All Exams Test series for 1 year @ ₹349 only
Question

A can complete a piece of work in 25 days while B can complete the same work in 30 days. They work on alternate basis, starting with A. Both A and B follow this pattern for 5 days and then A leaves the work. In how many days will B finish the remaining work?

This question was previously asked in
SSC CGL 2023 (Tier-II) Paper 1 Previous Year Paper (26-Oct-2023) (Shift-1)
The correct answer is \(24 \frac{2}{5}\)

Understanding the Work and Time Problem

This problem involves calculating the time taken to complete a piece of work when two individuals, A and B, work together under specific conditions. A and B have different efficiencies, work on alternate days initially, and then one leaves, leaving the other to finish the remaining task. We need to find how long B takes to finish the remaining work alone.

Calculating Individual Work Rates (Efficiency)

The efficiency of a person in completing work is usually measured as the fraction of work done per day.

  • A can complete the work in 25 days.
  • A's daily work rate = $\frac{1}{25}$ of the work per day.
  • B can complete the same work in 30 days.
  • B's daily work rate = $\frac{1}{30}$ of the work per day.

Work Done in the First 5 Days (Alternate Basis)

A and B work on alternate days, starting with A, for 5 days. Let's calculate the work done each day:

  • Day 1: A works. Work done = $\frac{1}{25}$
  • Day 2: B works. Work done = $\frac{1}{30}$
  • Day 3: A works. Work done = $\frac{1}{25}$
  • Day 4: B works. Work done = $\frac{1}{30}$
  • Day 5: A works. Work done = $\frac{1}{25}$

Total work done in 5 days is the sum of the work done on each of these days.

Total work in 5 days = (Work by A on Day 1, 3, 5) + (Work by B on Day 2, 4)

Work done by A in 3 days = $3 \times \frac{1}{25} = \frac{3}{25}$

Work done by B in 2 days = $2 \times \frac{1}{30} = \frac{2}{30} = \frac{1}{15}$

Total work done in the first 5 days = $\frac{3}{25} + \frac{1}{15}$

To add these fractions, we find a common denominator, which is the Least Common Multiple (LCM) of 25 and 15. LCM(25, 15) = 75.

  • $\frac{3}{25} = \frac{3 \times 3}{25 \times 3} = \frac{9}{75}$
  • $\frac{1}{15} = \frac{1 \times 5}{15 \times 5} = \frac{5}{75}$

Total work done in 5 days = $\frac{9}{75} + \frac{5}{75} = \frac{14}{75}$

Calculating the Remaining Work

The total work is considered as 1 unit. The work remaining after the first 5 days is calculated by subtracting the work done from the total work.

Remaining work = Total work - Work done in 5 days

Remaining work = $1 - \frac{14}{75} = \frac{75}{75} - \frac{14}{75} = \frac{61}{75}$

Time Taken by B to Finish the Remaining Work

After 5 days, A leaves the work. B has to finish the remaining work alone. We know B's daily work rate is $\frac{1}{30}$ of the work.

Time taken by B to finish the remaining work = $\frac{\text{Remaining Work}}{\text{B's daily work rate}}$

Time taken by B = $\frac{61/75}{1/30}$

This can be calculated as:

Time taken by B = $\frac{61}{75} \times 30$

We can simplify the calculation by dividing 75 and 30 by their common factor, 15.

$\frac{61}{75} \times 30 = \frac{61}{5 \times 15} \times (2 \times 15) = \frac{61 \times 2}{5} = \frac{122}{5}$

Now, we convert the improper fraction $\frac{122}{5}$ into a mixed number. Divide 122 by 5:

$122 \div 5$

$122 = 5 \times 24 + 2$

So, $\frac{122}{5} = 24 \frac{2}{5}$

Therefore, B will take $24 \frac{2}{5}$ days to finish the remaining work.

Revision Table: Work and Time Calculations

Worker Time to complete work Daily work rate
A 25 days $\frac{1}{25}$
B 30 days $\frac{1}{30}$

Activity Duration Work Done
A works (Days 1, 3, 5) 3 days $3 \times \frac{1}{25} = \frac{3}{25}$
B works (Days 2, 4) 2 days $2 \times \frac{1}{30} = \frac{1}{15}$
Total work in first 5 days 5 days $\frac{3}{25} + \frac{1}{15} = \frac{14}{75}$
Remaining Work - $1 - \frac{14}{75} = \frac{61}{75}$
Time for B to finish remaining work ? $\frac{61/75}{1/30} = 24 \frac{2}{5}$ days

Additional Information on Work and Time Problems

Work and time problems are common in quantitative aptitude sections of various exams. Key concepts include:

  • Work Rate: If a person can do a piece of work in 'n' days, their work rate is $\frac{1}{n}$ work per day.
  • Total Work: Often considered as 1 unit or the LCM of the individual times to make calculations with whole numbers easier.
  • Work Done: Work done = Work Rate $\times$ Time.
  • Combined Work Rate: If two people A and B work together, their combined work rate is the sum of their individual work rates (A's rate + B's rate).
  • Alternate Work: When individuals work on alternate days, calculate the work done over a cycle (usually 2 days if two people work) and see how many such cycles fit into the given time, or how many cycles are needed to complete the work.
  • Remaining Work: Calculated as Total Work - Work Done. The person or persons finishing the remaining work will take time based on their work rate(s).

Understanding these basic principles helps in solving various types of work and time problems efficiently.

Was this answer helpful?

Similar Questions

  1. Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?

  2. A man can do a piece of work in 30 hours. If he works with his son then the same piece of work is finished in 20 hours. If the son works alone, he can do the work in:

  3. To do a certain work, A and B work on alternate days with B beginning the work on the first day. A alone can complete the same work in 24 days. If the work gets completed in  \(11 \frac{1}{3}\)  days, then B alone can complete  \(\rm \frac{7}{9}^{th}\)  part of the original work in:

  4. Two men and 7 women can complete a work in 28 days whereas 6 men and 16 women can do the same work in 11 days. In how many days can 7 men complete the same work?

  5. 4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 25 women complete it?

  6. Raju and Rajat working together take 5 days to complete a piece of work. If Raju alone can do this work in 7 days, how long would Rajat take to complete the same work?

  7. If Mohit can complete \(\frac{2}{3}\)rd of a work in 24 days, then in how many days can \(\rm\frac{1}{9}^{th}\) of the work be complete by him?

  8. A is 50% more efficient then B. B worked to finish the same work in 20 days. If A and B worked together, then how much time will they take to finish the same work?

  9. 20 women and 15 men together can complete a work in 6 days. It takes 150 days for a single woman to complete the work. In how many days can a single man complete the work?

  10. A worker completes \(\frac{3}{5}\) of a work in 12 days. In how many days will he complete \(\frac{3}{4}\) of the work? 


Important Questions from Work Efficiency

  1. Sumi can complete a job working 5 hours per day in 2 days. If she doubles her working hours per day, then in how many days will she complete the work?

  2. Five men and 2 boys can do in 30 days as much work as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?

  3. A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work further increased by 50%?

  4. 24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?

  5. 3 men working 7 hours a day can complete a piece of work in 45 days. In how many days will 9 men working 6 hours a day complete the same work?

Need Expert Advice?
Upcoming Exams
SSC JHT
September 08, 2026
SSC Stenographer
September 09, 2026
SSC Selection Post
September 16, 2026
Test Series
SSC CGL img
SSC
SSC CGL (Tier I + Tier II) 2026 Mock Test Series - Latest Pattern
2501 Tests 6 Tests Free
4138 Attempts
4.2(839)
English, Hindi

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App