A team of 24 workers is assigned to finish a task in 15 days. After working for 1 day, 8 workers quit. Assuming all workers are equally efficient, how many additional days will the remaining workers need to complete the rest of the task?
21 days
Total work required: \(24 \times 15 = 360\) worker-days.
Work done in the first day by all 24 workers: \(24 \times 1 = 24\) worker-days.
Remaining work: \(360 - 24 = 336\) worker-days.
Workers left after 8 quit: \(24 - 8 = 16\).
Additional days needed: \(\dfrac{336}{16} = 21\).
Hence, the remaining workers need 21 additional days.