Question

A works thrice as fast as B. If B can complete a work in 256 days independently, then find the number of days in which A and B can together
finish the work.

The correct answer is
64

Work and Time: Calculating Combined Effort

This solution explains how to find the time taken for two individuals, A and B, to complete a work together, given their relative speeds and one individual's completion time.

Step 1: Understanding Relative Speeds

We are given that A works thrice as fast as B. This means the ratio of their work rates (speed) is:

$ \frac{\text{Speed}_A}{\text{Speed}_B} = \frac{3}{1} $

This implies that for every unit of work B does, A does 3 units of work in the same amount of time.

Step 2: Calculating Individual Work Rates

B completes the work in 256 days independently.

The amount of work B does in 1 day is:

$ \text{Work Rate}_B = \frac{1}{256} \text{ of the total work} $

Since A works 3 times as fast as B, A's work rate is 3 times B's work rate.

$ \text{Work Rate}_A = 3 \times \text{Work Rate}_B = 3 \times \frac{1}{256} = \frac{3}{256} \text{ of the total work per day} $

Step 3: Calculating Combined Work Rate

When A and B work together, their work rates add up to find their combined rate.

$ \text{Combined Rate} = \text{Work Rate}_A + \text{Work Rate}_B $

$ \text{Combined Rate} = \frac{3}{256} + \frac{1}{256} = \frac{4}{256} $

Simplifying the fraction gives the combined rate:

$ \text{Combined Rate} = \frac{1}{64} \text{ of the total work per day} $

Step 4: Calculating Combined Time

The total time taken to complete the work together is the reciprocal of the combined work rate.

$ \text{Time taken together} = \frac{1}{\text{Combined Rate}} = \frac{1}{\frac{1}{64}} $

$ \text{Time taken together} = 64 \text{ days} $

Final Answer

Therefore, A and B can together finish the work in 64 days.

Was this answer helpful?

Important Questions from Time and Work

  1. A can finish a job in 146 days, B can finish the same job in 219 days and C can finish the same job in 292 days. If all three are working together, how many days will they require to complete the same job?
  2. X can finish a work in 153 days, Y can finish a work in 255 and Z can finish the same piece of work 340 days. How many days will they require to complete the work, if X, Y and Z are working together?
  3. A finish a work in 1170 days and B can do the same work in 2340 days. Working together, they will complete the same work in how many days?
  4. A can finish a job in 102 days, B can finish the same job in 153 days and C can finish the same job in 204 days. If all three are working together, how many days will they require to complete the same job?
  5. M is thrice as efficient as workman as N and therefore is able to finish a job in 242 days less than N. Then N can finish the entire work in how many days?
Need Expert Advice?

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App