A team of 24 workers is assigned to finish a task in 15 days. After working for 1 day, 8 workers quit. Assuming all workers are equally efficient, how many additional days will the remaining workers need to complete the rest of the task?
21 days
Total work required: \(24 \times 15 = 360\) worker-days.
Work done in the first day by all 24 workers: \(24 \times 1 = 24\) worker-days.
Remaining work: \(360 - 24 = 336\) worker-days.
Workers left after 8 quit: \(24 - 8 = 16\).
Additional days needed: \(\dfrac{336}{16} = 21\).
Hence, the remaining workers need 21 additional days.
Mohan can do a piece of work in 10 days and Sohan in 15 days. They started working together, but after 3 days Mohan left the work . What time will Sohan take to finish the work?
A tank is filled in 8 hours by three taps A, B and C. The tap C is thrice as fast as B and B is twice as fast as A. How much time will pipe B alone take to fill the tank?
Had been one menless, then the number of days required to do a piece of work would have been one more. If the number of Man. Days required to complete the work is 56, how many workers were there?
A can do a piece of work in 16 hours, B and C can do it in 8 hours while A and C can do it 12 hours. How long will B alone take to do it?