This problem involves calculating the time required to complete the remaining work after changes in the number of workers and working hours.
The total amount of work can be measured in 'man-hours'. Initially, the plan was:
Total work = Number of men $\times$ Number of days $\times$ Hours per day
Total work = $15 \times 24 \times 8 = 2880$ man-hours.
The work was carried out for 6 days with the initial setup:
Work done = $15 \times 6 \times 8 = 720$ man-hours.
Subtract the work already done from the total work required:
Remaining work = Total work - Work done
Remaining work = $2880 - 720 = 2160$ man-hours.
After 6 days, the conditions changed:
Let the number of additional days required be $D$. The remaining work must be completed by the new workforce under the new conditions.
Remaining work = New number of men $\times$ Additional days ($D$) $\times$ New hours per day
$2160 = 20 \times D \times 6$
$2160 = 120 \times D$
$D = \frac{2160}{120}$
$D = 18$ days.
Therefore, 18 more days will be required to finish the remaining work.
A and B can complete a task together in 12 days, while B and C can finish it in 16 days. After A works on it for 5 days and B for 7 days, C takes the remaining 13 days to finish the work. How many days would it take for C to complete the work alone?
A is three times more efficient as a worker than B, which allows A to complete a job in 60 days less than B. If they work together, they can finish the job in:
A and B can finish a certain job in 28 and 35 days, respectively. They started working together, but A left after a while, and B managed to complete the remaining work in 17 days. How many days did A work before leaving?
If 6 machines complete a task in 10 days, how many days for 15 machines at the same rate?
A can do a work in 8 days and B in 12 days. They work together for 3 days. What part of the work is left?
Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?
A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?
Had been one menless, then the number of days required to do a piece of work would have been one more. If the number of Man. Days required to complete the work is 56, how many workers were there?
A can do a piece of work in 16 hours, B and C can do it in 8 hours while A and C can do it 12 hours. How long will B alone take to do it?