Amit can finish the work in 15 days, and Baban can finish the same work in 25 days. They work together for 5 days. The rest of the work was finished by Amit and Chetan in 4 days. How much time is required for Chetan to finish this work?
20 days
One day's work = 1 ÷ (days to finish). Work done in t days = t × combined one day's work.
Amit + Baban in 5 days = \(5\left(\frac{1}{15} + \frac{1}{25}\right) = 5 \times \frac{8}{75} = \frac{8}{15}\)
Remaining work = \(1 - \frac{8}{15} = \frac{7}{15}\)
Amit + Chetan per day = \(\frac{7}{15} \div 4 = \frac{7}{60}\)
Chetan per day = \(\frac{7}{60} - \frac{1}{15} = \frac{7 - 4}{60} = \frac{1}{20}\)
Chetan alone = 20 days
Check (total work 75 units): Amit 5, Baban 3 per day; 5 days give 40 units; 35 units left in 4 days = 8.75 per day, so Chetan = 3.75 per day and 75 ÷ 3.75 = 20 days.
Hence, 20 days.
P and Q working alone can complete a work in 9 days and 18 days respectively. They work on alternate days one at a time. P works on the first day. In how many days the whole work will be completed?
Aditya is twice as good a workman as Bipin and therefore can finish a job in 30 days less than Bipin. How many days are required to complete the job if working together?
A can do a job in 10 days and B in 12 days. They work on alternate days starting with A. In how many days will the job be finished?
Given ,6 men and 8 boys can complete the task in 10 days, and 26 men and 48 boys can finish it in just 2 days, how long will it take for 15 men and 20 boys to do the same work?
A and B together do a piece of work in 10 days. B alone does it in 15 days. How long will A take alone?
A does 60% of the work in 18 days. He then calls in B, and they together finish the remaining work in 4 days. How long would B alone take to do the whole work?
A can complete a work in 8 days, while B can do it in 16 days. How many days will they take together?
If 8 men can do a piece of work in 14 days, the time taken by 12 men to do the same piece of work will be:
A construction project was estimated to be completed in 180 days. Due to rain, only 60% of the days were productive. If the work done each productive day is constant, by what percent must daily output be increased to complete the project on time?
A can complete the work in 12 days, B in 15 days, and C in 20 days.
They work in the following manner:
• On the first day A works,
• On the second day, B works,
• On the third day, C works, The cycle repeats in the same order.
In how many days will the work be completed?