A can do a job in 10 days and B in 12 days. They work on alternate days starting with A. In how many days will the job be finished?
\(10\frac{5}{6}\) days
In alternate-day work we track how much of the job is done in each two-day cycle, then handle the leftover on the next turn.
A finishes the job in 10 days, so A does \(\dfrac{1}{10}\) per day; B finishes in 12 days, so B does \(\dfrac{1}{12}\) per day.
One cycle is A on day 1 and B on day 2, together \(\dfrac{1}{10} + \dfrac{1}{12} = \dfrac{6+5}{60} = \dfrac{11}{60}\) of the work.
After 5 full cycles (10 days) the work done is \(5\times \dfrac{11}{60} = \dfrac{55}{60}\).
The work still left is \(1 - \dfrac{55}{60} = \dfrac{5}{60} = \dfrac{1}{12}\).
Day 11 is A's turn again, and A's rate is \(\dfrac{1}{10}\) per day, so the time to clear the remainder is \(\dfrac{1/12}{1/10} = \dfrac{10}{12} = \dfrac{5}{6}\) day.
Adding this to the 10 days already spent gives \(10 + \dfrac{5}{6} = 10\tfrac{5}{6}\) days.
The job is finished in 10 5/6 days.
P and Q working alone can complete a work in 9 days and 18 days respectively. They work on alternate days one at a time. P works on the first day. In how many days the whole work will be completed?
P, Q and R working alone can complete a work in 24, 30 and 40 days respectively. All three of them started the work together but after 8 days P left the work. Q left the work 6 days before the work was completed. R completed the remaining work alone. In how many days was the total work completed?
A does 60% of the work in 18 days. He then calls in B, and they together finish the remaining work in 4 days. How long would B alone take to do the whole work?
If 8 men can do a piece of work in 14 days, the time taken by 12 men to do the same piece of work will be:
A and B together can do a job in 6 days. A alone does it in 9 days. In how many days can B alone do it?
Aditya is twice as good a workman as Bipin and therefore can finish a job in 30 days less than Bipin. How many days are required to complete the job if working together?
A can do a piece of work in 20 days and B in 30 days. They work together for 5 days. How much work is left?
A alone can do a work in 20 days, B alone in 30 days. They work together for 6 days, then A leaves. How many more days will B take to finish the remaining work?
A can do a work in 18 days, B in 27 days. They start together, but after 6 days A leaves. In how many more days will B finish the remaining work?
Given ,6 men and 8 boys can complete the task in 10 days, and 26 men and 48 boys can finish it in just 2 days, how long will it take for 15 men and 20 boys to do the same work?
Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?
A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?
Had been one menless, then the number of days required to do a piece of work would have been one more. If the number of Man. Days required to complete the work is 56, how many workers were there?
A can do a piece of work in 16 hours, B and C can do it in 8 hours while A and C can do it 12 hours. How long will B alone take to do it?