Question

6 women and 4 men can complete a work in 10 days, while 4 women and 5 men complete it in 10 days. In how many days will 8 women complete it?

This question was previously asked in
SSC CGL 2025 Tier 2 Paper 1 Question Paper (19-Jan-2026)
The correct answer is
17.5 days

Work and Time Problem: Calculation Steps

This problem involves calculating the time required for a specific group to complete a work based on the combined efforts of men and women.

Setting Up Work Rate Equations

Let $W$ represent the work rate of one woman (amount of work done per day) and $M$ represent the work rate of one man.

The total work is assumed to be 1 unit. The formula used is Work = Rate × Time.

  • From the first condition: 6 women and 4 men complete the work in 10 days. $ (6W + 4M) \times 10 = 1 $ $ 60W + 40M = 1 \quad \quad (1) $
  • From the second condition: 4 women and 5 men complete the work in 10 days. $ (4W + 5M) \times 10 = 1 $ $ 40W + 50M = 1 \quad \quad (2) $

Solving for Individual Work Rates

We need to solve the system of linear equations (1) and (2) to find the values of $W$ and $M$.

  • Multiply equation (1) by 5 and equation (2) by 4 to make the coefficient of $M$ the same: $ 5 \times (60W + 40M = 1) \implies 300W + 200M = 5 \quad \quad (1') $ $ 4 \times (40W + 50M = 1) \implies 160W + 200M = 4 \quad \quad (2') $
  • Subtract equation (2') from equation (1'): $ (300W - 160W) + (200M - 200M) = 5 - 4 $ $ 140W = 1 $ $ W = \frac{1}{140} $ So, one woman completes $ \frac{1}{140} $ of the work per day.
  • Substitute the value of $W$ back into equation (1): $ 60 \left( \frac{1}{140} \right) + 40M = 1 $ $ \frac{60}{140} + 40M = 1 $ $ \frac{3}{7} + 40M = 1 $ $ 40M = 1 - \frac{3}{7} $ $ 40M = \frac{4}{7} $ $ M = \frac{4}{7 \times 40} $ $ M = \frac{1}{70} $ So, one man completes $ \frac{1}{70} $ of the work per day.

Calculating Time for 8 Women

Now, we need to find the time it takes for 8 women to complete the work.

  • Calculate the combined work rate of 8 women: $ \text{Rate of 8 women} = 8 \times W = 8 \times \frac{1}{140} = \frac{8}{140} = \frac{2}{35} $ The rate of 8 women is $ \frac{2}{35} $ of the work per day.
  • Calculate the time required using the formula Time = Work / Rate: $ \text{Time} = \frac{1}{\text{Rate of 8 women}} = \frac{1}{\frac{2}{35}} = \frac{35}{2} $ $ \text{Time} = 17.5 \text{ days} $

Therefore, 8 women will complete the work in 17.5 days.

Was this answer helpful?

Similar Questions

  1. A alone can complete a job in 12 days and B alone in 18 days. A and B agree to do the work for ₹7,200. With C's help they finish it in 5 days. How much should C be paid?

  2. A and B can complete a task together in 12 days, while B and C can finish it in 16 days. After A works on it for 5 days and B for 7 days, C takes the remaining 13 days to finish the work. How many days would it take for C to complete the work alone?

  3. Athar can do a certain work in the same time in which Baban and Chetan together can do it. If Athar and Baban together could do it in 10 days and Chetan alone in 50 days, then Baban alone could do it in:
  4. A is three times more efficient as a worker than B, which allows A to complete a job in 60 days less than B. If they work together, they can finish the job in:

  5. A, B, and C can complete a certain task in 20, 30, and 60 days respectively. How many days will it take for A to finish the work if he receives help from B and C every third day?

  6. A can complete a task in 15 days, and B can complete the same task in 20 days. How long will it take them to complete the task together?
  7. A and B can complete a certain task together in 30 days. After A works for 16 days, B is left to finish the remaining work by himself in 44 days. How many days would it take for B to complete the entire task on his own?

  8. A and B can complete a task in 12 days and 18 days, respectively. They begin the work together, but B leaves after 4 days. How many more days will A take to finish the remaining work?

  9. If 6 machines complete a task in 10 days, how many days for 15 machines at the same rate?

  10. The ratio of the time taken by A and B to complete a task is 3 : 2. If B can complete the task alone in 18 hours, how many hours will they take to complete the task if they work together?


Important Questions from Time and Work

  1. Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?

  2. A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?

  3. Had been one menless, then the number of days required to do a piece of work would have been one more. If the number of Man. Days required to complete the work is 56, how many workers were there?

  4. A can do a piece of work in 16 hours, B and C can do it in 8 hours while A and C can do it 12 hours. How long will B alone take to do it?

  5. lf 12 men can do a work in 20 days, in how many days will the work be done by 15 men-
Need Expert Advice?
Upcoming Exams
UPSSSC PET
October 25, 2026
SSC JE
November 02, 2026
SSC CPO
November 20, 2026
SSC CHSL
November 30, 2026
Test Series
SSC CGL img
SSC
SSC CGL (Tier I + Tier II) 2026 Mock Test Series - Latest Pattern
2503 Tests 6 Tests Free
8064 Attempts
4.2(913)
English, Hindi

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App