A can do a piece of work in 20 days and B in 30 days. They work together for 5 days. How much work is left?
\(\frac{7}{12}\)
The rate of work is the fraction of the job completed in one day, found as the reciprocal of the number of days each person needs alone.
A's one-day work \(= \frac{1}{20}\) and B's one-day work \(= \frac{1}{30}\).
Working together, their one-day work \(= \frac{1}{20} + \frac{1}{30} = \frac{3+2}{60} = \frac{5}{60} = \frac{1}{12}\).
In 5 days they complete \(5 \times \frac{1}{12} = \frac{5}{12}\) of the whole work.
Work left \(= 1 - \frac{5}{12} = \frac{12-5}{12} = \frac{7}{12}\).
Key concept: combined rates of workers add up, and remaining work equals the whole (taken as 1) minus the work already done.
Hence the fraction of work still left is 7/12.
P and Q working alone can complete a work in 9 days and 18 days respectively. They work on alternate days one at a time. P works on the first day. In how many days the whole work will be completed?
P, Q and R working alone can complete a work in 24, 30 and 40 days respectively. All three of them started the work together but after 8 days P left the work. Q left the work 6 days before the work was completed. R completed the remaining work alone. In how many days was the total work completed?
A does 60% of the work in 18 days. He then calls in B, and they together finish the remaining work in 4 days. How long would B alone take to do the whole work?
If 8 men can do a piece of work in 14 days, the time taken by 12 men to do the same piece of work will be:
A and B together can do a job in 6 days. A alone does it in 9 days. In how many days can B alone do it?
A can do a job in 10 days and B in 12 days. They work on alternate days starting with A. In how many days will the job be finished?
A can do a work in 18 days, B in 27 days. They start together, but after 6 days A leaves. In how many more days will B finish the remaining work?
Aditya is twice as good a workman as Bipin and therefore can finish a job in 30 days less than Bipin. How many days are required to complete the job if working together?
Given ,6 men and 8 boys can complete the task in 10 days, and 26 men and 48 boys can finish it in just 2 days, how long will it take for 15 men and 20 boys to do the same work?
A can complete a task in 10 days and, B can finish a task in 15 days, respectively. A starts the work and works for 4 days, after which B joins A. How many more days will they take to complete the task?
Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?
A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?
Had been one menless, then the number of days required to do a piece of work would have been one more. If the number of Man. Days required to complete the work is 56, how many workers were there?
A can do a piece of work in 16 hours, B and C can do it in 8 hours while A and C can do it 12 hours. How long will B alone take to do it?