All Exams Test series for 1 year @ ₹349 only
Question

A contractor employs 15 men to complete a work in 24 days, working 8 hours per day. After six days, he adds five more men but also reduces the working hours to six per day from the seventh day onwards. If all men work with the same efficiency throughout, how many more days will be required to finish the remaining work?

This question was previously asked in
SSC CGL 2025 Tier 2 Paper 1 Question Paper (19-Jan-2026)
The correct answer is
18

This problem involves calculating the time required to complete the remaining work after changes in the number of workers and working hours.

Calculate Total Work Required

The total amount of work can be measured in 'man-hours'. Initially, the plan was:

  • Number of men: 15
  • Number of days: 24
  • Hours per day: 8

Total work = Number of men $\times$ Number of days $\times$ Hours per day

Total work = $15 \times 24 \times 8 = 2880$ man-hours.

Calculate Work Done in Initial Phase

The work was carried out for 6 days with the initial setup:

  • Number of men: 15
  • Number of days worked: 6
  • Hours per day: 8

Work done = $15 \times 6 \times 8 = 720$ man-hours.

Calculate Remaining Work

Subtract the work already done from the total work required:

Remaining work = Total work - Work done

Remaining work = $2880 - 720 = 2160$ man-hours.

Calculate New Work Rate and Time Needed

After 6 days, the conditions changed:

  • New number of men = 15 + 5 = 20
  • New hours per day = 6

Let the number of additional days required be $D$. The remaining work must be completed by the new workforce under the new conditions.

Remaining work = New number of men $\times$ Additional days ($D$) $\times$ New hours per day

$2160 = 20 \times D \times 6$

$2160 = 120 \times D$

$D = \frac{2160}{120}$

$D = 18$ days.

Therefore, 18 more days will be required to finish the remaining work.

Was this answer helpful?

Similar Questions

  1. A and B can complete a task together in 12 days, while B and C can finish it in 16 days. After A works on it for 5 days and B for 7 days, C takes the remaining 13 days to finish the work. How many days would it take for C to complete the work alone?

  2. A is three times more efficient as a worker than B, which allows A to complete a job in 60 days less than B. If they work together, they can finish the job in:

  3. 6 women and 4 men can complete a work in 10 days, while 4 women and 5 men complete it in 10 days. In how many days will 8 women complete it?
  4. 20 men can do a piece of work in 45 days. Find the percentage amount of work done by 60 men in 6 days.
  5. Athar can do a certain work in the same time in which Baban and Chetan together can do it. If Athar and Baban together could do it in 10 days and Chetan alone in 50 days, then Baban alone could do it in:
  6. If 6 machines complete a task in 10 days, how many days for 15 machines at the same rate?

  7. A can do a work in 8 days and B in 12 days. They work together for 3 days. What part of the work is left?

  8. A and B together can complete a work in 12 days. B and C together can complete the same work in 15 days. C and A together can do it in 20 days. In how many days can A alone complete the job?

  9. A, B, and C are capable of completing a job in 30, 45, and 90 days, respectively. A works every day, while B and C join A every fifth day. How long will it take to finish the task?

  10. The ratio of the efficiencies of two workers, P and Q, is 5 : 2. If P can complete a project in 12 days, how many days will Q take to complete the same project alone?


Important Questions from Time and Work

  1. A works thrice as fast as B. If B can complete a work in 256 days independently, then find the number of days in which A and B can together
    finish the work.
  2. A can finish a job in 146 days, B can finish the same job in 219 days and C can finish the same job in 292 days. If all three are working together, how many days will they require to complete the same job?
  3. X can finish a work in 153 days, Y can finish a work in 255 and Z can finish the same piece of work 340 days. How many days will they require to complete the work, if X, Y and Z are working together?
  4. A finish a work in 1170 days and B can do the same work in 2340 days. Working together, they will complete the same work in how many days?
  5. A can finish a job in 102 days, B can finish the same job in 153 days and C can finish the same job in 204 days. If all three are working together, how many days will they require to complete the same job?
Need Expert Advice?
Upcoming Exams
SSC CHSL
November 30, 2026
SSC JE
November 30, 2026
Test Series
SSC CGL img
SSC
SSC CGL (Tier I + Tier II) 2026 Mock Test Series - Latest Pattern
2574 Tests 6 Tests Free
9196 Attempts
4.2(954)
English, Hindi
More Questions from SSC CGL

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App