20, 15 and 10 days, respectively. R works on all days and S and T work on alternate days with T starting the work on the first day. In how many days is the work finished?
A can do \(1 \over 3\) of a piece of work in 32 days, B can do \(37{1 \over 2}\)% of the same work in 24 days, while C can do 60% of the same work in 48 days. B and C together started and worked for x days. After x days, B left the work and A joined C and both completed the remaining work in (x + 8) days. If the ratio of the work done by (B + C) together to the work done by (A + C) together is 9 ∶ 11, then what fraction of the same work can be completed by C alone in 3.5x days?
A group of college students had decided to complete a project in 10 days. As 2 students dropped out every day, the project got completed at the end of the 15th day. The number of students at the beginning of the project was:
Aarif, Arun and Abraham can do a work in 12, 20 and 24 days, respectively. They all begin together. Arun leaves the work 3 days and Abraham 6 days before its completion. In how many days is the work finished?
A,B and C can do a piece of work in 30 days, 40 days and 50 days, respectively. Beginning with A, if A, B and C do the work alternatively then in how many days will the work be finished?
15 men can complete a work in 25 days, and 25 women can complete the same work in 40 days. If all 15 men and 25 women work together, in how many days will the work get completed?
Working 5 hours a day, A can complete a task in 8 days and working 6 hours a day, B can finish the same task in 10 days, working 8 hours a day, they can jointly complete the task in __________.
Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?
A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?
24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?
A and B together can do a piece of work in 4 days, B and C can do it in 6 days, A and C can do it in 8 days. Then A, B and C together can do the same work in :-
A can complete 50% of a work in 9 days and B can do 25% of the work in 9 days, if they work alone. If they work together then how much work (in percentage) can be completed in 6 days?