This problem involves calculating the time required to complete the remaining work after changes in the number of workers and working hours.
The total amount of work can be measured in 'man-hours'. Initially, the plan was:
Total work = Number of men $\times$ Number of days $\times$ Hours per day
Total work = $15 \times 24 \times 8 = 2880$ man-hours.
The work was carried out for 6 days with the initial setup:
Work done = $15 \times 6 \times 8 = 720$ man-hours.
Subtract the work already done from the total work required:
Remaining work = Total work - Work done
Remaining work = $2880 - 720 = 2160$ man-hours.
After 6 days, the conditions changed:
Let the number of additional days required be $D$. The remaining work must be completed by the new workforce under the new conditions.
Remaining work = New number of men $\times$ Additional days ($D$) $\times$ New hours per day
$2160 = 20 \times D \times 6$
$2160 = 120 \times D$
$D = \frac{2160}{120}$
$D = 18$ days.
Therefore, 18 more days will be required to finish the remaining work.
A and B can complete a task together in 12 days, while B and C can finish it in 16 days. After A works on it for 5 days and B for 7 days, C takes the remaining 13 days to finish the work. How many days would it take for C to complete the work alone?
A is three times more efficient as a worker than B, which allows A to complete a job in 60 days less than B. If they work together, they can finish the job in:
If 6 machines complete a task in 10 days, how many days for 15 machines at the same rate?
A can do a work in 8 days and B in 12 days. They work together for 3 days. What part of the work is left?
A and B together can complete a work in 12 days. B and C together can complete the same work in 15 days. C and A together can do it in 20 days. In how many days can A alone complete the job?
A, B, and C are capable of completing a job in 30, 45, and 90 days, respectively. A works every day, while B and C join A every fifth day. How long will it take to finish the task?
The ratio of the efficiencies of two workers, P and Q, is 5 : 2. If P can complete a project in 12 days, how many days will Q take to complete the same project alone?