A and B together can complete a work in 12 days. B and C together can complete the same work in 15 days. C and A together can do it in 20 days. In how many days can A alone complete the job?
30 days
Step 1 – Pair rates:
\(\dfrac{1}{A} + \dfrac{1}{B} = \dfrac{1}{12},\ \dfrac{1}{B} + \dfrac{1}{C} = \dfrac{1}{15},\ \dfrac{1}{C} + \dfrac{1}{A} = \dfrac{1}{20}\).
Step 2 – Add all three:
\(2\!\left(\dfrac{1}{A}+\dfrac{1}{B}+\dfrac{1}{C}\right) = \dfrac{5+4+3}{60} = \dfrac{1}{5}\), so \(\dfrac{1}{A}+\dfrac{1}{B}+\dfrac{1}{C} = \dfrac{1}{10}\).
Step 3 – Isolate A: \(\dfrac{1}{A} = \dfrac{1}{10} - \dfrac{1}{15} = \dfrac{1}{30}\).
Hence, the correct answer is 30 days.
A and B can complete a task together in 12 days, while B and C can finish it in 16 days. After A works on it for 5 days and B for 7 days, C takes the remaining 13 days to finish the work. How many days would it take for C to complete the work alone?
A is three times more efficient as a worker than B, which allows A to complete a job in 60 days less than B. If they work together, they can finish the job in:
If 6 machines complete a task in 10 days, how many days for 15 machines at the same rate?
A can do a work in 8 days and B in 12 days. They work together for 3 days. What part of the work is left?
A, B, and C are capable of completing a job in 30, 45, and 90 days, respectively. A works every day, while B and C join A every fifth day. How long will it take to finish the task?
The ratio of the efficiencies of two workers, P and Q, is 5 : 2. If P can complete a project in 12 days, how many days will Q take to complete the same project alone?