All Exams Test series for 1 year @ ₹349 only
Question

A can do a work in 8 days and B in 12 days. They work together for 3 days. What part of the work is left?

This question was previously asked in
SSC CGL 2025 Tier 2 Paper 1 Question Paper (19-Jan-2026)
The correct answer is

\(\dfrac{3}{8}\)

Step 1 – Individual rates of work (per day):

\(\text{A's rate} = \dfrac{1}{8}, \quad \text{B's rate} = \dfrac{1}{12}\)

Step 2 – Combined rate per day:

\(\dfrac{1}{8} + \dfrac{1}{12} = \dfrac{3 + 2}{24} = \dfrac{5}{24}\)

Step 3 – Work completed in 3 days together:

\(3 \times \dfrac{5}{24} = \dfrac{15}{24} = \dfrac{5}{8}\)

Step 4 – Work remaining:

\(1 - \dfrac{5}{8} = \dfrac{3}{8}\)

Hence the part of work left is \(\dfrac{3}{8}\).

Was this answer helpful?

Similar Questions

  1. A and B can complete a task together in 12 days, while B and C can finish it in 16 days. After A works on it for 5 days and B for 7 days, C takes the remaining 13 days to finish the work. How many days would it take for C to complete the work alone?

  2. A alone can complete a job in 12 days and B alone in 18 days. A and B agree to do the work for ₹7,200. With C's help they finish it in 5 days. How much should C be paid?

  3. The ratio of the time taken by A and B to complete a task is 3 : 2. If B can complete the task alone in 18 hours, how many hours will they take to complete the task if they work together?

  4. A is three times more efficient as a worker than B, which allows A to complete a job in 60 days less than B. If they work together, they can finish the job in:

  5. A and B can complete a certain task together in 30 days. After A works for 16 days, B is left to finish the remaining work by himself in 44 days. How many days would it take for B to complete the entire task on his own?

  6. A, B, and C can complete a certain task in 20, 30, and 60 days respectively. How many days will it take for A to finish the work if he receives help from B and C every third day?

  7. If 6 machines complete a task in 10 days, how many days for 15 machines at the same rate?

  8. A and B can finish a certain job in 28 and 35 days, respectively. They started working together, but A left after a while, and B managed to complete the remaining work in 17 days. How many days did A work before leaving?

  9. A can lay railway track between two specified stations in 16 days, while B can complete the same task in 12 days. When C assists them, they manage to finish the job in just 4 days. How long would it take for C to complete the job on their own?

  10. A can build up a wall in 8 days while B can break it in 3 days. A has worked for 4 days and then B joined to work with A for another 2 days only. In how many days will A alone build up the remaining part of the wall?


Important Questions from Time and Work

  1. Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?

  2. A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?

  3. Had been one menless, then the number of days required to do a piece of work would have been one more. If the number of Man. Days required to complete the work is 56, how many workers were there?

  4. A can do a piece of work in 16 hours, B and C can do it in 8 hours while A and C can do it 12 hours. How long will B alone take to do it?

  5. lf 12 men can do a work in 20 days, in how many days will the work be done by 15 men-
Need Expert Advice?
Upcoming Exams
SSC Selection Post
September 16, 2026
Test Series
SSC CGL img
SSC
SSC CGL (Tier I + Tier II) 2026 Mock Test Series - Latest Pattern
2501 Tests 6 Tests Free
4426 Attempts
4.2(845)
English, Hindi

Start Your Preparation with Prepp Mobile App

Download the app from Google Play & App Store
Download the app from Google Play & App Store
Prepp Mobile App