This problem involves calculating the time taken by an individual (Baban) to complete a work, given information about the combined work rates of multiple people.
Let the rates of work for Athar, Baban, and Chetan be $R_A$, $R_B$, and $R_C$ respectively. The rate signifies the fraction of the work completed per day.
We have a system of three equations. Substitute the value of $R_C$ from the third equation into the first equation:
$ R_A = R_B + \frac{1}{50} $Now substitute this expression for $R_A$ into the second equation:
$ \left( R_B + \frac{1}{50} \right) + R_B = \frac{1}{10} $Simplify and solve for $R_B$:
$ 2 R_B + \frac{1}{50} = \frac{1}{10} $ $ 2 R_B = \frac{1}{10} - \frac{1}{50} $Find a common denominator (50) for the subtraction:
$ 2 R_B = \frac{5}{50} - \frac{1}{50} $ $ 2 R_B = \frac{4}{50} $ $ 2 R_B = \frac{2}{25} $ $ R_B = \frac{1}{25} $Baban's rate of work is $\frac{1}{25}$ of the work per day. The time taken by Baban alone is the reciprocal of his rate:
$ \text{Time for Baban} = \frac{1}{R_B} = \frac{1}{1/25} = 25 \text{ days} $A alone can complete a job in 12 days and B alone in 18 days. A and B agree to do the work for ₹7,200. With C's help they finish it in 5 days. How much should C be paid?
A and B can complete a task together in 12 days, while B and C can finish it in 16 days. After A works on it for 5 days and B for 7 days, C takes the remaining 13 days to finish the work. How many days would it take for C to complete the work alone?
A is three times more efficient as a worker than B, which allows A to complete a job in 60 days less than B. If they work together, they can finish the job in:
A, B, and C can complete a certain task in 20, 30, and 60 days respectively. How many days will it take for A to finish the work if he receives help from B and C every third day?
A and B can complete a certain task together in 30 days. After A works for 16 days, B is left to finish the remaining work by himself in 44 days. How many days would it take for B to complete the entire task on his own?
A and B can complete a task in 12 days and 18 days, respectively. They begin the work together, but B leaves after 4 days. How many more days will A take to finish the remaining work?
The ratio of the time taken by A and B to complete a task is 3 : 2. If B can complete the task alone in 18 hours, how many hours will they take to complete the task if they work together?
Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?
A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?
Had been one menless, then the number of days required to do a piece of work would have been one more. If the number of Man. Days required to complete the work is 56, how many workers were there?
A can do a piece of work in 16 hours, B and C can do it in 8 hours while A and C can do it 12 hours. How long will B alone take to do it?