A man can do a piece of work in 30 hours. If he works with his son then the same piece of work is finished in 20 hours. If the son works alone, he can do the work in:
60 hours
This problem involves the concept of work and time. The fundamental idea is that the rate at which work is done is inversely proportional to the time taken. If a person takes \( T \) hours to complete a piece of work, their work rate is \( \frac{1}{T} \) of the work per hour.
When two people work together, their individual work rates add up to form the combined work rate. Let's denote the time taken by the son alone to be \( x \) hours. Therefore, the son's work rate is \( \frac{1}{x} \) work per hour.
The combined work rate of the man and his son is the sum of the man's work rate and the son's work rate:
Man's Rate + Son's Rate = Combined Rate
\( \frac{1}{30} + \frac{1}{x} = \frac{1}{20} \)
Now, we need to solve this equation for \( x \), which represents the time the son takes to complete the work alone.
Subtract \( \frac{1}{30} \) from both sides of the equation:
\( \frac{1}{x} = \frac{1}{20} - \frac{1}{30} \)
To subtract the fractions on the right side, we find a common denominator. The least common multiple (LCM) of 20 and 30 is 60.
\( \frac{1}{x} = \frac{3}{60} - \frac{2}{60} \)
Now, subtract the numerators:
\( \frac{1}{x} = \frac{3 - 2}{60} \)
\( \frac{1}{x} = \frac{1}{60} \)
To find \( x \), we take the reciprocal of both sides:
\( x = 60 \)
So, the son can do the work alone in 60 hours.
| Entity | Time Taken (hours) | Work Rate (work per hour) |
|---|---|---|
| Man | 30 | \( \frac{1}{30} \) |
| Man and Son (Together) | 20 | \( \frac{1}{20} \) |
| Son (Alone) | \( x \) | \( \frac{1}{x} \) |
Equation: \( \frac{1}{30} + \frac{1}{x} = \frac{1}{20} \)
Solving for \( x \): \( x = 60 \)
The son working alone can do the work in 60 hours.
| Concept | Explanation | Formula |
|---|---|---|
| Work Rate | The amount of work done per unit of time. | Work Rate = \( \frac{1}{\text{Time Taken}} \) |
| Total Work | Considered as 1 unit (or 100%). | Total Work = Rate \( \times \) Time |
| Combined Rate | Sum of individual rates when people work together. | \( R_{total} = R_1 + R_2 + ... \) |
Time and work problems often involve calculating how long it takes for individuals or groups to complete a task, either alone or together. The key is to convert the time taken into a work rate. The work rate represents the fraction of the total work completed in one unit of time (e.g., per hour, per day).
Here are some common variations and tips:
Always ensure that the time units are consistent throughout the problem (e.g., all in hours or all in days).
Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?
To do a certain work, A and B work on alternate days with B beginning the work on the first day. A alone can complete the same work in 24 days. If the work gets completed in \(11 \frac{1}{3}\) days, then B alone can complete \(\rm \frac{7}{9}^{th}\) part of the original work in:
Two men and 7 women can complete a work in 28 days whereas 6 men and 16 women can do the same work in 11 days. In how many days can 7 men complete the same work?
4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 25 women complete it?
Raju and Rajat working together take 5 days to complete a piece of work. If Raju alone can do this work in 7 days, how long would Rajat take to complete the same work?
If Mohit can complete \(\frac{2}{3}\)rd of a work in 24 days, then in how many days can \(\rm\frac{1}{9}^{th}\) of the work be complete by him?
A is 50% more efficient then B. B worked to finish the same work in 20 days. If A and B worked together, then how much time will they take to finish the same work?
20 women and 15 men together can complete a work in 6 days. It takes 150 days for a single woman to complete the work. In how many days can a single man complete the work?
A worker completes \(\frac{3}{5}\) of a work in 12 days. In how many days will he complete \(\frac{3}{4}\) of the work?
A can complete a piece of work in 25 days while B can complete the same work in 30 days. They work on alternate basis, starting with A. Both A and B follow this pattern for 5 days and then A leaves the work. In how many days will B finish the remaining work?
Sumi can complete a job working 5 hours per day in 2 days. If she doubles her working hours per day, then in how many days will she complete the work?
Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?
A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?
24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?
3 men working 7 hours a day can complete a piece of work in 45 days. In how many days will 9 men working 6 hours a day complete the same work?